5055 N COLUMBUS AVE 91403

Certificate Information: 5055 N COLUMBUS AVE 91403

Application / Permit
22014-10000-01907
Plan Check / Job No.
B22LA07430
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) ADDITION TO (E) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
Permit Issued
Issued on 7/5/2022
Issuing Office
Metro
Current Status
CofO Issued on 1/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/21/2022 APPLICANT
Assigned to Plan Check Engineer 5/2/2022 AUNG SOE
Corrections Issued 5/4/2022 AUNG SOE
Applicant returned to address corrections 6/24/2022 JOSEPH RAFOLS
Plan Check Approved 6/30/2022 FERNANDO FLORES
Issued 7/5/2022 APPLICANT
CofO in Progress 1/13/2023 DAVID MATSON
CofO Issued 1/18/2023 MICHAEL SMITH
Permit Finaled 1/18/2023 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/20/2022 ROMAN GUTIERREZ
Sewer availability Cleared 5/20/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 5/23/2022 ROMAN GUTIERREZ
ZI Cleared 5/23/2022 RUBEN VASQUEZ
Public Works-Highway Ded. Cleared 5/23/2022 ROMAN GUTIERREZ
Public Works-Open Permits Cleared 5/23/2022 ROMAN GUTIERREZ
Public Works-Sewers Cleared 5/23/2022 ROMAN GUTIERREZ

Contact Information

Contractor B & C Construction Inc; Lic. No.: 1017702-B 4523 EAST 56TH STREET      MAYWOOD, CA 90270
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/8/2022 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 9/13/2022 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 9/30/2022 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 9/30/2022 Conditional Approval MISAEL ESPARZA
Green Building Rough 9/30/2022 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 9/30/2022 Approved MISAEL ESPARZA
MERV13>=Rough 9/30/2022 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 10/6/2022 Corrections Issued JACK KARGODORIAN
Green Building Rough 10/6/2022 Approved JACK KARGODORIAN
HVAC-Final 10/6/2022 Approved JACK KARGODORIAN
PLUMBING-Rough 10/6/2022 Approved JACK KARGODORIAN
Wood Frame 10/7/2022 Approved JACK KARGODORIAN
Drywall Nailing 10/14/2022 Approved THOMAS FINNILA
BUILDING-Rough-Frame 11/15/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 11/15/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Final 11/15/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 11/15/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
MERV13>=Final 11/15/2022 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 11/15/2022 SGSOV Approved CHRISTOPHER DELLEFIELD
Smoke Detectors 11/15/2022 Approved CHRISTOPHER DELLEFIELD
Final 11/28/2022 Partial Approval THOMAS FINNILA
Green Building Final 11/28/2022 Approved THOMAS FINNILA
Final 1/13/2023 OK to Issue CofO DAVID MATSON