4343 W RUSSELL AVE 90027
Certificate Information: 4343 W RUSSELL AVE 90027
- Application / Permit
- 22014-10000-01871
- Plan Check / Job No.
- B22LA07207
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CHANGE OF USE FROM EXISTING DUPLEX TO SFD & MAJOR REMODEL AND 2ND FLOOR ADDIITON
- Permit Issued
- Issued on 5/30/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2022 | STARR CHEN |
| Corrections Issued | 5/27/2022 | STARR CHEN |
| Quality Review Completed | 6/1/2022 | KEN GILL |
| Building Plans Picked Up | 6/2/2022 | APPLICANT |
| Applicant returned to address corrections | 9/14/2022 | STARR CHEN |
| Plan Check Approved | 11/30/2022 | STARR CHEN |
| Issued | 5/30/2024 | APPLICANT |
| CofO in Progress | 11/17/2025 | ENRIQUE MIRELES |
| Permit Finaled | 11/19/2025 | DEROLD HAUFF |
| CofO Issued | 11/19/2025 | DEROLD HAUFF |
| Permit Finaled | 11/19/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/7/2022 | CINDY QI |
| Sewer availability | Cleared | 7/7/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 7/8/2022 | CINDY QI |
| Demo/Removal of Rental Units | Cleared | 9/13/2022 | SUSAN LIM |
| Grading Pre-Inspection | Cleared | 10/5/2022 | KIRK LINKLATER |
| GPI Written Notices | Cleared | 11/30/2022 | STARR CHEN |
Contact Information
| Architect | , ; Lic. No.: C39413 | 4341 RUSSELL AVE , |
| Contractor | Future Builders & Design Inc; Lic. No.: 1058468-B | 20252 ARCHWOOD ST WINNETKA, CA 91306 |
| Engineer | Danielson,, Mark Reuben; Lic. No.: L7882 | 25000 AVE STANFORD STE 141 VALENCIA, CA 91355 |
| Engineer | Khanjian,, Hovik J; Lic. No.: C51609 | 326 S. SPARKS STREET BURBANK, CA 91506 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/6/2024 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 6/6/2024 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2024 | Partial Approval | JEFFREY MEAD |
| ELECTRICAL-Rough | 10/22/2024 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 10/22/2024 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 10/22/2024 | Corrections Issued | ENRIQUE MIRELES |
| Deputy Wood Construction | 10/29/2024 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 10/30/2024 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 10/30/2024 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 10/30/2024 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 11/15/2024 | Corrections Issued | BRENDAN MORELLI |
| Interior/Exterior Lathing | 11/19/2024 | Partial Approval | BRENDAN MORELLI |
| Insulation | 11/22/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Insulation | 11/27/2024 | Approved | NICHOLAS LOPEZ |
| Shower Pan | 12/24/2024 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 12/30/2024 | Approved | ENRIQUE MIRELES |
| Pre-Inspection | 1/3/2025 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 1/17/2025 | Approved | ALEX COLIN |
| Final | 8/29/2025 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 8/29/2025 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 8/29/2025 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 8/29/2025 | Approved | ENRIQUE MIRELES |
| Final | 9/16/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 9/23/2025 | OK to Issue CofO | ENRIQUE MIRELES |
| Service/Power Release | 9/23/2025 | Approved | ENRIQUE MIRELES |