5360 N AMESTOY AVE 91316
Certificate Information: 5360 N AMESTOY AVE 91316
- Application / Permit
- 22014-10000-01948
- Plan Check / Job No.
- B22LA07646
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND REMODEL TO (E) SFD WITH ATTACHED GARAGE
- Permit Issued
- Issued on 3/24/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2022 | CRYSTEL MAALOUF |
| Corrections Issued | 5/17/2022 | CRYSTEL MAALOUF |
| Quality Review Completed | 5/18/2022 | KEN GILL |
| Building Plans Picked Up | 6/2/2022 | APPLICANT |
| Plan Check Approved | 8/24/2022 | CRYSTEL MAALOUF |
| Issued | 3/24/2023 | APPLICANT |
| CofO in Progress | 10/31/2023 | JON MCHUGH |
| Permit Finaled | 11/21/2023 | JOHN JANSON |
| CofO Issued | 11/21/2023 | JOHN JANSON |
| Permit Finaled | 11/21/2023 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/27/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 6/27/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 7/15/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 7/15/2022 | ABDULLAH SADOZAI |
Contact Information
| Architect | Woodcraft,, Astra E; Lic. No.: C32722 | 20812 VENTURA BLVD SUITE 205 WOODLAND HILLS, CA 91364 |
| Contractor | Ca Alliance Builders Inc; Lic. No.: 1045324-B | 29215 FLORABUNDA RD CANYON COUNTRY, CA 91387 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/24/2023 | Not Ready for Inspection | JON MCHUGH |
| Deputy Drilled-In Anchors | 4/25/2023 | Conditional Approval | JON MCHUGH |
| Footing/Foundation/Slab | 4/27/2023 | Approved | JON MCHUGH |
| Wood Frame | 5/9/2023 | Corrections Issued | JON MCHUGH |
| Wood Frame | 5/17/2023 | Partial Approval | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2023 | Partial Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 7/17/2023 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 7/17/2023 | Approved | JOHN KIDWELL |
| Green Building Rough | 7/17/2023 | Approved | JOHN KIDWELL |
| HVAC-Rough | 7/17/2023 | Approved | JOHN KIDWELL |
| MERV13>=Rough | 7/17/2023 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 7/17/2023 | Approved | JOHN KIDWELL |
| Insulation | 7/20/2023 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 8/2/2023 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 8/25/2023 | Approved | HENRY KIM |
| Final | 10/10/2023 | Corrections Issued | JON MCHUGH |
| Green Building Final | 10/10/2023 | Not Ready for Inspection | JON MCHUGH |
| MERV13>=Final | 10/10/2023 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 10/10/2023 | SGSOV Approved | JON MCHUGH |
| Smoke Detectors | 10/10/2023 | Not Ready for Inspection | JON MCHUGH |
| Final | 10/23/2023 | Corrections Issued | JON MCHUGH |
| Green Building Final | 10/23/2023 | Approved | JON MCHUGH |
| Smoke Detectors | 10/23/2023 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Final | 10/31/2023 | Approved | JON MCHUGH |
| Final | 10/31/2023 | OK to Issue CofO | JON MCHUGH |
| HVAC-Final | 10/31/2023 | Approved | JON MCHUGH |
| PLUMBING-Final | 10/31/2023 | Approved | JON MCHUGH |
| Smoke Detectors | 10/31/2023 | Approved | JON MCHUGH |