3765 S WELLAND AVE 90018
Certificate Information: 3765 S WELLAND AVE 90018
- Application / Permit
- 22014-10000-02122
- Plan Check / Job No.
- B22LA08249
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL OF KITCHEN AND BATH. NEW ADDITION TO REAR (689 SQ FT)
- Permit Issued
- Issued on 6/30/2022
- Issuing Office
- Current Status
- CofO Issued on 2/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2022 | JAD BASMA |
| Corrections Issued | 6/1/2022 | JAD BASMA |
| Quality Review Completed | 6/2/2022 | SAI KHUM |
| Building Plans Picked Up | 6/10/2022 | APPLICANT |
| Plan Check Approved | 6/30/2022 | JAD BASMA |
| Issued | 6/30/2022 | APPLICANT |
| CofO in Progress | 12/16/2022 | ANTHONY EGSON |
| No Progress | 2/11/2023 | RICHARD STEINBACH |
| CofO in Progress | 2/16/2023 | RONALD MYRICK |
| CofO Issued | 2/16/2023 | RONALD MYRICK |
| Permit Finaled | 2/16/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Sewer availability | Cleared | 6/1/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2022 | STEVE MELGAR |
| Low Impact Development | Cleared | 6/21/2022 | MARCO SANCHEZ |
| Hydrant and Access approval | Cleared | 6/24/2022 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 6/27/2022 | STEVE MELGAR |
Contact Information
| Contractor | Daniel S D Construction Inc; Lic. No.: 657391-B | 2934 BEVERLY GLEN CIRCLE #357 LOS ANGELES, CA 90077 |
| Engineer | Segovia,, Felipe; Lic. No.: C41102 | 2622 DORSET DR TORRANCE, CA 90503 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/6/2022 | Approved | ANTHONY EGSON |
| Deputy Reinf. Concrete | 7/6/2022 | Approved | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 7/7/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Sewer | 7/7/2022 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 7/11/2022 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 7/11/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Sewer | 7/11/2022 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 7/15/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 8/16/2022 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 8/16/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 8/16/2022 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 8/16/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 8/16/2022 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 8/22/2022 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 8/22/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 8/22/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 8/24/2022 | Approved | ANTHONY EGSON |
| Insulation | 8/26/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 8/26/2022 | Approved | ANTHONY EGSON |
| Shower Pan | 8/26/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 8/31/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 10/12/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 10/12/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 10/19/2022 | Corrections Issued | ANTHONY EGSON |
| Final | 10/19/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 10/19/2022 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 10/19/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 10/19/2022 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 10/19/2022 | SGSOV Not Ready | ANTHONY EGSON |
| Service/Power Release | 10/19/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Smoke Detectors | 10/19/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 10/26/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 10/26/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 10/26/2022 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 10/26/2022 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 10/26/2022 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 10/26/2022 | SGSOV Not Ready | ANTHONY EGSON |
| Final | 11/3/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 11/3/2022 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 11/3/2022 | SGSOV Not Ready | ANTHONY EGSON |
| Final | 12/7/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 12/7/2022 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 12/13/2022 | Approved | ANTHONY EGSON |
| Final | 12/13/2022 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 12/13/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 12/13/2022 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 12/13/2022 | SGSOV Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 12/15/2022 | Approved | ANTHONY EGSON |
| Final | 12/15/2022 | OK to Issue CofO | ANTHONY EGSON |
| HVAC-Final | 12/15/2022 | Approved | ANTHONY EGSON |