10408 S BARING CROSS ST 90044
Certificate Information: 10408 S BARING CROSS ST 90044
- Application / Permit
- 22014-10000-02007
- Plan Check / Job No.
- B22LA07845
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 335 SF DETACHED GARAGE & (E) 52 SF STORAGE TO 2-BEDROOM ADU WITH (N) 314 SF ADDITION. TOTAL 701 SF ADU
- Permit Issued
- Issued on 4/10/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/1/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2022 | JESSE JIMENEZ |
| Corrections Issued | 5/9/2022 | JESSE JIMENEZ |
| Building Plans Picked Up | 5/11/2022 | APPLICANT |
| Plan Check Approved | 6/27/2022 | JOSEPH RAFOLS |
| Issued | 4/10/2023 | APPLICANT |
| CofO in Progress | 10/30/2023 | JAMES CHAVEZ |
| Permit Finaled | 11/1/2023 | ANSON MAGLASANG |
| CofO Issued | 11/1/2023 | ANSON MAGLASANG |
| Permit Finaled | 11/1/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 5/25/2022 | CINDY QI |
| Permit | Cleared | 5/25/2022 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 5/25/2022 | CINDY QI |
| Tenant Habitability Plan | Cleared | 5/25/2022 | ISMAEL HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/26/2022 | CINDY QI |
| Sewer availability | Cleared | 5/26/2022 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Keshishian,, Anthony; Lic. No.: C89551 | 2654 RISA D GLENDALE, CA 91208 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/12/2023 | Corrections Issued | JAMES CHAVEZ |
| Underground Mechanical | 4/12/2023 | Approved | JAMES CHAVEZ |
| Excavation/Setback/Form/Re-Bar | 4/14/2023 | Corrections Issued | JAMES CHAVEZ |
| Underground Mechanical | 4/14/2023 | Approved | JAMES CHAVEZ |
| Excavation/Setback/Form/Re-Bar | 4/17/2023 | Approved | JAMES CHAVEZ |
| Underground Mechanical | 4/17/2023 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2023 | Partial Approval | JAMES CHAVEZ |
| Green Building Rough | 5/15/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| PLUMBING-Rough | 5/15/2023 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Rough | 6/1/2023 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2023 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2023 | Corrections Issued | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2023 | Approved | JOHN KLARIN |
| Insulation | 6/13/2023 | Corrections Issued | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 6/15/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Green Building Rough | 6/15/2023 | Approved | JAMES CHAVEZ |
| HVAC-Rough | 6/15/2023 | Corrections Issued | JAMES CHAVEZ |
| Insulation | 6/16/2023 | Approved | JOHN KLARIN |
| Drywall Nailing | 6/21/2023 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 6/21/2023 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 8/21/2023 | Approved | JAMES CHAVEZ |
| Final | 8/21/2023 | Corrections Issued | JAMES CHAVEZ |
| Footing/Foundation/Slab | 8/21/2023 | Approved | JAMES CHAVEZ |
| Green Building Final | 8/21/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 8/21/2023 | SGSOV Not Ready | JAMES CHAVEZ |
| Smoke Detectors | 8/21/2023 | Approved | JAMES CHAVEZ |
| Final | 8/29/2023 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 8/29/2023 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 8/29/2023 | SGSOV Approved | JOHN KLARIN |
| Final | 9/26/2023 | Corrections Issued | JAMES CHAVEZ |
| Final | 10/30/2023 | OK to Issue CofO | JAMES CHAVEZ |