(2) NEW WASHER AND DRYER-EXTERIOR ENCLOSURES. STEEL STD CONSTRUCTION. 1 OF 2
Permit Issued
Issued on 7/7/2022
Issuing Office
Metro
Current Status
CofO Issued on 8/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/21/2022 APPLICANT
Assigned to Plan Check Engineer 5/2/2022 KHUONG TRUONG
Corrections Issued 5/3/2022 KHUONG TRUONG
Building Plans Picked Up 5/6/2022 APPLICANT
Applicant returned to address corrections 5/23/2022 SHANGQIN XIE
Plan Check Approved 7/1/2022 ZAW HAN
Issued 7/7/2022 APPLICANT
CofO in Progress 8/8/2023 FREDDIE RIVERA
CofO Issued 8/21/2023 DEROLD HAUFF
Permit Finaled 8/21/2023 DEROLD HAUFF

Permit Application Clearance Information

Tenant Habitability Plan Cleared 5/16/2022 RICARDO BOHORQUEZ
Roof/Waste drainage to street Cleared 5/17/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 5/18/2022 JEANIE LAM
Grading Pre-Inspection Cleared 7/1/2022 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,
Engineer Khazra,, Afshin; Lic. No.: C50250 22855 PAUL REVERE DR      CALABASAS, CA 91302

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/28/2022 Not Ready for Inspection RAFAEL CORTES
METHANE-Barrier 11/28/2022 Not Ready for Inspection RAFAEL CORTES
METHANE-Subgrade 11/28/2022 Not Ready for Inspection RAFAEL CORTES
Footing/Foundation/Slab 12/12/2022 Approved FREDDIE RIVERA
METHANE-Barrier 12/12/2022 Approved FREDDIE RIVERA
METHANE-Subgrade 12/12/2022 Approved FREDDIE RIVERA
Pre-Inspection 12/12/2022 Approved FREDDIE RIVERA
Light Gage Steel Frame 2/28/2023 Approved FREDDIE RIVERA
Final 4/13/2023 Partial Inspection STUART CHAPMAN
Green Building Final 4/13/2023 Approved STUART CHAPMAN
Green Building Rough 4/13/2023 Approved STUART CHAPMAN
METHANE-Final 4/13/2023 Approved STUART CHAPMAN
METHANE-Rough 4/13/2023 Approved STUART CHAPMAN
Smoke Detectors 4/13/2023 Not Ready for Inspection STUART CHAPMAN
Wood Frame 4/13/2023 Approved STUART CHAPMAN
Final 7/5/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 7/5/2023 Approved ALIZAH MAYAGOITIA
Final 8/8/2023 OK to Issue CofO FREDDIE RIVERA