1260 N ANGELO DR 90077

Certificate Information: 1260 N ANGELO DR 90077

Application / Permit
22014-10000-02166
Plan Check / Job No.
B22LA08358
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Renovation and one-story addition (398 sq ft) to exisiting one-story single family dwelling. No change to attached garage and pool
Permit Issued
Issued on 6/2/2023
Issuing Office
Valley
Current Status
CofO Issued on 6/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/3/2022 APPLICANT
Assigned to Plan Check Engineer 5/19/2022 JAD BASMA
Corrections Issued 5/21/2022 JAD BASMA
Quality Review Completed 5/31/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 6/7/2022 APPLICANT
Applicant returned to address corrections 8/19/2022 JAD BASMA
Plan Check Approved 9/20/2022 JAD BASMA
Issued 6/2/2023 APPLICANT
CofO in Progress 6/7/2024 SEAN HAUPT
Permit Finaled 6/14/2024 DANIEL ORRANTE
CofO Issued 6/14/2024 DANIEL ORRANTE
Permit Finaled 6/14/2024 DANIEL ORRANTE

Permit Application Clearance Information

ZI Cleared 6/8/2022 KENTON TRINH
BHO/Hillside ordinance Cleared 6/13/2022 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 6/16/2022 SAUL GARCIA
BHO/Hillside ordinance Cleared 7/1/2022 SAUL GARCIA
BHO/Hillside ordinance Cleared 7/1/2022 SAUL GARCIA
BHO/Hillside ordinance Cleared 7/1/2022 SAUL GARCIA
Private sewage disp. approval Cleared 7/6/2022 KIRK LINKLATER
Sewer availability Cleared 7/6/2022 SAUL GARCIA
GPI Written Notices Cleared 8/19/2022 JAD BASMA
Hydrant and Access approval Cleared 8/22/2022 GILBERT URREA
Roof/Waste drainage to street Cleared 8/27/2022 SAUL GARCIA
BHO/Hillside ordinance Cleared 9/12/2022 SAUL GARCIA
Grading Pre-Inspection Cleared 9/20/2022 JAD BASMA

Contact Information

Contractor Zuma Canyon Construction Inc; Lic. No.: 644942-B 6428 BONSALL DRIVE      MALIBU, CA 90265
Engineer Sayah, Engineering; Lic. No.: S6000 15233 VENTURA BLVD   1130    SJERMAN OAKS,

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/7/2023 Corrections Issued BRENDAN LOONEY
Deputy Reinf. Concrete 7/10/2023 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 7/20/2023 Corrections Issued BRENDAN LOONEY
Footing/Foundation/Slab 7/24/2023 Approved BRENDAN LOONEY
Deputy Reinf. Concrete 7/26/2023 Conditional Approval MICHAEL PELHAM
PLUMBING-Rough 8/2/2023 Corrections Issued BRENDAN LOONEY
Deputy Drilled-In Anchors 8/3/2023 Conditional Approval BRENDAN LOONEY
Shower Pan 8/11/2023 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 8/14/2023 Approved BRENDAN LOONEY
ELECTRICAL-Rough 8/24/2023 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 8/30/2023 Partial Approval STEPHANIE SWANSON
BUILDING-Rough-Frame 9/11/2023 Partial Approval BRENDAN LOONEY
Green Building Rough 9/11/2023 Not Ready for Inspection BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 9/15/2023 Corrections Issued CHRISTOPHER WILSON
Green Building Rough 9/15/2023 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 9/19/2023 Approved BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 9/19/2023 Partial Approval BRENDAN LOONEY
Interior/Exterior Lathing 9/25/2023 Partial Approval BRENDAN LOONEY
BUILDING-Rough-Frame 9/28/2023 Approved BRENDAN LOONEY
Drywall Nailing 10/10/2023 Approved BRENDAN LOONEY
Interior/Exterior Lathing 10/16/2023 Partial Approval BRENDAN LOONEY
PLUMBING-Rough 1/5/2024 Approved JESUS PINEDA
ELECTRICAL-Final 4/16/2024 Approved SEAN HAUPT
BUILDING-Rough-Frame 4/29/2024 Approved SEAN HAUPT
Final 4/29/2024 Corrections Issued SEAN HAUPT
Green Building Final 4/29/2024 Not Ready for Inspection SEAN HAUPT
Green Building Rough 4/29/2024 Approved SEAN HAUPT
PLUMBING-Final 4/29/2024 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 4/29/2024 SGSOV Not Ready SEAN HAUPT
Smoke Detectors 4/29/2024 Approved SEAN HAUPT
Final 6/6/2024 OK to Issue CofO SEAN HAUPT
Green Building Final 6/6/2024 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 6/6/2024 SGSOV Approved SEAN HAUPT