5523-5523 1/2 E YORK BLVD 90042
Certificate Information: 5523-5523 1/2 E YORK BLVD 90042
- Application / Permit
- 22014-10000-02199
- Plan Check / Job No.
- B22LA08487
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PRPOSED 2 ACCESSORY DWELLING UNITS (ADU), TOTAL AREA OF 1,040 SF. LID DEFERRAL.
- Permit Issued
- Issued on 9/30/2024
- Issuing Office
- Current Status
- CofO Issued on 12/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2022 | CRYSTEL MAALOUF |
| Corrections Issued | 6/29/2022 | CRYSTEL MAALOUF |
| Quality Review Completed | 7/11/2022 | GARO TELMI |
| Applicant returned to address corrections | 9/27/2022 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 12/7/2022 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 12/23/2022 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 1/17/2023 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 8/29/2023 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 9/1/2023 | CRYSTEL MAALOUF |
| Plan Check Approved | 10/3/2023 | CRYSTEL MAALOUF |
| Plan Check Approved | 10/16/2023 | CRYSTEL MAALOUF |
| Issued | 9/30/2024 | APPLICANT |
| CofO in Progress | 12/26/2025 | DAVID WILLIAMS |
| No Progress | 12/28/2025 | DEROLD HAUFF |
| CofO in Progress | 12/28/2025 | DEROLD HAUFF |
| Permit Finaled | 12/30/2025 | DEROLD HAUFF |
| CofO Issued | 12/30/2025 | DEROLD HAUFF |
| Permit Finaled | 12/30/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/3/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/6/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 9/6/2022 | JEANETTE VONG |
| Zoning Information File | Cleared | 8/2/2023 | CRYSTEL MAALOUF |
| Roof/Waste drainage to street | Cleared | 9/13/2023 | JESSICA OPINION |
| GPI Written Notices | Cleared | 10/3/2023 | CRYSTEL MAALOUF |
| Grading Pre-Inspection | Cleared | 10/3/2023 | CRYSTEL MAALOUF |
Contact Information
| Contractor | Bsm Llc; Lic. No.: 1081151-B | , |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 8232 GARVEY AVE 203 ROSEMEAD, CA 91770 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/13/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 11/20/2024 | Corrections Issued | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 11/22/2024 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 2/18/2025 | Not Ready for Inspection | CRAIG DAVIS |
| ELECTRICAL-Rough | 2/18/2025 | Corrections Issued | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2025 | Corrections Issued | CRAIG DAVIS |
| Green Building Rough | 2/18/2025 | Not Ready for Inspection | CRAIG DAVIS |
| HVAC-Rough | 2/18/2025 | Not Ready for Inspection | CRAIG DAVIS |
| PLUMBING-Rough | 2/18/2025 | Corrections Issued | CRAIG DAVIS |
| Verify Sprinkler Sign Off | 2/18/2025 | Not Ready for Inspection | CRAIG DAVIS |
| Deputy Wood Construction | 2/19/2025 | Conditional Approval | CRAIG DAVIS |
| BUILDING-Rough-Frame | 2/24/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 2/24/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2025 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 2/24/2025 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 2/24/2025 | Approved | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 2/24/2025 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 2/26/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 2/26/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2025 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 2/26/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 2/26/2025 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 2/26/2025 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 3/4/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 3/4/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Green Building Rough | 3/4/2025 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 3/4/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Underground Mechanical | 3/4/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Insulation | 3/5/2025 | Conditional Approval | JOSH MEISTER |
| Drywall Nailing | 3/10/2025 | Approved | DAVID WILLIAMS |
| Drywall Nailing | 3/20/2025 | Approved | REGINA MENDEZ |
| Shower Pan | 3/20/2025 | Approved | REGINA MENDEZ |
| Drywall Nailing | 3/26/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 3/26/2025 | Approved | REGINA MENDEZ |
| ELECTRICAL-Rough | 3/28/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Gas Test | 4/21/2025 | Approved | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 5/7/2025 | SGSOV Not Ready | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 5/15/2025 | Approved | DAVID WILLIAMS |
| ELECTRICAL-Final | 5/15/2025 | Approved | DAVID WILLIAMS |
| Final | 5/15/2025 | Corrections Issued | DAVID WILLIAMS |
| Footing/Foundation/Slab | 5/15/2025 | Approved | DAVID WILLIAMS |
| Green Building Final | 5/15/2025 | Approved | DAVID WILLIAMS |
| HVAC-Final | 5/15/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Final | 5/15/2025 | Approved | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 5/15/2025 | SGSOV Approved | DAVID WILLIAMS |
| Service/Power Release | 5/15/2025 | Approved | DAVID WILLIAMS |
| Smoke Detectors | 5/15/2025 | Approved | DAVID WILLIAMS |
| Final | 5/21/2025 | Corrections Issued | DAVID WILLIAMS |
| Final | 12/24/2025 | OK to Issue CofO | DAVID WILLIAMS |