4212 S HALLDALE AVE 90062

Certificate Information: 4212 S HALLDALE AVE 90062

Application / Permit
22014-10000-02091
Plan Check / Job No.
B22LA08132
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO (E) GARAGE TO CREATE (N) ADU PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 5/10/2023
Issuing Office
Metro
Current Status
CofO Issued on 9/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2022 APPLICANT
Assigned to Plan Check Engineer 5/6/2022 JOSEPH RAFOLS
Corrections Issued 5/7/2022 JOSEPH RAFOLS
Building Plans Picked Up 5/10/2022 APPLICANT
Plan Check Approved 10/21/2022 KHUONG TRUONG
Issued 5/10/2023 APPLICANT
CofO in Progress 9/19/2024 SABAS ALONSO
Permit Finaled 9/25/2024 RUBEN SALAS
CofO Issued 9/25/2024 RUBEN SALAS
Permit Finaled 9/25/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/27/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 6/2/2022 CINDY QI
Sewer availability Cleared 6/2/2022 CINDY QI
Construction near power lines Cleared 7/1/2022 TINA MIRANDA
Low Impact Development Cleared 9/19/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 9/20/2022 CINDY QI
Public Works-Open Permits Cleared 6/6/2024 FRANK SALAZAR

Contact Information

Contractor Quantum Construction & Design; Lic. No.: 1061867-B 3646 W SLAUSON AVE      LOS ANGELES, CA 90043
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/26/2023 Partial Approval JOSEPH MCGARRY
Underground Mechanical 7/10/2023 Partial Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 7/13/2023 Approved SABAS ALONSO
Footing/Foundation/Slab 7/13/2023 Approved SABAS ALONSO
Deputy Drilled-In Anchors 7/14/2023 Conditional Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 7/18/2023 No Access for Inspection CHARLES BOGHOSKHAN
ELECTRICAL-Rough 10/19/2023 Approved MICHAEL LEWIS
HVAC-Rough 10/19/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 10/19/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 10/25/2023 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 10/25/2023 Partial Approval SABAS ALONSO
Sewer 10/25/2023 Approved SABAS ALONSO
Underground Mechanical 10/25/2023 Partial Approval SABAS ALONSO
Deputy Wood Construction 10/27/2023 Conditional Approval SABAS ALONSO
BUILDING-Rough-Frame 10/31/2023 No Access for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 10/31/2023 No Access for Inspection SABAS ALONSO
Green Building Rough 10/31/2023 No Access for Inspection SABAS ALONSO
BUILDING-Rough-Frame 11/13/2023 No Access for Inspection SABAS ALONSO
Green Building Rough 11/13/2023 No Access for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 11/16/2023 Conditional Approval SABAS ALONSO
BUILDING-Rough-Frame 11/20/2023 Not Ready for Inspection SABAS ALONSO
Green Building Rough 11/20/2023 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 11/27/2023 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 11/27/2023 Approved SABAS ALONSO
Green Building Rough 11/27/2023 Approved SABAS ALONSO
HVAC-Rough 11/27/2023 Approved SABAS ALONSO
Insulation 11/30/2023 No Access for Inspection BRENDAN MORELLI
Interior/Exterior Lathing 11/30/2023 No Access for Inspection BRENDAN MORELLI
Insulation 12/5/2023 Corrections Issued BRENDAN MORELLI
Interior/Exterior Lathing 12/5/2023 Partial Approval BRENDAN MORELLI
Drywall Nailing 12/7/2023 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 12/11/2023 Approved MICHAEL LEWIS
Insulation 12/11/2023 Approved MICHAEL LEWIS
ELECTRICAL-Final 5/29/2024 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 5/29/2024 Approved SABAS ALONSO
PLUMBING-Final 5/29/2024 Approved SABAS ALONSO
Service/Power Release 5/29/2024 Not Ready for Inspection SABAS ALONSO
Shower Pan 5/29/2024 Approved SABAS ALONSO
ELECTRICAL-Final 6/3/2024 Corrections Issued SABAS ALONSO
ELECTRICAL-Final 6/12/2024 No Access for Inspection SABAS ALONSO
Final 6/13/2024 Not Ready for Inspection SABAS ALONSO
Green Building Final 6/13/2024 No Access for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 6/13/2024 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 6/13/2024 No Access for Inspection SABAS ALONSO
ELECTRICAL-Final 6/14/2024 Corrections Issued SABAS ALONSO
ELECTRICAL-Final 6/25/2024 Approved SABAS ALONSO
Underground Mechanical 6/25/2024 Approved SABAS ALONSO
HVAC-Final 7/2/2024 No Access for Inspection SABAS ALONSO
Final 7/5/2024 Corrections Issued SABAS ALONSO
Green Building Final 7/5/2024 Approved SABAS ALONSO
HVAC-Final 7/5/2024 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 7/5/2024 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 7/5/2024 Approved SABAS ALONSO
HVAC-Final 7/10/2024 Not Ready for Inspection CRAIG DAVIS
Pre-Inspection 7/11/2024 Partial Inspection SABAS ALONSO
ELECTRICAL-Final 9/6/2024 No Access for Inspection SABAS ALONSO
Final 9/6/2024 No Access for Inspection SABAS ALONSO
HVAC-Final 9/6/2024 No Access for Inspection SABAS ALONSO
PLUMBING-Final 9/6/2024 No Access for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 9/6/2024 SGSOV Not Ready SABAS ALONSO
ELECTRICAL-Final 9/10/2024 Approved SABAS ALONSO
Final 9/10/2024 Corrections Issued SABAS ALONSO
HVAC-Final 9/10/2024 Approved SABAS ALONSO
PLUMBING-Final 9/10/2024 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 9/10/2024 SGSOV Approved SABAS ALONSO
HVAC-Final 9/12/2024 Approved SABAS ALONSO
Final 9/17/2024 OK to Issue CofO SABAS ALONSO