2248 N WORKMAN ST 90031
Certificate Information: 2248 N WORKMAN ST 90031
- Application / Permit
- 22014-10000-01938
- Plan Check / Job No.
- B22LA07592
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan Addition to and conversion of existing garage to a new A.D.U. PLANCHECK PER LAMC 12.22 A33 (C) AND (D) AND PER WFPP CODE ENFORCEMENT "COMPLY WITH DEPARTMENT ORDER effective date 03/12/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 1/23/2023
- Issuing Office
- Current Status
- CofO Issued on 11/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2022 | SUNMIN LEE |
| Corrections Issued | 5/6/2022 | SUNMIN LEE |
| Plan Check Approved | 1/18/2023 | JOSEPH RAFOLS |
| Issued | 1/23/2023 | APPLICANT |
| CofO in Progress | 10/30/2023 | JACOB SEGURA |
| Permit Finaled | 11/29/2023 | DANIEL SANCHEZ |
| CofO Issued | 11/29/2023 | DANIEL SANCHEZ |
| Permit Finaled | 11/29/2023 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Address approval | Cleared | 5/11/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 5/12/2022 | WALLIE JONG |
| Sewer availability | Cleared | 5/12/2022 | WALLIE JONG |
| Low Impact Development | Cleared | 8/22/2022 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 8/23/2022 | WALLIE JONG |
| CPC | Cleared | 12/21/2022 | JONATHAN KAPLAN |
| HPOZ | Cleared | 12/21/2022 | JONATHAN KAPLAN |
Contact Information
| Contractor | Hollywood Contractor Corp; Lic. No.: 1092628-B | , |
Inspector Information
| THOMAS WILLIS, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| JEFFREY CHRISTIAN, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| FERMIN RUBIO, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| JACOB SEGURA, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| CLAUDIO MORENO, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK RUDE, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/25/2023 | Approved | JAVIER RAMOS SR |
| Pre-Inspection | 3/30/2023 | Partial Inspection | JAVIER RAMOS SR |
| Underground Mechanical | 3/30/2023 | Partial Approval | JAVIER RAMOS SR |
| Pre-Inspection | 4/4/2023 | Corrections Issued | JAVIER RAMOS SR |
| PLUMBING-Rough | 4/25/2023 | Partial Approval | JAVIER RAMOS SR |
| Footing/Foundation/Slab | 5/2/2023 | Approved | JAVIER RAMOS SR |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2023 | Approved | JAVIER RAMOS SR |
| BUILDING-Rough-Frame | 6/15/2023 | Approved | JAVIER RAMOS SR |
| ELECTRICAL-Rough | 6/15/2023 | Partial Approval | JAVIER RAMOS SR |
| HVAC-Rough | 6/15/2023 | Not Ready for Inspection | JAVIER RAMOS SR |
| PLUMBING-Rough | 6/15/2023 | Approved | JAVIER RAMOS SR |
| Underground Mechanical | 6/15/2023 | Approved | JAVIER RAMOS SR |
| HVAC-Rough | 6/22/2023 | Approved | JAVIER RAMOS SR |
| Interior/Exterior Lathing | 6/22/2023 | Partial Approval | JAVIER RAMOS SR |
| Insulation | 6/27/2023 | Approved | JAVIER RAMOS SR |
| Drywall Nailing | 6/29/2023 | Approved | JAVIER RAMOS SR |
| Interior/Exterior Lathing | 7/18/2023 | Approved | JAVIER RAMOS SR |
| Underground Mechanical | 7/26/2023 | Approved | JAVIER RAMOS SR |
| Pre-Inspection | 8/2/2023 | Approved | JAVIER RAMOS SR |
| Final | 8/17/2023 | No Access for Inspection | JAVIER RAMOS SR |
| SGSOV-Seismic Gas S/O Valve | 8/17/2023 | SGSOV Not Ready | JAVIER RAMOS SR |
| Smoke Detectors | 8/17/2023 | No Access for Inspection | JAVIER RAMOS SR |
| Final | 8/23/2023 | Not Ready for Inspection | JAVIER RAMOS SR |
| SGSOV-Seismic Gas S/O Valve | 8/23/2023 | SGSOV Not Ready | JAVIER RAMOS SR |
| Smoke Detectors | 8/23/2023 | Not Ready for Inspection | JAVIER RAMOS SR |
| Final | 9/1/2023 | Partial Inspection | ROBERT MINASSIANS |
| SGSOV-Seismic Gas S/O Valve | 9/1/2023 | SGSOV Not Ready | ROBERT MINASSIANS |
| Sewer | 9/1/2023 | Approved | ROBERT MINASSIANS |
| Smoke Detectors | 9/1/2023 | Approved | ROBERT MINASSIANS |
| Final | 10/4/2023 | Corrections Issued | JACOB SEGURA |
| SGSOV-Seismic Gas S/O Valve | 10/4/2023 | SGSOV Not Ready | JACOB SEGURA |
| Final | 10/12/2023 | Partial Approval | JACOB SEGURA |
| SGSOV-Seismic Gas S/O Valve | 10/12/2023 | SGSOV Approved | JACOB SEGURA |
| Final | 10/25/2023 | OK to Issue CofO | JACOB SEGURA |