22233 W WELBY WAY 91303

Certificate Information: 22233 W WELBY WAY 91303

Application / Permit
22014-10000-01908
Plan Check / Job No.
B22LA07432
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
271 SQ. FT. 1-STORY ADDITION TO 1-STORY SINGLE FAMILY DWELLING AND INTERIOR REMODEL.
Permit Issued
Issued on 6/14/2022
Issuing Office
Current Status
CofO Issued on 2/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2022 APPLICANT
Assigned to Plan Check Engineer 5/4/2022 ZAW HAN
Corrections Issued 5/5/2022 ZAW HAN
Building Plans Picked Up 5/6/2022 APPLICANT
Plan Check Approved 5/27/2022 DANIEL SANJUAN
Issued 6/14/2022 APPLICANT
CofO in Progress 2/8/2024 TROY SANDERS
Permit Finaled 2/29/2024 JOHN JANSON
CofO Issued 2/29/2024 JOHN JANSON
Permit Finaled 2/29/2024 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/9/2022 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 5/9/2022 MEGAN GODINEZ
Sewer availability Cleared 5/9/2022 MEGAN GODINEZ
ZI Cleared 5/11/2022 RYAN LY

Contact Information

Contractor Pnr Builders Inc; Lic. No.: 1028148-B 21226 VENTURA BLVD #250      WOODLAND HILLS, CA 91364
Engineer Mroczka,, Peter J; Lic. No.: C42648 9301 DARBY AVE APT 1      NORTHRIDGE, CA 91325

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/6/2022 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 2/27/2023 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 3/2/2023 Partial Approval TROY SANDERS
Special/Order Compliance 3/2/2023 Partial Inspection MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 3/9/2023 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 4/17/2023 Partial Approval TROY SANDERS
Interior/Exterior Lathing 4/17/2023 Not Ready for Inspection TROY SANDERS
BUILDING-Rough-Frame 5/17/2023 Approved TROY SANDERS
ELECTRICAL-Rough 5/17/2023 Approved TROY SANDERS
Green Building Rough 5/17/2023 Approved TROY SANDERS
Interior/Exterior Lathing 5/17/2023 Partial Approval TROY SANDERS
Drywall Nailing 2/7/2024 Approved TROY SANDERS
Final 2/7/2024 OK to Issue CofO TROY SANDERS
Footing/Foundation/Slab 2/7/2024 Approved TROY SANDERS
Green Building Final 2/7/2024 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 2/7/2024 SGSOV Approved TROY SANDERS
Smoke Detectors 2/7/2024 Approved TROY SANDERS