6024 N ALDEA AVE 91316
Certificate Information: 6024 N ALDEA AVE 91316
- Application / Permit
- 22014-10000-01846
- Plan Check / Job No.
- B22LA07081
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Existing 420 sq. ft garage with a new 487.72 sq ft. to be converted to ADU (907.72 sq ft total) per LAMC 12.22A.33(c)-(d)
- Permit Issued
- Issued on 8/16/2022
- Issuing Office
- Current Status
- CofO Issued on 5/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2022 | HANS SANTIAGO |
| Corrections Issued | 4/24/2022 | HANS SANTIAGO |
| Plan Check Approved | 5/24/2022 | ANDREW SANTIAGO |
| Issued | 8/16/2022 | APPLICANT |
| CofO in Progress | 5/17/2023 | JON MCHUGH |
| No Progress | 5/23/2023 | SEAN WIRCH |
| CofO in Progress | 5/23/2023 | JON MCHUGH |
| CofO in Progress | 5/23/2023 | JON MCHUGH |
| Permit Finaled | 5/23/2023 | JOHN JANSON |
| CofO Issued | 5/23/2023 | JOHN JANSON |
| Permit Finaled | 5/23/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/4/2022 | ROMAN GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 5/4/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 5/6/2022 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Southerland,, Richard Charles; Lic. No.: C88965 | 16526 BLACKHAWK ST GRANADA HILLS, CA 91344 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 10/31/2022 | No Access for Inspection | SEAN HAUPT |
| Deputy Drilled-In Anchors | 11/15/2022 | Approved | SEAN HAUPT |
| Sewer | 11/15/2022 | Approved | SEAN HAUPT |
| Deputy Drilled-In Anchors | 11/16/2022 | Partial Approval | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 11/23/2022 | Corrections Issued | DAVID SANDOVAL |
| Underground Mechanical | 11/23/2022 | Corrections Issued | DAVID SANDOVAL |
| Excavation/Setback/Form/Re-Bar | 12/6/2022 | Conditional Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 12/6/2022 | Corrections Issued | SEAN HAUPT |
| Underground Mechanical | 12/6/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2023 | Partial Approval | SEAN HAUPT |
| Deputy Wood Construction | 1/30/2023 | Conditional Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2023 | Approved | SEAN HAUPT |
| Rough-Elec/Plmb/HVAC | 2/7/2023 | Not Ready for Inspection | SEAN HAUPT |
| ELECTRICAL-Rough | 2/10/2023 | Approved | SEAN HAUPT |
| HVAC-Rough | 2/10/2023 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 2/10/2023 | Approved | SEAN HAUPT |
| Green Building Rough | 2/13/2023 | Not Ready for Inspection | JESUS PINEDA |
| Shower Pan | 2/13/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 2/17/2023 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 2/21/2023 | Approved | SEAN HAUPT |
| Green Building Rough | 2/21/2023 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 2/21/2023 | Approved | SEAN HAUPT |
| Insulation | 2/22/2023 | Approved | SEAN HAUPT |
| Drywall Nailing | 2/27/2023 | Corrections Issued | SEAN HAUPT |
| Drywall Nailing | 3/8/2023 | Corrections Issued | SEAN HAUPT |
| Footing/Foundation/Slab | 4/7/2023 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 4/7/2023 | SGSOV Not Ready | SEAN HAUPT |
| ELECTRICAL-Final | 4/17/2023 | Corrections Issued | JON MCHUGH |
| Final | 4/17/2023 | Corrections Issued | JON MCHUGH |
| Green Building Final | 4/17/2023 | Approved | JON MCHUGH |
| HVAC-Final | 4/17/2023 | Corrections Issued | JON MCHUGH |
| PLUMBING-Final | 4/17/2023 | Corrections Issued | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 4/17/2023 | SGSOV Not Ready | JON MCHUGH |
| Service/Power Release | 4/17/2023 | Not Ready for Inspection | JON MCHUGH |
| Smoke Detectors | 4/17/2023 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Final | 4/28/2023 | Not Ready for Inspection | SEAN HAUPT |
| Final | 4/28/2023 | Corrections Issued | SEAN HAUPT |
| HVAC-Final | 4/28/2023 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Final | 4/28/2023 | Not Ready for Inspection | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 4/28/2023 | SGSOV Approved | SEAN HAUPT |
| Service/Power Release | 4/28/2023 | Not Ready for Inspection | SEAN HAUPT |
| Smoke Detectors | 4/28/2023 | Not Ready for Inspection | SEAN HAUPT |
| Special/Order Compliance | 5/1/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 5/3/2023 | Not Ready for Inspection | JON MCHUGH |
| Final | 5/3/2023 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Final | 5/3/2023 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Final | 5/3/2023 | Not Ready for Inspection | JON MCHUGH |
| Service/Power Release | 5/3/2023 | Not Ready for Inspection | JON MCHUGH |
| Smoke Detectors | 5/3/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 5/8/2023 | Not Ready for Inspection | JON MCHUGH |
| Final | 5/8/2023 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Final | 5/8/2023 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Final | 5/8/2023 | Not Ready for Inspection | JON MCHUGH |
| Pre-Inspection | 5/8/2023 | Not Ready for Inspection | JON MCHUGH |
| Service/Power Release | 5/8/2023 | Not Ready for Inspection | JON MCHUGH |
| Special/Order Compliance | 5/8/2023 | Partial Inspection | SEAN WIRCH |
| ELECTRICAL-Final | 5/11/2023 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Final | 5/11/2023 | Approved | JON MCHUGH |
| PLUMBING-Final | 5/11/2023 | Approved | JON MCHUGH |
| Service/Power Release | 5/11/2023 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Final | 5/17/2023 | Approved | JON MCHUGH |
| Final | 5/17/2023 | OK to Issue CofO | JON MCHUGH |
| Service/Power Release | 5/17/2023 | Approved | JON MCHUGH |