1260 N ANGELO DR 90077
Certificate Information: 1260 N ANGELO DR 90077
- Application / Permit
- 22014-10000-02166
- Plan Check / Job No.
- B22LA08358
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Renovation and one-story addition (398 sq ft) to exisiting one-story single family dwelling. No change to attached garage and pool
- Permit Issued
- Issued on 6/2/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2022 | JAD BASMA |
| Corrections Issued | 5/21/2022 | JAD BASMA |
| Quality Review Completed | 5/31/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 6/7/2022 | APPLICANT |
| Applicant returned to address corrections | 8/19/2022 | JAD BASMA |
| Plan Check Approved | 9/20/2022 | JAD BASMA |
| Issued | 6/2/2023 | APPLICANT |
| CofO in Progress | 6/7/2024 | SEAN HAUPT |
| Permit Finaled | 6/14/2024 | DANIEL ORRANTE |
| CofO Issued | 6/14/2024 | DANIEL ORRANTE |
| Permit Finaled | 6/14/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZI | Cleared | 6/8/2022 | KENTON TRINH |
| BHO/Hillside ordinance | Cleared | 6/13/2022 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2022 | SAUL GARCIA |
| BHO/Hillside ordinance | Cleared | 7/1/2022 | SAUL GARCIA |
| BHO/Hillside ordinance | Cleared | 7/1/2022 | SAUL GARCIA |
| BHO/Hillside ordinance | Cleared | 7/1/2022 | SAUL GARCIA |
| Private sewage disp. approval | Cleared | 7/6/2022 | KIRK LINKLATER |
| Sewer availability | Cleared | 7/6/2022 | SAUL GARCIA |
| GPI Written Notices | Cleared | 8/19/2022 | JAD BASMA |
| Hydrant and Access approval | Cleared | 8/22/2022 | GILBERT URREA |
| Roof/Waste drainage to street | Cleared | 8/27/2022 | SAUL GARCIA |
| BHO/Hillside ordinance | Cleared | 9/12/2022 | SAUL GARCIA |
| Grading Pre-Inspection | Cleared | 9/20/2022 | JAD BASMA |
Contact Information
| Contractor | Zuma Canyon Construction Inc; Lic. No.: 644942-B | 6428 BONSALL DRIVE MALIBU, CA 90265 |
| Engineer | Sayah, Engineering; Lic. No.: S6000 | 15233 VENTURA BLVD 1130 SJERMAN OAKS, |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/7/2023 | Corrections Issued | BRENDAN LOONEY |
| Deputy Reinf. Concrete | 7/10/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 7/20/2023 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 7/24/2023 | Approved | BRENDAN LOONEY |
| Deputy Reinf. Concrete | 7/26/2023 | Conditional Approval | MICHAEL PELHAM |
| PLUMBING-Rough | 8/2/2023 | Corrections Issued | BRENDAN LOONEY |
| Deputy Drilled-In Anchors | 8/3/2023 | Conditional Approval | BRENDAN LOONEY |
| Shower Pan | 8/11/2023 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 8/14/2023 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Rough | 8/24/2023 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 8/30/2023 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 9/11/2023 | Partial Approval | BRENDAN LOONEY |
| Green Building Rough | 9/11/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Green Building Rough | 9/15/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 9/19/2023 | Approved | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2023 | Partial Approval | BRENDAN LOONEY |
| Interior/Exterior Lathing | 9/25/2023 | Partial Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 9/28/2023 | Approved | BRENDAN LOONEY |
| Drywall Nailing | 10/10/2023 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 10/16/2023 | Partial Approval | BRENDAN LOONEY |
| PLUMBING-Rough | 1/5/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 4/16/2024 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 4/29/2024 | Approved | SEAN HAUPT |
| Final | 4/29/2024 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 4/29/2024 | Not Ready for Inspection | SEAN HAUPT |
| Green Building Rough | 4/29/2024 | Approved | SEAN HAUPT |
| PLUMBING-Final | 4/29/2024 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 4/29/2024 | SGSOV Not Ready | SEAN HAUPT |
| Smoke Detectors | 4/29/2024 | Approved | SEAN HAUPT |
| Final | 6/6/2024 | OK to Issue CofO | SEAN HAUPT |
| Green Building Final | 6/6/2024 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 6/6/2024 | SGSOV Approved | SEAN HAUPT |