382 N ADERNO WAY 90272

Certificate Information: 382 N ADERNO WAY 90272

Application / Permit
22014-10000-02120
Plan Check / Job No.
B22LA08245
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2ND STORY ADDITION TO EXISTING SINGLE FAMILY DWELLING AND REMODEL. 1 OF 4
Permit Issued
Issued on 2/10/2023
Issuing Office
West Los Angeles
Current Status
CofO Corrected on 3/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/2/2022 APPLICANT
Assigned to Plan Check Engineer 5/19/2022 ADRIANA LOPEZ
Corrections Issued 5/21/2022 ADRIANA LOPEZ
Quality Review Completed 5/26/2022 KEN GILL
Building Plans Picked Up 6/2/2022 APPLICANT
Applicant returned to address corrections 10/14/2022 ADRIANA LOPEZ
Plan Check Approved 2/7/2023 ADRIANA LOPEZ
Issued 2/10/2023 APPLICANT
CofO in Progress 2/20/2026 MEL KHACHATOURIAN
CofO Issued-Status Void 2/20/2026 RICHARD STEINBACH
Permit Finaled-Status Void 2/20/2026 RICHARD STEINBACH
Re-Activate Permit 3/13/2026 RICHARD STEINBACH
Permit Finaled 3/16/2026 RICHARD STEINBACH
CofO Corrected 3/16/2026 RICHARD STEINBACH
Permit Finaled 3/16/2026 RICHARD STEINBACH

Permit Application Clearance Information

Permit Cleared 8/18/2022 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 8/22/2022 ANTHONY MAINEZ
Sewer availability Cleared 8/22/2022 ANTHONY MAINEZ
Coastal Zone Cleared 11/30/2022 MAXFIELD VERMY
Coastal Zone Cleared 11/30/2022 MAXFIELD VERMY
Coastal Zone Cleared 11/30/2022 MAXFIELD VERMY
Miscellaneous Cleared 11/30/2022 MAXFIELD VERMY
Hydrant and Access approval Cleared 1/11/2023 LAVEON RIDER
Trees in Parkway Cleared 1/12/2023 ADALBERTO VERA
Disturb/Remove Protected Trees Cleared 1/17/2023 ADALBERTO VERA
Low Impact Development Cleared 1/17/2023 LONDY ALVARADO
Roof/Waste drainage to street Cleared 1/23/2023 JASON NG
GPI Written Notices Cleared 2/7/2023 ADRIANA LOPEZ
Grading Pre-Inspection Cleared 2/7/2023 ADRIANA LOPEZ

Contact Information

Architect Bakhoum,, Nagy R; Lic. No.: C26503 3800 PACIFIC COAST HIGHWAY      TORRANCE, CA 90505
Contractor T Apple General Contracting Incorporated; Lic. No.: 1064015-B 760 N TOWNE AVE      CLAREMONT, CA 91711
Engineer Garcia,, Lionel Jesus; Lic. No.: C58475 24702 NARBONNE AVE      LOMITA, CA 90717

Inspector Information

MEL KHACHATOURIAN, (213) 796-6439 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/5/2023 Partial Approval BRENDAN LOONEY
Footing/Foundation/Slab 4/5/2023 Partial Approval BRENDAN LOONEY
Pre-Inspection 4/5/2023 Corrections Issued BRENDAN LOONEY
Deputy Drilled-In Anchors 4/19/2023 No Access for Inspection KENNETH NAGLE
Footing/Foundation/Slab 5/1/2023 Partial Approval BRENDAN LOONEY
Reinforced Concrete Frame 5/12/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Underground Mechanical 5/12/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 5/22/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Wood Frame 6/2/2023 Partial Approval KENNETH NAGLE
Wood Frame 6/21/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Underground Mechanical 6/30/2023 Partial Approval EVAN COOPER
Footing/Foundation/Slab 7/6/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Underground Mechanical 7/18/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 8/9/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Pre-Inspection 8/9/2023 Approved GERMAN RODRIGUEZ MENDOZA
Deputy Wood Construction 8/10/2023 No Access for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 8/14/2023 Corrections Issued OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 10/11/2023 Partial Approval EVAN COOPER
PLUMBING-Rough 10/17/2023 Corrections Issued EVAN COOPER
ELECTRICAL-Rough 11/30/2023 Approved EVAN COOPER
PLUMBING-Rough 11/30/2023 Approved EVAN COOPER
HVAC-Rough 12/1/2023 Corrections Issued EVAN COOPER
Shower Pan 12/6/2023 Approved MICHAEL PELHAM
Interior/Exterior Lathing 12/12/2023 Approved EVAN COOPER
BUILDING-Rough-Frame 12/13/2023 Approved EVAN COOPER
Green Building Rough 12/13/2023 Approved EVAN COOPER
Insulation 12/13/2023 Corrections Issued EVAN COOPER
Verify Sprinkler Sign Off 12/13/2023 Approved EVAN COOPER
Insulation 12/22/2023 Approved EVAN COOPER
Interior/Exterior Lathing 1/8/2024 Approved EVAN COOPER
Drywall Nailing 1/22/2024 Approved EVAN COOPER
Underground Mechanical 6/13/2024 Partial Inspection JOHNNY MIRANDA
ELECTRICAL-Rough 6/17/2024 Not Ready for Inspection MATTHEW JENKINS
PLUMBING-Rough 6/17/2024 Not Ready for Inspection MATTHEW JENKINS
Underground Mechanical 6/21/2024 Approved EVAN COOPER
Service/Power Release 9/23/2024 Approved EVAN COOPER
PLUMBING-Final 12/26/2024 Approved EVAN COOPER
HVAC-Final 12/27/2024 Approved EVAN COOPER
ELECTRICAL-Final 12/30/2024 Approved EVAN COOPER
Final 12/30/2024 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 5/20/2025 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 5/20/2025 SGSOV Not Ready BOBBY KEY
Final 8/19/2025 Corrections Issued BOBBY KEY
Green Building Final 8/19/2025 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 8/19/2025 SGSOV Approved BOBBY KEY
Smoke Detectors 8/19/2025 Approved BOBBY KEY
Final 12/5/2025 Not Ready for Inspection MEL KHACHATOURIAN
Final 2/17/2026 Not Ready for Inspection MEL KHACHATOURIAN
Final 2/20/2026 OK to Issue CofO MEL KHACHATOURIAN
Service/Power Release 2/20/2026 Approved MEL KHACHATOURIAN