2028 S KELTON AVE 90025
Certificate Information: 2028 S KELTON AVE 90025
- Application / Permit
- 22014-10000-02023
- Plan Check / Job No.
- B22LA07889
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT GARAGE AND (N) ADDITION INTO (N) DETACHED ADU PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 4/22/2025
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 6/10/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/1/2022 | SUNMIN LEE |
| Corrections Issued | 5/3/2022 | SUNMIN LEE |
| Applicant returned to address corrections | 8/24/2022 | SUNMIN LEE |
| Applicant returned to address corrections | 10/27/2022 | SUNMIN LEE |
| Applicant returned to address corrections | 11/2/2022 | MINA HABILI |
| Plan Check Approved | 12/6/2022 | FERNANDO FLORES |
| Issued | 4/22/2025 | APPLICANT |
| CofO in Progress | 6/10/2026 | ANTHONY EGSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/15/2022 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 6/15/2022 | KIRK LINKLATER |
| Roof/Waste drainage to street | Cleared | 6/15/2022 | DINAH GARIN |
| ZA Case | Cleared | 6/15/2022 | ANACANY HURTADO |
| Eng Process Fee Ord 176,300 | Cleared | 6/17/2022 | DINAH GARIN |
| Sewer availability | Cleared | 6/17/2022 | DINAH GARIN |
| Specific Plan | Cleared | 6/27/2022 | FREDDY GARCIA |
| Construction within easement | Cleared | 8/19/2022 | RIDWAN HARDY |
Contact Information
| Architect | Bullock,, Rachel Lane; Lic. No.: NA35963 | , |
| Contractor | J P Contractor Services; Lic. No.: 996127-B | 20058 VENTURA BLVD 17 WOODLAND HILLS, CA 91364 |
| Engineer | Sayah,, Daniel H; Lic. No.: S6000 | 15233 VENTURA BLVD 1130 SHERMAN OAKS, CA 91403 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/15/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| Deputy Drilled-In Anchors | 8/18/2025 | Conditional Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 8/19/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 8/19/2025 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 8/22/2025 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 8/22/2025 | Partial Approval | ARAM AVEDISIAN |
| Sewer | 8/22/2025 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2025 | Partial Approval | ARAM AVEDISIAN |
| Sewer | 9/15/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| Sewer | 9/17/2025 | Corrections Issued | ARAM AVEDISIAN |
| Sewer | 9/19/2025 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 10/29/2025 | Corrections Issued | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2025 | Approved | MICHAEL ALLEN |
| Shower Pan | 10/29/2025 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 11/3/2025 | Corrections Issued | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 12/17/2025 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 12/17/2025 | Partial Approval | MICHAEL ALLEN |
| Interior/Exterior Lathing | 12/17/2025 | Partial Approval | MICHAEL ALLEN |
| Special/Order Compliance | 12/17/2025 | Corrections Issued | MICHAEL ALLEN |
| HVAC-Rough | 12/23/2025 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 12/23/2025 | Approved | JESUS PINEDA |
| Insulation | 1/6/2026 | Partial Approval | MICHAEL ALLEN |
| Drywall Nailing | 1/21/2026 | Approved | MICHAEL ALLEN |
| Insulation | 1/21/2026 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 1/27/2026 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Final | 6/4/2026 | Approved | WILBER ROSALES |
| Final | 6/4/2026 | Corrections Issued | WILBER ROSALES |
| HVAC-Final | 6/4/2026 | Approved | WILBER ROSALES |
| PLUMBING-Final | 6/4/2026 | Approved | WILBER ROSALES |
| Final | 6/9/2026 | OK to Issue CofO | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 6/9/2026 | SGSOV Not Required | ANTHONY EGSON |
| Smoke Detectors | 6/9/2026 | Approved | ANTHONY EGSON |