837 N SOTO ST 90033

Certificate Information: 837 N SOTO ST 90033

Application / Permit
22014-10000-01924
Plan Check / Job No.
B22LA07535
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ONE (1) STORY ADU (752.12 S.F.) ADDITION TO AN EXISTING TWO (2) CAR (369 SF) GARAGE
Permit Issued
Issued on 4/26/2023
Issuing Office
Metro
Current Status
CofO Issued on 9/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/25/2022 APPLICANT
Assigned to Plan Check Engineer 5/4/2022 JOSEPH RAFOLS
Corrections Issued 5/5/2022 ADAM HEGAZI
Building Plans Picked Up 5/10/2022 APPLICANT
Applicant returned to address corrections 4/17/2023 WEIJIAN HUANG
Plan Check Approved 4/26/2023 SHANGQIN XIE
Issued 4/26/2023 APPLICANT
CofO in Progress 9/9/2024 ALIZAH MAYAGOITIA
CofO Issued 9/17/2024 DEROLD HAUFF
Permit Finaled 9/17/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/14/2022 STEVE MELGAR
Historic Resource Verification Cleared 5/16/2022 MAX LODER
Eng Process Fee Ord 176,300 Cleared 5/18/2022 STEVE MELGAR
Sewer availability Cleared 5/18/2022 STEVE MELGAR
Redevelopment Project Area Cleared 5/24/2022 DAVID URITA
Low Impact Development Cleared 11/16/2022 DEBORA LEITE
Roof/Waste drainage to street Cleared 12/19/2022 STEVE MELGAR
GPI Written Notices Cleared 4/17/2023 ADAM HEGAZI
Grading Pre-Inspection Cleared 4/17/2023 ADAM HEGAZI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/26/2023 Conditional Approval OSVALDO PARAMO
Footing/Foundation/Slab 5/30/2023 Corrections Issued OSVALDO PARAMO
METHANE-Barrier 5/30/2023 Not Ready for Inspection OSVALDO PARAMO
METHANE-Subgrade 5/30/2023 Not Ready for Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 6/1/2023 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 6/9/2023 Approved OSVALDO PARAMO
METHANE-Barrier 6/9/2023 Approved OSVALDO PARAMO
METHANE-Subgrade 6/9/2023 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 6/20/2023 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 6/20/2023 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 6/30/2023 Partial Approval ALIZAH MAYAGOITIA
Insulation 6/30/2023 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 6/30/2023 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 7/28/2023 Corrections Issued AMY COLIN
ELECTRICAL-Rough 8/17/2023 Approved OSVALDO PARAMO
HVAC-Rough 8/17/2023 Approved OSVALDO PARAMO
MERV13>=Rough 8/17/2023 Approved OSVALDO PARAMO
METHANE-Rough 8/17/2023 Approved OSVALDO PARAMO
PLUMBING-Rough 8/17/2023 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 8/24/2023 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 8/30/2023 Partial Approval OSVALDO PARAMO
Green Building Rough 8/30/2023 Approved OSVALDO PARAMO
Shower Pan 8/30/2023 Approved OSVALDO PARAMO
Deputy Wood Construction 8/31/2023 Conditional Approval LILIANA PORTILLO
BUILDING-Rough-Frame 9/5/2023 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 9/5/2023 Approved OSVALDO PARAMO
Interior/Exterior Lathing 9/5/2023 Partial Approval OSVALDO PARAMO
Drywall Nailing 9/13/2023 Approved OSVALDO PARAMO
Insulation 9/13/2023 Approved OSVALDO PARAMO
Interior/Exterior Lathing 9/13/2023 Approved OSVALDO PARAMO
Sewer 10/25/2023 Approved OSVALDO PARAMO
Underground Mechanical 10/25/2023 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 1/22/2024 SGSOV Not Ready OSVALDO PARAMO
Final 1/25/2024 Corrections Issued OSVALDO PARAMO
Green Building Final 1/25/2024 Not Ready for Inspection OSVALDO PARAMO
MERV13>=Final 1/25/2024 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 1/25/2024 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 1/25/2024 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Final 8/22/2024 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 8/22/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Final 8/22/2024 Corrections Issued ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 8/22/2024 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 8/22/2024 Approved ALIZAH MAYAGOITIA
Final 8/30/2024 Partial Inspection OSVALDO PARAMO
Green Building Final 8/30/2024 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 8/30/2024 SGSOV Not Ready OSVALDO PARAMO
Final 9/6/2024 OK to Issue CofO ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 9/6/2024 SGSOV Approved ALIZAH MAYAGOITIA
Service/Power Release 9/6/2024 Approved ALIZAH MAYAGOITIA