2248 N WORKMAN ST 90031

Certificate Information: 2248 N WORKMAN ST 90031

Application / Permit
22014-10000-01938
Plan Check / Job No.
B22LA07592
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan Addition to and conversion of existing garage to a new A.D.U. PLANCHECK PER LAMC 12.22 A33 (C) AND (D) AND PER WFPP CODE ENFORCEMENT "COMPLY WITH DEPARTMENT ORDER effective date 03/12/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 1/23/2023
Issuing Office
Current Status
CofO Issued on 11/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/28/2022 APPLICANT
Assigned to Plan Check Engineer 5/5/2022 SUNMIN LEE
Corrections Issued 5/6/2022 SUNMIN LEE
Plan Check Approved 1/18/2023 JOSEPH RAFOLS
Issued 1/23/2023 APPLICANT
CofO in Progress 10/30/2023 JACOB SEGURA
Permit Finaled 11/29/2023 DANIEL SANCHEZ
CofO Issued 11/29/2023 DANIEL SANCHEZ
Permit Finaled 11/29/2023 DANIEL SANCHEZ

Permit Application Clearance Information

Address approval Cleared 5/11/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 5/12/2022 WALLIE JONG
Sewer availability Cleared 5/12/2022 WALLIE JONG
Low Impact Development Cleared 8/22/2022 JULIAN SUNG
Roof/Waste drainage to street Cleared 8/23/2022 WALLIE JONG
CPC Cleared 12/21/2022 JONATHAN KAPLAN
HPOZ Cleared 12/21/2022 JONATHAN KAPLAN

Contact Information

Contractor Hollywood Contractor Corp; Lic. No.: 1092628-B       ,

Inspector Information

THOMAS WILLIS, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
JEFFREY CHRISTIAN, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
FERMIN RUBIO, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
JACOB SEGURA, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
CLAUDIO MORENO, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
MARK RUDE, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/25/2023 Approved JAVIER RAMOS SR
Pre-Inspection 3/30/2023 Partial Inspection JAVIER RAMOS SR
Underground Mechanical 3/30/2023 Partial Approval JAVIER RAMOS SR
Pre-Inspection 4/4/2023 Corrections Issued JAVIER RAMOS SR
PLUMBING-Rough 4/25/2023 Partial Approval JAVIER RAMOS SR
Footing/Foundation/Slab 5/2/2023 Approved JAVIER RAMOS SR
Floor/Roof Diaphrgm/Shear Wall 5/30/2023 Approved JAVIER RAMOS SR
BUILDING-Rough-Frame 6/15/2023 Approved JAVIER RAMOS SR
ELECTRICAL-Rough 6/15/2023 Partial Approval JAVIER RAMOS SR
HVAC-Rough 6/15/2023 Not Ready for Inspection JAVIER RAMOS SR
PLUMBING-Rough 6/15/2023 Approved JAVIER RAMOS SR
Underground Mechanical 6/15/2023 Approved JAVIER RAMOS SR
HVAC-Rough 6/22/2023 Approved JAVIER RAMOS SR
Interior/Exterior Lathing 6/22/2023 Partial Approval JAVIER RAMOS SR
Insulation 6/27/2023 Approved JAVIER RAMOS SR
Drywall Nailing 6/29/2023 Approved JAVIER RAMOS SR
Interior/Exterior Lathing 7/18/2023 Approved JAVIER RAMOS SR
Underground Mechanical 7/26/2023 Approved JAVIER RAMOS SR
Pre-Inspection 8/2/2023 Approved JAVIER RAMOS SR
Final 8/17/2023 No Access for Inspection JAVIER RAMOS SR
SGSOV-Seismic Gas S/O Valve 8/17/2023 SGSOV Not Ready JAVIER RAMOS SR
Smoke Detectors 8/17/2023 No Access for Inspection JAVIER RAMOS SR
Final 8/23/2023 Not Ready for Inspection JAVIER RAMOS SR
SGSOV-Seismic Gas S/O Valve 8/23/2023 SGSOV Not Ready JAVIER RAMOS SR
Smoke Detectors 8/23/2023 Not Ready for Inspection JAVIER RAMOS SR
Final 9/1/2023 Partial Inspection ROBERT MINASSIANS
SGSOV-Seismic Gas S/O Valve 9/1/2023 SGSOV Not Ready ROBERT MINASSIANS
Sewer 9/1/2023 Approved ROBERT MINASSIANS
Smoke Detectors 9/1/2023 Approved ROBERT MINASSIANS
Final 10/4/2023 Corrections Issued JACOB SEGURA
SGSOV-Seismic Gas S/O Valve 10/4/2023 SGSOV Not Ready JACOB SEGURA
Final 10/12/2023 Partial Approval JACOB SEGURA
SGSOV-Seismic Gas S/O Valve 10/12/2023 SGSOV Approved JACOB SEGURA
Final 10/25/2023 OK to Issue CofO JACOB SEGURA