1641 W 223RD ST 90501
Certificate Information: 1641 W 223RD ST 90501
- Application / Permit
- 22014-10000-02195
- Plan Check / Job No.
- B22LA08483
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: Single-story ground floor additions to (E) single-story SFD.
- Permit Issued
- Issued on 11/30/2022
- Issuing Office
- Current Status
- CofO Issued on 9/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2022 | KELVIN CHUONG |
| Corrections Issued | 6/10/2022 | KELVIN CHUONG |
| Quality Review Completed | 6/10/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 11/8/2022 | KELVIN CHUONG |
| Plan Check Approved | 11/17/2022 | KELVIN CHUONG |
| Issued | 11/30/2022 | APPLICANT |
| CofO in Progress | 9/25/2024 | EUGENE CASSIDY |
| Permit Finaled | 9/27/2024 | ANSON MAGLASANG |
| CofO Issued | 9/27/2024 | ANSON MAGLASANG |
| Permit Finaled | 9/27/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Sewer availability | Cleared | 8/10/2022 | ERIK BEASLEY |
| Low Impact Development | Cleared | 9/29/2022 | LONDY ALVARADO |
| Eng Process Fee Ord 176,300 | Cleared | 10/12/2022 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 10/17/2022 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Evangelista,, Gil Viernes; Lic. No.: S2422 | 749 N FEATHERWOOD DR DIAMOND BAR, CA 91765 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/13/2023 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 4/19/2023 | Corrections Issued | EUGENE CASSIDY |
| METHANE-Barrier | 4/19/2023 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 4/19/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 4/19/2023 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 6/5/2023 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2023 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2023 | Partial Approval | EUGENE CASSIDY |
| Interior/Exterior Lathing | 7/31/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Rough | 9/7/2023 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 9/7/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 9/7/2023 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 9/19/2023 | Partial Approval | EUGENE CASSIDY |
| Wood Frame | 9/19/2023 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 9/28/2023 | Approved | EUGENE CASSIDY |
| Green Building Rough | 10/17/2023 | Approved | EUGENE CASSIDY |
| Insulation | 10/17/2023 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 10/25/2023 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 10/25/2023 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 11/14/2023 | SGSOV Not Ready | EUGENE CASSIDY |
| Sewer | 11/14/2023 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 11/14/2023 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/4/2024 | Approved | EUGENE CASSIDY |
| Final | 4/4/2024 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 4/4/2024 | Approved | EUGENE CASSIDY |
| Green Building Final | 4/4/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Final | 4/4/2024 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 4/4/2024 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 4/4/2024 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 4/4/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 5/7/2024 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 5/7/2024 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 5/7/2024 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 5/7/2024 | Approved | EUGENE CASSIDY |
| Final | 9/4/2024 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Final | 9/24/2024 | Approved | EUGENE CASSIDY |
| Final | 9/24/2024 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 9/24/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 9/24/2024 | Approved | EUGENE CASSIDY |