4226 N STERN AVE 91423
Certificate Information: 4226 N STERN AVE 91423
- Application / Permit
- 22014-10000-02189
- Plan Check / Job No.
- B22LA08423
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2ND FLOOR ADDITION AND 1ST FLOOR REMODEL TO AN EXISTING 1 STORY SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 7/12/2022
- Issuing Office
- Current Status
- CofO Corrected on 5/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2022 | VU NGUYEN |
| Corrections Issued | 6/6/2022 | VU NGUYEN |
| Quality Review Completed | 6/9/2022 | EUGENE BARBEAU |
| Applicant returned to address corrections | 6/17/2022 | VU NGUYEN |
| Plan Check Approved | 7/12/2022 | VU NGUYEN |
| Issued | 7/12/2022 | APPLICANT |
| CofO in Progress | 5/10/2023 | MATTHEW NELSON |
| CofO Issued-Status Void | 5/11/2023 | MICHAEL SMITH |
| Permit Finaled-Status Void | 5/11/2023 | MICHAEL SMITH |
| Re-Activate Permit | 5/25/2023 | MICHAEL SMITH |
| Permit Finaled | 5/25/2023 | MICHAEL SMITH |
| CofO Corrected | 5/25/2023 | MICHAEL SMITH |
| Permit Finaled | 5/25/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/8/2022 | CHRIS CHAHBAZ |
| Sewer availability | Cleared | 6/8/2022 | CHRIS CHAHBAZ |
| Grading Pre-Inspection | Cleared | 6/14/2022 | KIRK LINKLATER |
| Low Impact Development | Cleared | 6/14/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 6/15/2022 | CHRIS CHAHBAZ |
| GPI Written Notices | Cleared | 7/12/2022 | VU NGUYEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mniarji,, Majd Sameer; Lic. No.: NA93049 | , |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/18/2022 | Conditional Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 10/21/2022 | Corrections Issued | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 10/27/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 11/15/2022 | Partial Approval | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 11/22/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 11/22/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 11/23/2022 | Approved | MISAEL ESPARZA |
| Deputy Wood Construction | 12/13/2022 | Conditional Approval | DAVID MATSON |
| Wood Frame | 12/14/2022 | Partial Approval | MISAEL ESPARZA |
| Deputy Wood Construction | 1/17/2023 | Conditional Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2023 | Corrections Issued | MISAEL ESPARZA |
| Wood Frame | 1/17/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2023 | Partial Approval | MISAEL ESPARZA |
| Wood Frame | 1/23/2023 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2023 | Approved | MISAEL ESPARZA |
| Wood Frame | 1/30/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Pre-Inspection | 2/10/2023 | Approved | MISAEL ESPARZA |
| Rough-Elec/Plmb/HVAC | 2/10/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/15/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 2/15/2023 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 2/15/2023 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 2/15/2023 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 2/22/2023 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/27/2023 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 2/27/2023 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 2/27/2023 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 3/2/2023 | Conditional Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 3/2/2023 | Conditional Approval | MISAEL ESPARZA |
| Insulation | 3/6/2023 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 3/15/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 3/15/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Pre-Inspection | 3/15/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 3/29/2023 | Approved | MISAEL ESPARZA |
| Shower Pan | 3/29/2023 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 4/3/2023 | SGSOV Not Ready | THOMAS FINNILA |
| BUILDING-Rough-Frame | 5/10/2023 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 5/10/2023 | Approved | MATTHEW NELSON |
| Final | 5/10/2023 | OK to Issue CofO | MATTHEW NELSON |
| HVAC-Final | 5/10/2023 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 5/10/2023 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 5/10/2023 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 5/10/2023 | Approved | MATTHEW NELSON |