4212 S HALLDALE AVE 90062
Certificate Information: 4212 S HALLDALE AVE 90062
- Application / Permit
- 22014-10000-02091
- Plan Check / Job No.
- B22LA08132
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO (E) GARAGE TO CREATE (N) ADU PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 5/10/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2022 | JOSEPH RAFOLS |
| Corrections Issued | 5/7/2022 | JOSEPH RAFOLS |
| Building Plans Picked Up | 5/10/2022 | APPLICANT |
| Plan Check Approved | 10/21/2022 | KHUONG TRUONG |
| Issued | 5/10/2023 | APPLICANT |
| CofO in Progress | 9/19/2024 | SABAS ALONSO |
| Permit Finaled | 9/25/2024 | RUBEN SALAS |
| CofO Issued | 9/25/2024 | RUBEN SALAS |
| Permit Finaled | 9/25/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/27/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2022 | CINDY QI |
| Sewer availability | Cleared | 6/2/2022 | CINDY QI |
| Construction near power lines | Cleared | 7/1/2022 | TINA MIRANDA |
| Low Impact Development | Cleared | 9/19/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 9/20/2022 | CINDY QI |
| Public Works-Open Permits | Cleared | 6/6/2024 | FRANK SALAZAR |
Contact Information
| Contractor | Quantum Construction & Design; Lic. No.: 1061867-B | 3646 W SLAUSON AVE LOS ANGELES, CA 90043 |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/26/2023 | Partial Approval | JOSEPH MCGARRY |
| Underground Mechanical | 7/10/2023 | Partial Approval | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 7/13/2023 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 7/13/2023 | Approved | SABAS ALONSO |
| Deputy Drilled-In Anchors | 7/14/2023 | Conditional Approval | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 7/18/2023 | No Access for Inspection | CHARLES BOGHOSKHAN |
| ELECTRICAL-Rough | 10/19/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 10/19/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 10/19/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 10/25/2023 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2023 | Partial Approval | SABAS ALONSO |
| Sewer | 10/25/2023 | Approved | SABAS ALONSO |
| Underground Mechanical | 10/25/2023 | Partial Approval | SABAS ALONSO |
| Deputy Wood Construction | 10/27/2023 | Conditional Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 10/31/2023 | No Access for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2023 | No Access for Inspection | SABAS ALONSO |
| Green Building Rough | 10/31/2023 | No Access for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 11/13/2023 | No Access for Inspection | SABAS ALONSO |
| Green Building Rough | 11/13/2023 | No Access for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2023 | Conditional Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 11/20/2023 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Rough | 11/20/2023 | Corrections Issued | SABAS ALONSO |
| BUILDING-Rough-Frame | 11/27/2023 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2023 | Approved | SABAS ALONSO |
| Green Building Rough | 11/27/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 11/27/2023 | Approved | SABAS ALONSO |
| Insulation | 11/30/2023 | No Access for Inspection | BRENDAN MORELLI |
| Interior/Exterior Lathing | 11/30/2023 | No Access for Inspection | BRENDAN MORELLI |
| Insulation | 12/5/2023 | Corrections Issued | BRENDAN MORELLI |
| Interior/Exterior Lathing | 12/5/2023 | Partial Approval | BRENDAN MORELLI |
| Drywall Nailing | 12/7/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 12/11/2023 | Approved | MICHAEL LEWIS |
| Insulation | 12/11/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 5/29/2024 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 5/29/2024 | Approved | SABAS ALONSO |
| PLUMBING-Final | 5/29/2024 | Approved | SABAS ALONSO |
| Service/Power Release | 5/29/2024 | Not Ready for Inspection | SABAS ALONSO |
| Shower Pan | 5/29/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 6/3/2024 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Final | 6/12/2024 | No Access for Inspection | SABAS ALONSO |
| Final | 6/13/2024 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 6/13/2024 | No Access for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 6/13/2024 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 6/13/2024 | No Access for Inspection | SABAS ALONSO |
| ELECTRICAL-Final | 6/14/2024 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Final | 6/25/2024 | Approved | SABAS ALONSO |
| Underground Mechanical | 6/25/2024 | Approved | SABAS ALONSO |
| HVAC-Final | 7/2/2024 | No Access for Inspection | SABAS ALONSO |
| Final | 7/5/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 7/5/2024 | Approved | SABAS ALONSO |
| HVAC-Final | 7/5/2024 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 7/5/2024 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 7/5/2024 | Approved | SABAS ALONSO |
| HVAC-Final | 7/10/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Pre-Inspection | 7/11/2024 | Partial Inspection | SABAS ALONSO |
| ELECTRICAL-Final | 9/6/2024 | No Access for Inspection | SABAS ALONSO |
| Final | 9/6/2024 | No Access for Inspection | SABAS ALONSO |
| HVAC-Final | 9/6/2024 | No Access for Inspection | SABAS ALONSO |
| PLUMBING-Final | 9/6/2024 | No Access for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 9/6/2024 | SGSOV Not Ready | SABAS ALONSO |
| ELECTRICAL-Final | 9/10/2024 | Approved | SABAS ALONSO |
| Final | 9/10/2024 | Corrections Issued | SABAS ALONSO |
| HVAC-Final | 9/10/2024 | Approved | SABAS ALONSO |
| PLUMBING-Final | 9/10/2024 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 9/10/2024 | SGSOV Approved | SABAS ALONSO |
| HVAC-Final | 9/12/2024 | Approved | SABAS ALONSO |
| Final | 9/17/2024 | OK to Issue CofO | SABAS ALONSO |