1040 E PALMS BLVD 90291
Certificate Information: 1040 E PALMS BLVD 90291
- Application / Permit
- 22014-10000-01808
- Plan Check / Job No.
- B22LA06959
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* ADDITION AND REMODEL TO (E) 1-STORY SFD WITH ATTACHED 2-CAR GARAGE.
- Permit Issued
- Issued on 5/24/2022
- Issuing Office
- Current Status
- CofO Issued on 2/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/20/2022 | VIVIAN LAO |
| Corrections Issued | 4/21/2022 | VIVIAN LAO |
| Plan Check Approved | 5/18/2022 | VIVIAN LAO |
| Issued | 5/24/2022 | APPLICANT |
| CofO in Progress | 2/10/2023 | EVAN COOPER |
| Permit Finaled | 2/14/2023 | DANIEL ORRANTE |
| CofO Issued | 2/14/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/14/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/2/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/3/2022 | DINAH GARIN |
Contact Information
| Architect | Murphy,, Brian Alfred; Lic. No.: NA23187 | , |
| Contractor | Owner-Builder | , |
| Engineer | Polon,, Gordon Leonard; Lic. No.: NA28564 | , |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/27/2022 | Partial Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 8/30/2022 | Corrections Issued | DAVID FEILER |
| Special/Order Compliance | 8/30/2022 | Partial Inspection | CLAYTON GRAHAM |
| Excavation/Setback/Form/Re-Bar | 9/6/2022 | Approved | DAVID FEILER |
| Footing/Foundation/Slab | 9/6/2022 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 9/13/2022 | Partial Approval | DAVID FEILER |
| ELECTRICAL-Rough | 9/13/2022 | Partial Approval | DAVID FEILER |
| Green Building Rough | 9/13/2022 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 9/13/2022 | Not Ready for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2022 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 9/15/2022 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 10/27/2022 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 10/27/2022 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2022 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 10/27/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Rough | 10/27/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 10/27/2022 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 11/3/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 11/3/2022 | Partial Approval | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 11/10/2022 | Corrections Issued | DAVID FEILER |
| Interior/Exterior Lathing | 11/14/2022 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 11/23/2022 | Approved | DAVID FEILER |
| Green Building Rough | 11/23/2022 | Corrections Issued | DAVID FEILER |
| Shower Pan | 11/23/2022 | Not Ready for Inspection | DAVID FEILER |
| Verify Sprinkler Sign Off | 11/23/2022 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 11/29/2022 | Approved | DAVID FEILER |
| Green Building Rough | 11/29/2022 | Approved | DAVID FEILER |
| Insulation | 11/29/2022 | Corrections Issued | DAVID FEILER |
| Insulation | 12/2/2022 | Approved | BRENDAN LOONEY |
| Drywall Nailing | 12/6/2022 | Approved | EVAN COOPER |
| Special/Order Compliance | 12/6/2022 | Partial Inspection | JEREMY TODD |
| Underground Mechanical | 12/6/2022 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 12/9/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 2/8/2023 | Approved | EVAN COOPER |
| Final | 2/8/2023 | Corrections Issued | EVAN COOPER |
| Green Building Final | 2/8/2023 | Approved | EVAN COOPER |
| HVAC-Final | 2/8/2023 | Approved | EVAN COOPER |
| PLUMBING-Final | 2/8/2023 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 2/8/2023 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 2/8/2023 | Approved | EVAN COOPER |
| Final | 2/10/2023 | OK to Issue CofO | EVAN COOPER |