6210 S 10TH AVE 1-23 90043
Certificate Information: 6210 S 10TH AVE 1-23 90043
- Application / Permit
- 22014-10000-01986
- Plan Check / Job No.
- B22LA07787
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- ePlan. Convert portion of (E) attached carport of a 2-story apartment building to 3 accessory dwelling units (ADU) per CA GOVT. Code 65852.2 (e)(1)(C)
- Permit Issued
- Issued on 9/29/2022
- Issuing Office
- Current Status
- CofO Issued on 2/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2022 | TU HUA |
| Corrections Issued | 6/3/2022 | TU HUA |
| Quality Review Completed | 6/8/2022 | CHAD DOI |
| Applicant returned to address corrections | 7/27/2022 | TU HUA |
| Plan Check Approved | 8/5/2022 | TU HUA |
| Issued | 9/29/2022 | APPLICANT |
| CofO in Progress | 2/26/2025 | DARRYL ARNOLD |
| Permit Finaled | 2/26/2025 | WINSTON DUNNING |
| CofO Issued | 2/26/2025 | WINSTON DUNNING |
Permit Application Clearance Information
| Address approval | Cleared | 6/13/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 6/13/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2022 | TREVOR QUAN |
Contact Information
| Architect | Feld,, Dovid Yitzchak; Lic. No.: NA37588 | , |
| Contractor | Oyz Developments Llc; Lic. No.: 1079567-B | , |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/3/2023 | Corrections Issued | ALAN MORELOS |
| Footing/Foundation/Slab | 4/21/2023 | Not Ready for Inspection | DARRYL ARNOLD |
| Wood Frame | 10/2/2023 | Approved | MARTIN TAVITIAN |
| Insulation | 10/10/2023 | Approved | RICARDO ROBLES |
| Interior/Exterior Lathing | 10/10/2023 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 10/19/2023 | Approved | RICARDO ROBLES |
| Interior/Exterior Lathing | 10/19/2023 | Approved | RICARDO ROBLES |
| Final | 5/20/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 5/20/2024 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 5/20/2024 | Corrections Issued | DARRYL ARNOLD |
| Pre-Inspection | 5/22/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| Final | 12/18/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 12/18/2024 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 12/18/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| Final | 1/31/2025 | Conditional Approval | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 1/31/2025 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 1/31/2025 | Approved | DARRYL ARNOLD |
| Final | 2/26/2025 | OK to Issue CofO | DARRYL ARNOLD |