3941 N VESELICH AVE 3A-3C 90039

Certificate Information: 3941 N VESELICH AVE 3A-3C 90039

Application / Permit
22014-10000-01997
Plan Check / Job No.
B22LA07815
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONVERT EXISTING GARAGE TO ADU ON BLDG #3 (3A, 3B, 3C) 1 OF 3
Permit Issued
Issued on 10/6/2023
Issuing Office
Metro
Current Status
CofO Issued on 3/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/5/2022 APPLICANT
Assigned to Plan Check Engineer 6/9/2022 SERGIO GUTIERREZ
Disabled Access Plans Picked Up 6/14/2022 APPLICANT
Corrections Issued 6/28/2022 SERGIO GUTIERREZ
Quality Review Completed 7/6/2022 RODOLFO ARIAS
Building Plans Picked Up 7/8/2022 APPLICANT
Applicant returned to address corrections 10/12/2022 SERGIO GUTIERREZ
Applicant returned to address corrections 9/20/2023 SERGIO GUTIERREZ
Plan Check Approved 9/21/2023 SERGIO GUTIERREZ
Issued 10/6/2023 APPLICANT
CofO in Progress 3/19/2025 LUIS CCAMACHO
CofO Issued 3/21/2025 ERNESTO CORRAL
Permit Finaled 3/21/2025 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 1/6/2023 JEANETTE VONG
Highway dedication Cleared 1/6/2023 JEANETTE VONG
Roof/Waste drainage to street Cleared 1/6/2023 JEANETTE VONG
Sewer availability Cleared 1/6/2023 JEANETTE VONG
Miscellaneous Cleared 1/10/2023 MAXFIELD VERMY
Miscellaneous Cleared 1/10/2023 MAXFIELD VERMY
ZA Case Cleared 1/10/2023 MAXFIELD VERMY
Green Code Cleared 5/4/2023 AARON COSTA
Fire Marshal Fire Life Safety Cleared 6/8/2023 SARAH ZHANG
Tenant Habitability Plan Cleared 6/12/2023 RICARDO BOHORQUEZ
Eng Process Fee Ord 176,300 Cleared 6/28/2023 JESSICA OPINION
Hydrant and Access approval Cleared 7/6/2023 LAVEON RIDER
DAS Clearance Cleared 7/7/2023 SERGIO GUTIERREZ
Trees in Parkway Cleared 8/21/2023 ADALBERTO VERA

Contact Information

Architect Malak,, Hany; Lic. No.: C27490 360 PINE TREE LANE      MONROVIA, CA 91016
Contractor Grundco; Lic. No.: 1016287-B 24372 VANOWEN ST STE 205      WEST HILLS, CA 91307
Engineer Chan,, Dominic Kam-Tim; Lic. No.: S4381 5147 GOLDEN WEST AVE      TEMPLE CITY, CA 91780

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/15/2023 Partial Approval RONALD JIMENEZ
Footing/Foundation/Slab 11/15/2023 Partial Approval RONALD JIMENEZ
Footing/Foundation/Slab 11/22/2023 Partial Approval RONALD JIMENEZ
Deputy Reinf. Concrete 11/29/2023 Conditional Approval RONALD JIMENEZ
Footing/Foundation/Slab 1/25/2024 Partial Approval RAFAEL CORTES
Light Gage Steel Frame 3/1/2024 Not Ready for Inspection RAFAEL CORTES
Light Gage Steel Frame 3/5/2024 Partial Approval RAFAEL CORTES
Insulation 3/8/2024 Partial Approval JEROME BLACKWOOD
Light Gage Steel Frame 3/8/2024 Approved JEROME BLACKWOOD
Drywall Nailing 3/12/2024 Approved RAFAEL CORTES
Interior/Exterior Lathing 3/20/2024 Approved EDWIN GREGORYONA
Interior/Exterior Lathing 3/26/2024 Not Ready for Inspection RAFAEL CORTES
Final 12/3/2024 Not Ready for Inspection LUIS CCAMACHO
Footing/Foundation/Slab 12/3/2024 Not Ready for Inspection LUIS CCAMACHO
Green Building Final 12/3/2024 Not Ready for Inspection LUIS CCAMACHO
Green Building Rough 12/3/2024 Not Ready for Inspection LUIS CCAMACHO
Reinforced Concrete Frame 12/3/2024 Not Ready for Inspection LUIS CCAMACHO
SGSOV-Seismic Gas S/O Valve 12/3/2024 SGSOV Not Ready LUIS CCAMACHO
Smoke Detectors 12/3/2024 Not Ready for Inspection LUIS CCAMACHO
Wood Frame 12/3/2024 Not Ready for Inspection LUIS CCAMACHO
Final 3/18/2025 OK to Issue CofO LUIS CCAMACHO
Footing/Foundation/Slab 3/18/2025 Approved LUIS CCAMACHO
Green Building Final 3/18/2025 Approved LUIS CCAMACHO
Green Building Rough 3/18/2025 Approved LUIS CCAMACHO
Reinforced Concrete Frame 3/18/2025 Approved LUIS CCAMACHO
SGSOV-Seismic Gas S/O Valve 3/18/2025 SGSOV No Gas LUIS CCAMACHO
Smoke Detectors 3/18/2025 Approved LUIS CCAMACHO
Wood Frame 3/18/2025 Approved LUIS CCAMACHO