6147 W TEMPLE HILL DR 90068

Certificate Information: 6147 W TEMPLE HILL DR 90068

Application / Permit
22014-10000-02081
Plan Check / Job No.
B22LA08121
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
eplan PROPOSED ADDITION TO EXISTING DETACHED GARAGE.
Permit Issued
Issued on 7/26/2023
Issuing Office
Current Status
CofO Issued on 5/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/2/2022 APPLICANT
Assigned to Plan Check Engineer 6/2/2022 MICHAEL LOPEZ
Corrections Issued 6/10/2022 MICHAEL LOPEZ
Quality Review Completed 6/15/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 8/19/2022 MICHAEL LOPEZ
Plan Check Approved 9/15/2022 MICHAEL LOPEZ
Issued 7/26/2023 APPLICANT
CofO in Progress 2/19/2025 CRAIG VAUGHAN
No Progress 2/20/2025 BRIAN SULLIVAN
CofO in Progress 2/20/2025 BRIAN SULLIVAN
No Progress 3/2/2025 DEROLD HAUFF
CofO in Progress 3/2/2025 DEROLD HAUFF
No Progress 3/23/2025 DEROLD HAUFF
CofO in Progress 3/23/2025 DEROLD HAUFF
Permit Finaled 5/3/2025 DEROLD HAUFF
CofO Issued 5/3/2025 DEROLD HAUFF
Permit Finaled 5/3/2025 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/9/2022 ALEXANDER HELFER
ZA Case Cleared 7/7/2022 RUBEN VASQUEZ
ZI Cleared 7/7/2022 RUBEN VASQUEZ
Roof/Waste drainage to street Cleared 7/9/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 8/1/2022 CINDY QI

Contact Information

Architect Bestor,, Barbara A; Lic. No.: C26132 2030 HYPERION AVENUE      LOS ANGELES, CA 90027
Contractor Lightning Construction & Design Inc; Lic. No.: 951122-B 6047 TAMPA AVE #303      TARZANA, CA 91356
Engineer Phillips,, Craig; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/31/2023 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 8/3/2023 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 8/9/2023 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 9/15/2023 Partial Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 9/27/2023 Partial Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 11/2/2023 Partial Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 11/14/2023 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 1/8/2024 Approved ROY SPAULDING
HVAC-Rough 1/8/2024 Corrections Issued ROY SPAULDING
PLUMBING-Rough 1/8/2024 Approved ROY SPAULDING
BUILDING-Rough-Frame 1/16/2024 Not Ready for Inspection ROY SPAULDING
Green Building Rough 1/16/2024 Partial Approval ROY SPAULDING
HVAC-Rough 1/16/2024 Corrections Issued ROY SPAULDING
Interior/Exterior Lathing 1/16/2024 Approved ROY SPAULDING
BUILDING-Rough-Frame 1/18/2024 Approved ROY SPAULDING
Green Building Rough 1/18/2024 Approved ROY SPAULDING
HVAC-Rough 1/18/2024 Approved ROY SPAULDING
Insulation 1/23/2024 Approved BRIAN SULLIVAN
Drywall Nailing 2/1/2024 Not Ready for Inspection BRIAN SULLIVAN
Shower Pan 2/1/2024 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 2/8/2024 Approved JOSH MEISTER
Drywall Nailing 2/12/2024 Approved BRIAN SULLIVAN
ELECTRICAL-Final 7/22/2024 Approved ROY SPAULDING
HVAC-Final 7/22/2024 Approved ROY SPAULDING
PLUMBING-Final 7/22/2024 Approved ROY SPAULDING
Final 11/5/2024 OK to Issue CofO CRAIG VAUGHAN
Green Building Final 11/5/2024 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 11/5/2024 SGSOV Not Required CRAIG VAUGHAN
Smoke Detectors 11/5/2024 Approved CRAIG VAUGHAN