631 1/2 N ROBINSON ST 90026
Certificate Information: 631 1/2 N ROBINSON ST 90026
- Application / Permit
- 22014-10000-01861
- Plan Check / Job No.
- B22LA07182
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (1) NEW WASHER AND DRYER-EXTERIOR ENCLOSURES. STEEL SFD CONSTRUCTION. 2 OF 2
- Permit Issued
- Issued on 7/7/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/2/2022 | KHUONG TRUONG |
| Corrections Issued | 5/3/2022 | KHUONG TRUONG |
| Building Plans Picked Up | 5/6/2022 | APPLICANT |
| Applicant returned to address corrections | 5/23/2022 | SHANGQIN XIE |
| Plan Check Approved | 7/1/2022 | ZAW HAN |
| Issued | 7/7/2022 | APPLICANT |
| CofO in Progress | 8/8/2023 | FREDDIE RIVERA |
| Permit Finaled | 8/21/2023 | DEROLD HAUFF |
| CofO Issued | 8/21/2023 | DEROLD HAUFF |
| Permit Finaled | 8/21/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/17/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 5/18/2022 | JEANIE LAM |
| Tenant Habitability Plan | Cleared | 6/13/2022 | RICARDO BOHORQUEZ |
| Grading Pre-Inspection | Cleared | 6/28/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khazra,, Afshin; Lic. No.: C50250 | 22855 PAUL REVERE DR CALABASAS, CA 91302 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/28/2022 | Not Ready for Inspection | RAFAEL CORTES |
| METHANE-Barrier | 11/28/2022 | Not Ready for Inspection | RAFAEL CORTES |
| METHANE-Subgrade | 11/28/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Footing/Foundation/Slab | 12/14/2022 | Approved | FREDDIE RIVERA |
| METHANE-Barrier | 12/14/2022 | Approved | FREDDIE RIVERA |
| METHANE-Subgrade | 12/14/2022 | Approved | FREDDIE RIVERA |
| Light Gage Steel Frame | 2/28/2023 | Approved | FREDDIE RIVERA |
| Final | 4/13/2023 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 4/13/2023 | Approved | STUART CHAPMAN |
| Green Building Rough | 4/13/2023 | Approved | STUART CHAPMAN |
| METHANE-Final | 4/13/2023 | Approved | STUART CHAPMAN |
| METHANE-Rough | 4/13/2023 | Approved | STUART CHAPMAN |
| Smoke Detectors | 4/13/2023 | Approved | STUART CHAPMAN |
| Wood Frame | 4/13/2023 | Approved | STUART CHAPMAN |
| Light Gage Steel Frame | 5/11/2023 | Partial Inspection | FREDDIE RIVERA |
| Final | 7/5/2023 | Partial Approval | ALIZAH MAYAGOITIA |