4533 N SUNNYSLOPE AVE 91423
Certificate Information: 4533 N SUNNYSLOPE AVE 91423
- Application / Permit
- 22014-10000-01832
- Plan Check / Job No.
- B22LA07013
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: (N) EGRESS AND INGRESS ADDITION AND CONVERT (E) GRAGE TO 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 7/15/2023
- Issuing Office
- Current Status
- CofO Issued on 6/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/18/2022 | DANIEL YIP |
| Corrections Issued | 5/19/2022 | DANIEL YIP |
| Applicant returned to address corrections | 7/1/2022 | DANIEL YIP |
| Plan Check Approved | 5/2/2023 | DANIEL YIP |
| Issued | 7/15/2023 | APPLICANT |
| CofO in Progress | 6/6/2024 | JOHN COLEMAN |
| Permit Finaled | 6/22/2024 | RUBEN SALAS |
| CofO Issued | 6/22/2024 | RUBEN SALAS |
| Permit Finaled | 6/22/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/29/2022 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 6/29/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 6/29/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/5/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 7/5/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 7/5/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 7/5/2022 | MEGAN GODINEZ |
| ZI | Cleared | 7/7/2022 | JAZMIN ROQUE |
| Construction near power lines | Cleared | 8/18/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Bel Crest Builders Inc; Lic. No.: 616411-B | , |
| Engineer | Salto,, Alvaro; Lic. No.: NA83859 | , |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/9/2023 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 8/9/2023 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 8/11/2023 | Corrections Issued | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 8/11/2023 | Approved | MISAEL ESPARZA |
| Underground Mechanical | 8/11/2023 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 10/25/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 10/25/2023 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 10/25/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 10/25/2023 | Corrections Issued | MISAEL ESPARZA |
| MERV13>=Rough | 10/25/2023 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 10/25/2023 | Conditional Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 11/27/2023 | Partial Approval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 11/27/2023 | Approved | MISAEL ESPARZA |
| Green Building Rough | 11/27/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 11/27/2023 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 11/27/2023 | Approved | MISAEL ESPARZA |
| Rough-Elec/Plmb/HVAC | 11/27/2023 | Approved | MISAEL ESPARZA |
| Insulation | 12/6/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 12/6/2023 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 12/14/2023 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 12/20/2023 | Approved | MISAEL ESPARZA |
| Green Building Rough | 12/20/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 2/8/2024 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 3/15/2024 | Partial Inspection | MISAEL ESPARZA |
| Sewer | 3/15/2024 | Corrections Issued | MISAEL ESPARZA |
| Sewer | 3/19/2024 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 6/3/2024 | Approved | MISAEL ESPARZA |
| Final | 6/3/2024 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 6/3/2024 | Approved | MISAEL ESPARZA |
| Green Building Final | 6/3/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| MERV13>=Final | 6/3/2024 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 6/3/2024 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 6/3/2024 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 6/6/2024 | Approved | JOHN COLEMAN |
| Final | 6/6/2024 | OK to Issue CofO | JOHN COLEMAN |
| Green Building Final | 6/6/2024 | Approved | JOHN COLEMAN |
| HVAC-Final | 6/6/2024 | Approved | JOHN COLEMAN |
| PLUMBING-Final | 6/6/2024 | Approved | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 6/6/2024 | SGSOV Approved | JOHN COLEMAN |
| Smoke Detectors | 6/6/2024 | Approved | JOHN COLEMAN |