1630 S CREST DR 90035

Certificate Information: 1630 S CREST DR 90035

Application / Permit
22014-10000-02140
Plan Check / Job No.
B22LA08316
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-STORY HOUSE ADDITION WITH NEW ATTACHED ADU
Permit Issued
Issued on 8/3/2022
Issuing Office
Current Status
CofO Issued on 9/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/3/2022 APPLICANT
Assigned to Plan Check Engineer 5/19/2022 JAD BASMA
Corrections Issued 5/22/2022 JAD BASMA
Quality Review Completed 5/31/2022 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 7/20/2022 JAD BASMA
Issued 8/3/2022 APPLICANT
Building Plans Picked Up 8/5/2022 APPLICANT
CofO in Progress 9/9/2024 ARAM AVEDISIAN
Permit Finaled 9/10/2024 RICHARD STEINBACH
CofO Issued 9/10/2024 RICHARD STEINBACH
Permit Finaled 9/10/2024 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 5/26/2022 CHRISTOPHER ROCHA
Address approval Cleared 5/26/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 5/26/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 5/26/2022 CHRISTOPHER ROCHA
Low Impact Development Cleared 6/23/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 6/28/2022 CHRISTOPHER ROCHA
GPI Written Notices Cleared 7/20/2022 JAD BASMA

Contact Information

Contractor Owner-Builder       ,
Engineer Thang, Lee And Associates Structural Engineering, Inc; Lic. No.: S4978 319 FOOTHILL BLVD   SUITE C    ARCADIA, CA 91006

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/6/2022 Partial Approval EVAN COOPER
METHANE-Subgrade 10/24/2022 Partial Approval EVAN COOPER
Footing/Foundation/Slab 11/28/2022 Approved EVAN COOPER
METHANE-Barrier 11/28/2022 Approved EVAN COOPER
METHANE-Subgrade 11/28/2022 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 12/21/2022 Corrections Issued JEREMY TODD
Special/Order Compliance 12/21/2022 Partial Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 12/23/2022 Approved JEREMY TODD
Deputy Wood Construction 1/12/2023 Conditional Approval JEREMY TODD
Floor/Roof Diaphrgm/Shear Wall 1/12/2023 Approved JEREMY TODD
Deputy Wood Construction 1/24/2023 Conditional Approval JEREMY TODD
Floor/Roof Diaphrgm/Shear Wall 1/24/2023 Approved JEREMY TODD
HVAC-Rough 1/30/2023 Not Ready for Inspection JEREMY TODD
Floor/Roof Diaphrgm/Shear Wall 3/2/2023 Approved JEREMY TODD
PLUMBING-Rough 3/7/2023 Approved JEREMY TODD
ELECTRICAL-Rough 4/5/2023 Approved JEREMY TODD
HVAC-Rough 4/25/2023 Approved JEREMY TODD
BUILDING-Rough-Frame 5/2/2023 Approved JEREMY TODD
Green Building Rough 5/2/2023 Approved JEREMY TODD
METHANE-Rough 5/2/2023 Approved JEREMY TODD
Shower Pan 5/11/2023 Approved JEREMY TODD
Interior/Exterior Lathing 5/16/2023 Approved JEREMY TODD
Insulation 5/19/2023 Approved JEREMY TODD
Drywall Nailing 5/30/2023 Approved JEREMY TODD
Interior/Exterior Lathing 6/30/2023 Approved JEREMY TODD
ELECTRICAL-Final 6/11/2024 Partial Approval MEL KHACHATOURIAN
ELECTRICAL-Final 7/29/2024 Corrections Issued MEL KHACHATOURIAN
HVAC-Final 8/2/2024 Approved MEL KHACHATOURIAN
PLUMBING-Final 8/5/2024 Approved MEL KHACHATOURIAN
Special/Order Compliance 8/5/2024 Approved DANIEL VERA
ELECTRICAL-Final 8/9/2024 Partial Approval MEL KHACHATOURIAN
ELECTRICAL-Final 9/9/2024 Approved ARAM AVEDISIAN
Final 9/9/2024 OK to Issue CofO ARAM AVEDISIAN
Green Building Final 9/9/2024 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 9/9/2024 SGSOV Approved ARAM AVEDISIAN
Service/Power Release 9/9/2024 Approved ARAM AVEDISIAN
Smoke Detectors 9/9/2024 Approved ARAM AVEDISIAN