949 S HIGHLAND AVE 90036
Certificate Information: 949 S HIGHLAND AVE 90036
- Application / Permit
- 22014-10000-01863
- Plan Check / Job No.
- B22LA07184
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- REMODEL EXISTING BEDROOM, BATHROOM, DEN, ADD NEW LAUNDRY NOOK, PANTRY, STORAGE, AND ATTACHED TRELLIS PATIO COVER (400 SF).
- Permit Issued
- Issued on 8/23/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2022 | KHUONG TRUONG |
| Corrections Issued | 5/14/2022 | KHUONG TRUONG |
| Building Plans Picked Up | 5/17/2022 | APPLICANT |
| Applicant returned to address corrections | 7/11/2022 | JAD BASMA |
| Applicant returned to address corrections | 7/21/2022 | ZAW HAN |
| Issued | 8/23/2022 | APPLICANT |
| CofO in Progress | 4/25/2024 | RICHARD DOCKUS |
| CofO Issued | 4/29/2024 | DEROLD HAUFF |
| Permit Finaled | 4/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/26/2022 | STEVE MELGAR |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Manoukian,, Krikor Kerop; Lic. No.: C87010 | 2310 W MAGNOLIA BLVD STE A BURBANK, CA 91506 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/30/2022 | Approved | RICHARD DOCKUS |
| Excavation/Setback/Form/Re-Bar | 4/4/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 4/4/2023 | Approved | MICHAEL LEWIS |
| METHANE-Barrier | 4/4/2023 | Approved | MICHAEL LEWIS |
| METHANE-Subgrade | 4/4/2023 | Approved | MICHAEL LEWIS |
| Deputy Drilled-In Anchors | 4/5/2023 | Conditional Approval | RICHARD DOCKUS |
| Pre-Inspection | 5/24/2023 | Approved | RICHARD DOCKUS |
| Footing/Foundation/Slab | 6/1/2023 | Corrections Issued | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 9/12/2023 | Approved | RICHARD DOCKUS |
| METHANE-Rough | 9/12/2023 | Approved | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2023 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 9/15/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Shower Pan | 9/15/2023 | Approved | RONNIE MINDANAO |
| Insulation | 9/20/2023 | Corrections Issued | RONNIE MINDANAO |
| Interior/Exterior Lathing | 9/20/2023 | Approved | RONNIE MINDANAO |
| Insulation | 9/22/2023 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 9/22/2023 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 10/2/2023 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 4/4/2024 | Conditional Approval | RONNIE MINDANAO |
| Final | 4/4/2024 | Corrections Issued | RONNIE MINDANAO |
| Footing/Foundation/Slab | 4/4/2024 | Approved | RONNIE MINDANAO |
| Green Building Final | 4/4/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Green Building Rough | 4/4/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 4/4/2024 | SGSOV Not Ready | RONNIE MINDANAO |
| Smoke Detectors | 4/4/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 4/9/2024 | Approved | RONNIE MINDANAO |
| Final | 4/9/2024 | Corrections Issued | RONNIE MINDANAO |
| Green Building Final | 4/9/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Green Building Rough | 4/9/2024 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 4/9/2024 | SGSOV Not Ready | RONNIE MINDANAO |
| Smoke Detectors | 4/9/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Wood Frame | 4/9/2024 | Approved | RONNIE MINDANAO |
| Final | 4/19/2024 | OK to Issue CofO | RICHARD DOCKUS |
| Green Building Final | 4/19/2024 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 4/19/2024 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 4/19/2024 | Approved | RICHARD DOCKUS |