1946 W BLAKE AVE 90039
Certificate Information: 1946 W BLAKE AVE 90039
- Application / Permit
- 22014-10000-01926
- Plan Check / Job No.
- B22LA07537
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO AN ADU WITH 1-STORY ADDITION. PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 5/18/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/4/2022 | LUKE GONZALES |
| Corrections Issued | 5/4/2022 | LUKE GONZALES |
| Building Plans Picked Up | 5/5/2022 | APPLICANT |
| Plan Check Approved | 5/18/2022 | AUNG SOE |
| Issued | 5/18/2022 | APPLICANT |
| CofO in Progress | 6/4/2024 | HAMIK HARTOUNIAN |
| Permit Finaled | 6/4/2024 | DEROLD HAUFF |
| CofO Issued | 6/4/2024 | DEROLD HAUFF |
| Permit Finaled | 6/4/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| ZI | Cleared | 5/9/2022 | MAYELA VILLA |
| Address approval | Cleared | 5/12/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 5/12/2022 | CHRISTOPHER ROCHA |
| Roof/Waste drainage to street | Cleared | 5/12/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 5/12/2022 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tuchscher,, James Todd; Lic. No.: C77649 | 5503 E 2ND ST LONG BEACH, CA 90803 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/11/2022 | Partial Inspection | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 7/28/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 8/1/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Deputy Reinf. Concrete | 8/2/2022 | Conditional Approval | THOMAS LOGRASSO |
| Green Building Rough | 8/5/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Rough | 8/5/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Reinforced Masonry Frame | 8/5/2022 | Partial Approval | THOMAS LOGRASSO |
| Gas Test | 8/16/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Rough | 8/16/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Rough | 8/16/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 8/16/2022 | Partial Approval | THOMAS LOGRASSO |
| Reinforced Masonry Frame | 8/16/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Sewer | 8/16/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 8/23/2022 | Approved | THOMAS LOGRASSO |
| Masonry Wall/Backfill | 8/23/2022 | Partial Approval | THOMAS LOGRASSO |
| Deputy Drilled-In Anchors | 8/30/2022 | Conditional Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 9/29/2022 | Partial Approval | THOMAS LOGRASSO |
| Green Building Rough | 9/29/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Rough | 9/29/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2022 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2022 | Partial Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 12/7/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 1/23/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 1/23/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 1/23/2023 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 2/8/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Gas Test | 2/8/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Rough | 2/8/2023 | Approved | THOMAS LOGRASSO |
| PLUMBING-Rough | 2/8/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 2/10/2023 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 2/13/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Rough | 2/13/2023 | Approved | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 2/13/2023 | Approved | THOMAS LOGRASSO |
| Insulation | 2/17/2023 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 3/28/2023 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 3/28/2023 | Approved | THOMAS LOGRASSO |
| Shower Pan | 3/28/2023 | Approved | THOMAS LOGRASSO |
| Sewer | 9/15/2023 | Approved | THOMAS LOGRASSO |
| Underground Mechanical | 9/15/2023 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 6/3/2024 | Approved | HAMIK HARTOUNIAN |
| Final | 6/3/2024 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Green Building Final | 6/3/2024 | Approved | HAMIK HARTOUNIAN |
| MERV13>=Final | 6/3/2024 | Approved | HAMIK HARTOUNIAN |
| Reinforced Masonry Frame | 6/3/2024 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 6/3/2024 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 6/3/2024 | Approved | HAMIK HARTOUNIAN |
| Structural Steel Frame | 6/3/2024 | Approved | HAMIK HARTOUNIAN |