2941 S VICTORIA AVE 90016

Certificate Information: 2941 S VICTORIA AVE 90016

Application / Permit
22014-10000-01819
Plan Check / Job No.
B22LA06993
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED [18 X 18] GARAGE INTO 674.5 SF ONE BEDROOM ADU PER 12.22A33. ADD 17 X 22 PORTION.
Permit Issued
Issued on 10/20/2022
Issuing Office
San Pedro
Current Status
Issued on 10/20/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/21/2022 APPLICANT
Assigned to Plan Check Engineer 5/2/2022 JESSE JIMENEZ
Corrections Issued 5/3/2022 JESSE JIMENEZ
Building Plans Picked Up 5/6/2022 APPLICANT
Applicant returned to address corrections 9/6/2022 MINA HABILI
Plan Check Approved 10/4/2022 ADAM HEGAZI
Issued 10/20/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/16/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 6/14/2022 STEVE MELGAR
Sewer availability Cleared 6/14/2022 STEVE MELGAR
Low Impact Development Cleared 8/29/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 9/1/2022 TREVOR QUAN
Construction near power lines Cleared 9/6/2022 OSCAR CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Acciani,, Mark; Lic. No.: C83929 PO BOX 1390      RUNNING SPRINGS, CA 92382

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/28/2022 Conditional Approval FREDDIE RIVERA
Sewer 1/6/2023 Approved MICHAEL LEWIS
Pre-Inspection 1/9/2023 Partial Inspection CALEB MEISTER
Footing/Foundation/Slab 2/27/2023 Approved CALEB MEISTER
BUILDING-Rough-Frame 8/8/2023 Not Ready for Inspection CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 8/8/2023 Approved CALEB MEISTER
Green Building Rough 8/8/2023 Not Ready for Inspection CALEB MEISTER
Green Building Rough 6/6/2024 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 6/6/2024 Partial Approval JUSTIN HAWLEY
Pre-Inspection 6/6/2024 Approved JUSTIN HAWLEY
PLUMBING-Rough 6/17/2024 Corrections Issued JUSTIN HAWLEY
Underground Mechanical 6/18/2024 Approved JUSTIN HAWLEY
Pre-Inspection 9/18/2024 Approved JUSTIN HAWLEY
Rough-Elec/Plmb/HVAC 9/18/2024 Corrections Issued JUSTIN HAWLEY
ELECTRICAL-Rough 9/20/2024 Approved WILLIAM SIERRA
PLUMBING-Rough 9/20/2024 Not Ready for Inspection WILLIAM SIERRA
BUILDING-Rough-Frame 10/25/2024 Approved JUSTIN HAWLEY
Rough-Elec/Plmb/HVAC 10/25/2024 Approved JUSTIN HAWLEY
Insulation 11/4/2024 Approved JUSTIN HAWLEY
Drywall Nailing 12/12/2024 Approved JOSH MEISTER
Gas Test 4/2/2025 Approved JOSH MEISTER
Underground Mechanical 5/5/2025 Approved ALEX COLIN
ELECTRICAL-Rough 5/22/2025 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Final 9/8/2025 Not Ready for Inspection ARTHUR NEGRETE
Special/Order Compliance 9/8/2025 Partial Inspection OSVALDO PARAMO
ELECTRICAL-Final 9/22/2025 Approved JUSTIN HAWLEY