825 E 99TH ST 90002
Certificate Information: 825 E 99TH ST 90002
- Application / Permit
- 22014-10000-02073
- Plan Check / Job No.
- B22LA08054
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **eplan** CONVERT EXISTING DETACHED GARAGE TO ACCESSORY DWELLING UNIT AND ADDITION (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
- Permit Issued
- Issued on 9/2/2022
- Issuing Office
- Current Status
- CofO Issued on 6/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/15/2022 | GEORGE ALVAREZ |
| Corrections Issued | 5/17/2022 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 6/19/2022 | AUNG SOE |
| Plan Check Approved | 6/20/2022 | AUNG SOE |
| Issued | 9/2/2022 | APPLICANT |
| CofO in Progress | 6/5/2024 | BEN MOLSTAD |
| Permit Finaled | 6/13/2024 | DONALD CRICHLOW |
| CofO Issued | 6/13/2024 | DONALD CRICHLOW |
| Permit Finaled | 6/13/2024 | DONALD CRICHLOW |
Permit Application Clearance Information
| Address approval | Cleared | 5/24/2022 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 5/24/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 6/7/2022 | JEANIE LAM |
| Sewer availability | Cleared | 6/7/2022 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Southerland,, Richard Charles; Lic. No.: C88965 | 16526 BLACKHAWK ST GRANADA HILLS, CA 91344 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/30/2023 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 3/30/2023 | Partial Approval | JOHN KLARIN |
| Deputy Drilled-In Anchors | 4/11/2023 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2023 | Partial Approval | JOHN KLARIN |
| ELECTRICAL-Rough | 5/4/2023 | Not Ready for Inspection | JOHN KLARIN |
| HVAC-Rough | 5/4/2023 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 5/4/2023 | Corrections Issued | JOHN KLARIN |
| Rough-Elec/Plmb/HVAC | 5/9/2023 | Approved | JOHN KLARIN |
| Insulation | 5/26/2023 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 6/21/2023 | Not Ready for Inspection | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2023 | Approved | JOHN KLARIN |
| Gas Test | 6/21/2023 | Approved | JOHN KLARIN |
| Grounding or Bonding | 6/21/2023 | Not Ready for Inspection | JOHN KLARIN |
| Drywall Nailing | 6/26/2023 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 2/22/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 2/22/2024 | Corrections Issued | BEN MOLSTAD |
| Final | 2/22/2024 | Corrections Issued | BEN MOLSTAD |
| Gas Test | 2/22/2024 | Approved | BEN MOLSTAD |
| Green Building Final | 2/22/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Rough | 2/22/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Final | 2/22/2024 | Corrections Issued | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 2/22/2024 | SGSOV Not Ready | BEN MOLSTAD |
| Smoke Detectors | 2/22/2024 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Final | 6/4/2024 | Approved | BEN MOLSTAD |
| Final | 6/4/2024 | OK to Issue CofO | BEN MOLSTAD |
| Green Building Final | 6/4/2024 | Approved | BEN MOLSTAD |
| HVAC-Final | 6/4/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Final | 6/4/2024 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 6/4/2024 | SGSOV Approved | BEN MOLSTAD |
| Smoke Detectors | 6/4/2024 | Approved | BEN MOLSTAD |