4364 S WESTLAWN AVE 90066

Certificate Information: 4364 S WESTLAWN AVE 90066

Application / Permit
22014-10000-01813
Plan Check / Job No.
B22LA06972
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
GROUND FLOOR ADDITION AND CONVERT EXISTING DETACHED GARAGE AND RECREATION ROOM TO A NEW ACCESSORY DWELLING UNIT WITH AN ATTACHED ENTRY PORCH PER LAMC 12.22 A.33(b)(1)). WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 8/5/2025
Issuing Office
Current Status
CofO Issued on 4/7/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/18/2022 APPLICANT
Assigned to Plan Check Engineer 4/20/2022 ARSALAN SHABESTARI
Corrections Issued 4/26/2022 ARSALAN SHABESTARI
Applicant returned to address corrections 7/26/2023 ARSALAN SHABESTARI
Plan Check Approved 8/4/2023 ARSALAN SHABESTARI
No Progress 10/25/2024 DAVID CASTILLO
Plan Check Approved 8/1/2025 DAVID CASTILLO
Issued 8/5/2025 APPLICANT
CofO in Progress 4/2/2026 ANTHONY EGSON
Permit Finaled 4/7/2026 RICHARD STEINBACH
CofO Issued 4/7/2026 RICHARD STEINBACH
Permit Finaled 4/7/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 5/19/2022 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 5/19/2022 JENSON LEE
Sewer availability Cleared 5/19/2022 JENSON LEE
Specific Plan Cleared 6/30/2022 FREDDY GARCIA
Construction near power lines Cleared 9/7/2022 RIDWAN HARDY
Construction within easement Cleared 9/7/2022 RIDWAN HARDY
Roof/Waste drainage to street Cleared 7/15/2023 AHMED AMARRAGY
Specific Plan Cleared 1/7/2025 FREDDY GARCIA

Contact Information

Architect Holden,, Clay Franklin; Lic. No.: C31098 P O BOX 66113      LOS ANGELES, CA 90066
Contractor W A Construction Inc; Lic. No.: 1024282-B       ,
Engineer Paniagua,, Cristobal; Lic. No.: C72894 5956 WEST BLVD      LOS ANGELES, CA 90043

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/3/2025 Partial Approval RUBEN RIVAS
Underground Mechanical 9/16/2025 Partial Approval RUBEN RIVAS
Footing/Foundation/Slab 9/23/2025 Approved RUBEN RIVAS
Footing/Foundation/Slab 9/30/2025 Approved RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 10/15/2025 Approved RUBEN RIVAS
Deputy Wood Construction 10/16/2025 Conditional Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 10/20/2025 Approved RUBEN RIVAS
BUILDING-Rough-Frame 11/5/2025 Approved RUBEN RIVAS
ELECTRICAL-Rough 11/5/2025 Approved RUBEN RIVAS
Green Building Rough 11/5/2025 Approved RUBEN RIVAS
HVAC-Rough 11/5/2025 Approved RUBEN RIVAS
PLUMBING-Rough 11/5/2025 Approved RUBEN RIVAS
Interior/Exterior Lathing 11/25/2025 Not Ready for Inspection ANTHONY EGSON
Interior/Exterior Lathing 12/2/2025 Partial Approval RUBEN RIVAS
Wood Frame 12/4/2025 Approved RUBEN RIVAS
Insulation 12/16/2025 Approved ANTHONY EGSON
Shower Pan 12/16/2025 Approved ANTHONY EGSON
Interior/Exterior Lathing 12/30/2025 Partial Approval ANTHONY EGSON
Drywall Nailing 12/31/2025 Approved ANTHONY EGSON
Interior/Exterior Lathing 1/6/2026 Approved ANTHONY EGSON
Service/Power Release 1/23/2026 Partial Inspection ANTHONY EGSON
PLUMBING-Final 3/4/2026 Approved ANTHONY EGSON
ELECTRICAL-Final 3/16/2026 Approved ANTHONY EGSON
PLUMBING-Final 3/16/2026 Corrections Issued ANTHONY EGSON
PLUMBING-Final 3/23/2026 Approved ANTHONY EGSON
Green Building Final 3/26/2026 Approved ANTHONY EGSON
HVAC-Final 3/26/2026 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 3/31/2026 SGSOV Not Required ANTHONY EGSON
Smoke Detectors 3/31/2026 Approved ANTHONY EGSON
Final 4/1/2026 OK to Issue CofO ANTHONY EGSON