837 N SOTO ST 90033
Certificate Information: 837 N SOTO ST 90033
- Application / Permit
- 22014-10000-01924
- Plan Check / Job No.
- B22LA07535
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ONE (1) STORY ADU (752.12 S.F.) ADDITION TO AN EXISTING TWO (2) CAR (369 SF) GARAGE
- Permit Issued
- Issued on 4/26/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/4/2022 | JOSEPH RAFOLS |
| Corrections Issued | 5/5/2022 | ADAM HEGAZI |
| Building Plans Picked Up | 5/10/2022 | APPLICANT |
| Applicant returned to address corrections | 4/17/2023 | WEIJIAN HUANG |
| Plan Check Approved | 4/26/2023 | SHANGQIN XIE |
| Issued | 4/26/2023 | APPLICANT |
| CofO in Progress | 9/9/2024 | ALIZAH MAYAGOITIA |
| CofO Issued | 9/17/2024 | DEROLD HAUFF |
| Permit Finaled | 9/17/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/14/2022 | STEVE MELGAR |
| Historic Resource Verification | Cleared | 5/16/2022 | MAX LODER |
| Eng Process Fee Ord 176,300 | Cleared | 5/18/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 5/18/2022 | STEVE MELGAR |
| Redevelopment Project Area | Cleared | 5/24/2022 | DAVID URITA |
| Low Impact Development | Cleared | 11/16/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 12/19/2022 | STEVE MELGAR |
| GPI Written Notices | Cleared | 4/17/2023 | ADAM HEGAZI |
| Grading Pre-Inspection | Cleared | 4/17/2023 | ADAM HEGAZI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/26/2023 | Conditional Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 5/30/2023 | Corrections Issued | OSVALDO PARAMO |
| METHANE-Barrier | 5/30/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| METHANE-Subgrade | 5/30/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 6/1/2023 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 6/9/2023 | Approved | OSVALDO PARAMO |
| METHANE-Barrier | 6/9/2023 | Approved | OSVALDO PARAMO |
| METHANE-Subgrade | 6/9/2023 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2023 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 6/20/2023 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Insulation | 6/30/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 6/30/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2023 | Corrections Issued | AMY COLIN |
| ELECTRICAL-Rough | 8/17/2023 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 8/17/2023 | Approved | OSVALDO PARAMO |
| MERV13>=Rough | 8/17/2023 | Approved | OSVALDO PARAMO |
| METHANE-Rough | 8/17/2023 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 8/17/2023 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Rough | 8/24/2023 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 8/30/2023 | Partial Approval | OSVALDO PARAMO |
| Green Building Rough | 8/30/2023 | Approved | OSVALDO PARAMO |
| Shower Pan | 8/30/2023 | Approved | OSVALDO PARAMO |
| Deputy Wood Construction | 8/31/2023 | Conditional Approval | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 9/5/2023 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2023 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 9/5/2023 | Partial Approval | OSVALDO PARAMO |
| Drywall Nailing | 9/13/2023 | Approved | OSVALDO PARAMO |
| Insulation | 9/13/2023 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 9/13/2023 | Approved | OSVALDO PARAMO |
| Sewer | 10/25/2023 | Approved | OSVALDO PARAMO |
| Underground Mechanical | 10/25/2023 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 1/22/2024 | SGSOV Not Ready | OSVALDO PARAMO |
| Final | 1/25/2024 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 1/25/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| MERV13>=Final | 1/25/2024 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 1/25/2024 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 1/25/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Final | 8/22/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 8/22/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 8/22/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 8/22/2024 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 8/22/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 8/30/2024 | Partial Inspection | OSVALDO PARAMO |
| Green Building Final | 8/30/2024 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 8/30/2024 | SGSOV Not Ready | OSVALDO PARAMO |
| Final | 9/6/2024 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 9/6/2024 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 9/6/2024 | Approved | ALIZAH MAYAGOITIA |