2941 S VICTORIA AVE 90016
Certificate Information: 2941 S VICTORIA AVE 90016
- Application / Permit
- 22014-10000-01819
- Plan Check / Job No.
- B22LA06993
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED [18 X 18] GARAGE INTO 674.5 SF ONE BEDROOM ADU PER 12.22A33. ADD 17 X 22 PORTION.
- Permit Issued
- Issued on 10/20/2022
- Issuing Office
- San Pedro
- Current Status
- Issued on 10/20/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/2/2022 | JESSE JIMENEZ |
| Corrections Issued | 5/3/2022 | JESSE JIMENEZ |
| Building Plans Picked Up | 5/6/2022 | APPLICANT |
| Applicant returned to address corrections | 9/6/2022 | MINA HABILI |
| Plan Check Approved | 10/4/2022 | ADAM HEGAZI |
| Issued | 10/20/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/16/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 6/14/2022 | STEVE MELGAR |
| Low Impact Development | Cleared | 8/29/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 9/1/2022 | TREVOR QUAN |
| Construction near power lines | Cleared | 9/6/2022 | OSCAR CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Acciani,, Mark; Lic. No.: C83929 | PO BOX 1390 RUNNING SPRINGS, CA 92382 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/28/2022 | Conditional Approval | FREDDIE RIVERA |
| Sewer | 1/6/2023 | Approved | MICHAEL LEWIS |
| Pre-Inspection | 1/9/2023 | Partial Inspection | CALEB MEISTER |
| Footing/Foundation/Slab | 2/27/2023 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 8/8/2023 | Not Ready for Inspection | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2023 | Approved | CALEB MEISTER |
| Green Building Rough | 8/8/2023 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Rough | 6/6/2024 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 6/6/2024 | Partial Approval | JUSTIN HAWLEY |
| Pre-Inspection | 6/6/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Rough | 6/17/2024 | Corrections Issued | JUSTIN HAWLEY |
| Underground Mechanical | 6/18/2024 | Approved | JUSTIN HAWLEY |
| Pre-Inspection | 9/18/2024 | Approved | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 9/18/2024 | Corrections Issued | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 9/20/2024 | Approved | WILLIAM SIERRA |
| PLUMBING-Rough | 9/20/2024 | Not Ready for Inspection | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 10/25/2024 | Approved | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 10/25/2024 | Approved | JUSTIN HAWLEY |
| Insulation | 11/4/2024 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 12/12/2024 | Approved | JOSH MEISTER |
| Gas Test | 4/2/2025 | Approved | JOSH MEISTER |
| Underground Mechanical | 5/5/2025 | Approved | ALEX COLIN |
| ELECTRICAL-Rough | 5/22/2025 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Final | 9/8/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Special/Order Compliance | 9/8/2025 | Partial Inspection | OSVALDO PARAMO |
| ELECTRICAL-Final | 9/22/2025 | Approved | JUSTIN HAWLEY |