5757 N MATILIJA AVE 91401
Certificate Information: 5757 N MATILIJA AVE 91401
- Application / Permit
- 22014-10000-02178
- Plan Check / Job No.
- B22LA08389
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PATIO COVER ADDITION TO EXISTING SINGLE FAMILY DWELLING PER WFPP
- Permit Issued
- Issued on 9/30/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/4/2022 | CRISTINA SALAZAR |
| Corrections Issued | 5/4/2022 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 6/17/2022 | RACHEL BEYENE |
| Plan Check Approved | 9/30/2022 | FERNANDO FLORES |
| Issued | 9/30/2022 | APPLICANT |
| CofO in Progress | 11/8/2022 | JENNIFER RABUCHIN |
| CofO Issued | 11/17/2022 | MICHAEL SMITH |
| Permit Finaled | 11/17/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/17/2022 | CHRISTOPHER ROCHA |
| Roof/Waste drainage to street | Cleared | 6/17/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 10/19/2022 | Partial Approval | JENNIFER RABUCHIN |
| Final | 10/19/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 10/19/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 10/19/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Green Building Rough | 10/19/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 10/19/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/2/2022 | Approved | JENNIFER RABUCHIN |
| Final | 11/2/2022 | OK to Issue CofO | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 11/2/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 11/2/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 11/2/2022 | Approved | JENNIFER RABUCHIN |