1544 S MIDVALE AVE 90024

Certificate Information: 1544 S MIDVALE AVE 90024

Application / Permit
22014-10000-01925
Plan Check / Job No.
B22LA07536
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED ADDITION( 1ST AND 2ND FLOOR) AND MAJOR REMODEL TO (E) ONE STORY SFD. *******See Comment (RFA)******
Permit Issued
Issued on 9/30/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/11/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/27/2022 APPLICANT
Assigned to Plan Check Engineer 5/26/2022 TSE MING HUANG
Corrections Issued 6/8/2022 TSE MING HUANG
Quality Review Completed 6/14/2022 EUGENE BARBEAU
Building Plans Picked Up 6/15/2022 APPLICANT
Applicant returned to address corrections 8/2/2022 TSE MING HUANG
Applicant returned to address corrections 8/30/2022 TSE MING HUANG
Plan Check Approved 9/27/2022 TSE MING HUANG
Issued 9/30/2022 APPLICANT
CofO in Progress 4/11/2024 ASHLEY THOMPSON
Permit Finaled 4/11/2024 DANIEL ORRANTE
CofO Issued 4/11/2024 DANIEL ORRANTE
Permit Finaled 4/11/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/17/2022 DINAH GARIN
Sewer availability Cleared 6/17/2022 DINAH GARIN
Specific Plan Cleared 7/7/2022 PEDRO AYALA
Grading Pre-Inspection Cleared 8/2/2022 TSE MING HUANG
Low Impact Development Cleared 8/24/2022 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 8/27/2022 JOSE HERNANDEZ

Contact Information

Architect Ryder,, Derek Thomas; Lic. No.: C32847 4111 GLENALBYN DRIVE      LOS ANGELES, CA 90065
Contractor Skyson Construction Co; Lic. No.: 515183-B 17609 VENTURA BLVD #218      ENCINO, CA 91316
Engineer Marquis,, Steve; Lic. No.: C69672 27508 SWEETLAND ROAD      NORTH SAN JUAN, CA 95960

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Posting Pre-Inspection 10/17/2022 Approved ANDREW NAVE
Pre-Inspection 10/17/2022 Approved ANDREW NAVE
Excavation/Setback/Form/Re-Bar 12/1/2022 Approved CHRISTOPHER WILSON
Footing/Foundation/Slab 12/1/2022 Partial Approval CHRISTOPHER WILSON
METHANE-Barrier 12/1/2022 Approved CHRISTOPHER WILSON
METHANE-Subgrade 12/1/2022 Approved CHRISTOPHER WILSON
PLUMBING-Rough 12/5/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 2/15/2023 Conditional Approval CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 2/16/2023 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 3/1/2023 Corrections Issued CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 3/2/2023 Partial Approval CLAYTON GRAHAM
ELECTRICAL-Rough 3/29/2023 Partial Approval CLAYTON GRAHAM
ELECTRICAL-Rough 4/13/2023 Not Ready for Inspection JEREMY TODD
Floor/Roof Diaphrgm/Shear Wall 4/13/2023 Not Ready for Inspection JEREMY TODD
HVAC-Rough 4/13/2023 Approved JEREMY TODD
PLUMBING-Rough 4/13/2023 Approved JEREMY TODD
BUILDING-Rough-Frame 4/27/2023 Conditional Approval JESUS PINEDA
ELECTRICAL-Rough 4/27/2023 Approved JESUS PINEDA
Interior/Exterior Lathing 4/27/2023 Partial Approval JESUS PINEDA
BUILDING-Rough-Frame 5/4/2023 Approved JESUS PINEDA
Green Building Rough 5/4/2023 Approved JESUS PINEDA
METHANE-Rough 5/4/2023 Approved JESUS PINEDA
Wood Frame 5/4/2023 Approved JESUS PINEDA
Insulation 5/11/2023 Approved JEREMY TODD
Drywall Nailing 5/26/2023 Approved BRENDAN LOONEY
Special/Order Compliance 5/26/2023 Corrections Issued BRENDAN LOONEY
Shower Pan 8/21/2023 No Access for Inspection ARAM AVEDISIAN
Interior/Exterior Lathing 9/1/2023 Approved BEN MOLSTAD
Shower Pan 9/7/2023 Approved BEN MOLSTAD
ELECTRICAL-Rough 11/30/2023 Approved BEN MOLSTAD
Service/Power Release 1/25/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Deck 2/12/2024 Not Ready for Inspection ASHLEY THOMPSON
ELECTRICAL-Final 2/12/2024 Corrections Issued ASHLEY THOMPSON
Final 2/12/2024 Corrections Issued ASHLEY THOMPSON
Footing/Foundation/Slab 2/12/2024 Approved ASHLEY THOMPSON
Gas Test 2/12/2024 Corrections Issued ASHLEY THOMPSON
Grading Pre-Inspection 2/12/2024 Not Ready for Inspection ASHLEY THOMPSON
Green Building Final 2/12/2024 Corrections Issued ASHLEY THOMPSON
HVAC-Final 2/12/2024 Corrections Issued ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 2/12/2024 SGSOV Not Ready ASHLEY THOMPSON
Sewer 2/12/2024 Not Ready for Inspection ASHLEY THOMPSON
Smoke Detectors 2/12/2024 Not Ready for Inspection ASHLEY THOMPSON
ELECTRICAL-Final 2/21/2024 Corrections Issued ASHLEY THOMPSON
Final 2/21/2024 Not Ready for Inspection ASHLEY THOMPSON
Gas Test 2/21/2024 Approved ASHLEY THOMPSON
Green Building Final 2/21/2024 Not Ready for Inspection ASHLEY THOMPSON
HVAC-Final 2/21/2024 Not Ready for Inspection ASHLEY THOMPSON
PLUMBING-Final 2/21/2024 Approved ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 2/21/2024 SGSOV Approved ASHLEY THOMPSON
Service/Power Release 2/21/2024 Not Ready for Inspection ASHLEY THOMPSON
Smoke Detectors 2/21/2024 Not Ready for Inspection ASHLEY THOMPSON
Service/Power Release 2/23/2024 Approved MEL KHACHATOURIAN
ELECTRICAL-Final 3/14/2024 Approved STEPHANIE SWANSON
Green Building Final 3/14/2024 Approved STEPHANIE SWANSON
Final 3/20/2024 Corrections Issued STEPHANIE SWANSON
HVAC-Final 3/20/2024 Approved STEPHANIE SWANSON
Smoke Detectors 3/20/2024 Approved STEPHANIE SWANSON
Final 3/22/2024 Corrections Issued OGANES TARAKHCHYAN
Final 4/10/2024 Conditional Approval MICHAEL PELHAM
Final 4/11/2024 OK to Issue CofO ASHLEY THOMPSON