1118 W 37TH DR 1-6 90007

Certificate Information: 1118 W 37TH DR 1-6 90007

Application / Permit
22014-10000-02134
Plan Check / Job No.
B22LA08299
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONVERT (E) 858 SQ FT COVERED GARAGE TO ADU PER LAMC 12.22 A33(c) and (e) AND (N) 594 ADDITION ( TOTAL (N) ADU 1452 SQ FT)
Permit Issued
Issued on 12/22/2022
Issuing Office
Metro
Current Status
CofO Issued on 10/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/3/2022 APPLICANT
Assigned to Plan Check Engineer 5/12/2022 VARAND SARKISIAN
Corrections Issued 5/18/2022 VARAND SARKISIAN
Quality Review Completed 5/23/2022 HANS SANTIAGO
Building Plans Picked Up 6/3/2022 APPLICANT
Plan Check Approved 10/13/2022 VARAND SARKISIAN
Issued 12/22/2022 APPLICANT
CofO in Progress 10/4/2023 MARTIN TAVITIAN
CofO Issued 10/30/2023 TED RIES
Permit Finaled 10/30/2023 TED RIES

Permit Application Clearance Information

ZI Cleared 6/30/2022 LOUIS ORTEGA
Address approval Cleared 7/1/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 7/1/2022 JEANETTE VONG
Roof/Waste drainage to street Cleared 7/1/2022 JEANETTE VONG
Sewer availability Cleared 7/1/2022 JEANETTE VONG
Green Code Cleared 7/11/2022 DONALD CRICHLOW
Tenant Habitability Plan Cleared 7/12/2022 MICHAEL SOTO
Community Plan Implem. Overlay Cleared 7/20/2022 RAFAEL FONTES
Hydrant and Access approval Cleared 8/23/2022 RUEL COLE
Low Impact Development Cleared 10/5/2022 MITESH PATEL

Contact Information

Contractor B & Sons Construction Inc; Lic. No.: 1066259-B 4361 E MISSION BLVD #37      MONTCLAIR, CA 91763
Engineer Hwang,, Junho; Lic. No.: S5592 815 FAIRVIEW AVE #205      SOUTH PASADENA, CA 91030

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/20/2023 Approved MARTIN TAVITIAN
Floor/Roof Diaphrgm/Shear Wall 2/10/2023 Approved MARTIN TAVITIAN
Green Building Rough 2/10/2023 Conditional Approval MARTIN TAVITIAN
Wall Anchors 2/10/2023 Conditional Approval MARTIN TAVITIAN
Wood Frame 2/10/2023 Conditional Approval MARTIN TAVITIAN
Floor/Roof Diaphrgm/Shear Wall 3/3/2023 Partial Approval BRUCE CAMPBELL
Green Building Rough 3/3/2023 Not Ready for Inspection BRUCE CAMPBELL
Wood Frame 3/3/2023 Partial Approval BRUCE CAMPBELL
Insulation 3/21/2023 Approved MARTIN TAVITIAN
Drywall Nailing 3/30/2023 Partial Inspection MARTIN TAVITIAN
Floor/Roof Diaphrgm/Shear Wall 3/30/2023 Partial Inspection MARTIN TAVITIAN
Insulation 3/30/2023 Partial Inspection MARTIN TAVITIAN
Interior/Exterior Lathing 3/30/2023 Approved MARTIN TAVITIAN
Special/Order Compliance 3/30/2023 Partial Approval MARTIN TAVITIAN
T-Bar Ceiling 3/30/2023 Partial Inspection MARTIN TAVITIAN
Drywall Nailing 4/17/2023 Approved ALAN MORELOS
Insulation 4/17/2023 Approved ALAN MORELOS
Final 6/7/2023 Partial Approval MARTIN TAVITIAN
Green Building Final 6/7/2023 Approved MARTIN TAVITIAN
Green Building Rough 6/7/2023 Approved MARTIN TAVITIAN
SGSOV-Seismic Gas S/O Valve 6/7/2023 SGSOV Approved MARTIN TAVITIAN
Smoke Detectors 6/7/2023 Approved MARTIN TAVITIAN
Wood Frame 6/7/2023 Approved MARTIN TAVITIAN