6416 W 82ND ST 90045
Certificate Information: 6416 W 82ND ST 90045
- Application / Permit
- 22014-10000-01959
- Plan Check / Job No.
- B22LA07688
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1 STORY REMODEL (NEW ATTACHED 2-CAR GARAGE) AND 2ND STORY ADDITION TO A SINGLE FAMILY RESIDENCE.
- Permit Issued
- Issued on 9/20/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2022 | ADRIANA LOPEZ |
| Corrections Issued | 5/14/2022 | ADRIANA LOPEZ |
| Quality Review Completed | 5/18/2022 | KEN GILL |
| Applicant returned to address corrections | 6/30/2022 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 7/12/2022 | ADRIANA LOPEZ |
| Plan Check Approved | 7/21/2022 | ADRIANA LOPEZ |
| Issued | 9/20/2022 | APPLICANT |
| CofO in Progress | 10/14/2023 | HERBERT GIRON |
| Permit Finaled | 10/16/2023 | DANIEL ORRANTE |
| CofO Issued | 10/16/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/16/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Permit | Cleared | 5/26/2022 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2022 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 6/6/2022 | ANTHONY MAINEZ |
| Permit | Cleared | 6/9/2022 | ANTHONY MAINEZ |
| Low Impact Development | Cleared | 6/23/2022 | MICHAEL SCADUTO |
| Roof/Waste drainage to street | Cleared | 6/28/2022 | ANTHONY MAINEZ |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Local Construction Remodeling; Lic. No.: 966738-B | 14901 TUBA STREET MISSION HILLS, CA 91345 |
| Engineer | Namdar,, Mansour Tom; Lic. No.: S2976 | 16867 SEVERO PLACE ENCINO, CA 91436 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/1/2022 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 11/14/2022 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 11/18/2022 | Approved | HERBERT GIRON |
| Deputy Wood Construction | 12/7/2022 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2022 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2022 | Partial Approval | HERBERT GIRON |
| Deputy Wood Construction | 1/25/2023 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2023 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2023 | Approved | HERBERT GIRON |
| HVAC-Rough | 2/1/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 2/1/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 2/13/2023 | Not Ready for Inspection | HERBERT GIRON |
| Sewer | 2/13/2023 | Approved | HERBERT GIRON |
| Underground Mechanical | 2/13/2023 | Approved | HERBERT GIRON |
| Sewer | 2/14/2023 | Approved | HERBERT GIRON |
| Underground Mechanical | 2/14/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 2/27/2023 | Approved | HERBERT GIRON |
| HVAC-Rough | 2/27/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 2/27/2023 | Partial Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 3/1/2023 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 3/1/2023 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Rough | 3/1/2023 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 3/20/2023 | Conditional Approval | HERBERT GIRON |
| Green Building Rough | 3/20/2023 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 3/28/2023 | Approved | HERBERT GIRON |
| Shower Pan | 3/28/2023 | Approved | HERBERT GIRON |
| Insulation | 3/31/2023 | Approved | HERBERT GIRON |
| Drywall Nailing | 4/6/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 4/6/2023 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 8/28/2023 | Corrections Issued | HERBERT GIRON |
| Gas Test | 8/28/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 8/28/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 8/28/2023 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 8/28/2023 | SGSOV Approved | HERBERT GIRON |
| ELECTRICAL-Final | 8/31/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 8/31/2023 | Approved | HERBERT GIRON |
| Final | 10/13/2023 | OK to Issue CofO | HERBERT GIRON |
| Green Building Final | 10/13/2023 | Approved | HERBERT GIRON |
| Service/Power Release | 10/13/2023 | Approved | HERBERT GIRON |
| Smoke Detectors | 10/13/2023 | Approved | HERBERT GIRON |