118-120 W OPP ST 90744

Certificate Information: 118-120 W OPP ST 90744

Application / Permit
22014-10000-01844
Plan Check / Job No.
B22LA07057
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. 2-story accessory dwelling unit (ADU) [per LA Ordinace 12.22A33] addtiion to existing single family dwelling (sfd). Remodel SFD to have 2 bathrooms.
Permit Issued
Issued on 8/15/2023
Issuing Office
Current Status
CofO Issued on 9/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/19/2022 APPLICANT
Assigned to Plan Check Engineer 5/19/2022 TU HUA
Corrections Issued 5/27/2022 TU HUA
Quality Review Completed 6/8/2022 CHAD DOI
Applicant returned to address corrections 8/17/2022 TU HUA
Applicant returned to address corrections 5/26/2023 TU HUA
Plan Check Approved 8/4/2023 TU HUA
Issued 8/15/2023 APPLICANT
CofO in Progress 9/24/2025 JOSEPH MCGARRY
Permit Finaled 9/24/2025 ANSON MAGLASANG
CofO Issued 9/24/2025 ANSON MAGLASANG
Permit Finaled 9/24/2025 ANSON MAGLASANG

Permit Application Clearance Information

"Q" conditions Cleared 7/7/2022 ANACANY HURTADO
Clean Up Green Up Cleared 7/7/2022 ANACANY HURTADO
Address approval Cleared 7/13/2022 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 7/18/2022 JOSE HERNANDEZ
Sewer availability Cleared 7/18/2022 JOSE HERNANDEZ
Low Impact Development Cleared 5/11/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 5/15/2023 ANA SORIANO

Contact Information

Architect Gutierrez,, Juan Antonio; Lic. No.: C33231 15622 PATRONELLA AVENUE      GARDENA, CA 90249
Contractor Rudys Handyman And Construction; Lic. No.: 1036421-B       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/31/2024 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 7/31/2024 Not Ready for Inspection EUGENE CASSIDY
METHANE-Barrier 7/31/2024 Approved EUGENE CASSIDY
METHANE-Subgrade 7/31/2024 Approved EUGENE CASSIDY
PLUMBING-Rough 7/31/2024 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 8/6/2024 Corrections Issued EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 8/7/2024 Conditional Approval EUGENE CASSIDY
Special/Order Compliance 8/7/2024 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 8/20/2024 Partial Approval EUGENE CASSIDY
Green Building Rough 8/20/2024 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 8/20/2024 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 9/23/2024 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 9/23/2024 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 9/23/2024 Not Ready for Inspection EUGENE CASSIDY
Insulation 9/23/2024 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 9/23/2024 Corrections Issued EUGENE CASSIDY
Wood Frame 9/23/2024 Not Ready for Inspection EUGENE CASSIDY
Deputy Wood Construction 9/25/2024 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 9/25/2024 Partial Approval JOSEPH MCGARRY
HVAC-Rough 9/25/2024 Corrections Issued JOSEPH MCGARRY
PLUMBING-Rough 9/25/2024 Partial Approval JOSEPH MCGARRY
Shower Pan 9/25/2024 Partial Approval JOSEPH MCGARRY
Wood Frame 9/25/2024 Partial Approval JOSEPH MCGARRY
Drywall Nailing 10/2/2024 Partial Approval EUGENE CASSIDY
Green Building Rough 10/2/2024 Partial Approval EUGENE CASSIDY
HVAC-Rough 10/2/2024 Partial Approval EUGENE CASSIDY
Insulation 10/2/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 10/2/2024 Partial Approval EUGENE CASSIDY
Drywall Nailing 10/18/2024 Approved EUGENE CASSIDY
Green Building Rough 10/18/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 10/18/2024 Approved EUGENE CASSIDY
Shower Pan 10/18/2024 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 5/14/2025 Approved EUGENE CASSIDY
Final 5/14/2025 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 5/14/2025 Approved EUGENE CASSIDY
Green Building Final 5/14/2025 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 5/14/2025 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 5/14/2025 Approved EUGENE CASSIDY
Final 8/6/2025 Corrections Issued JOSEPH MCGARRY
Green Building Final 8/6/2025 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 8/6/2025 SGSOV Approved JOSEPH MCGARRY
Service/Power Release 8/6/2025 Approved JOSEPH MCGARRY
Final 9/22/2025 OK to Issue CofO JOSEPH MCGARRY
Service/Power Release 9/22/2025 Approved JOSEPH MCGARRY