513 N MUSEUM DR 90065
Certificate Information: 513 N MUSEUM DR 90065
- Application / Permit
- 22014-10000-01780
- Plan Check / Job No.
- B22LA06845
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT PART OF GARAGE INTO A JADU PER STATE CODE.
- Permit Issued
- Issued on 1/19/2023
- Issuing Office
- Current Status
- CofO in Progress on 6/11/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/20/2022 | JOE VO |
| Corrections Issued | 4/21/2022 | JOE VO |
| Applicant returned to address corrections | 10/19/2022 | JOE VO |
| Applicant returned to address corrections | 10/27/2022 | JOE VO |
| Plan Check Approved | 11/5/2022 | JOE VO |
| Issued | 1/19/2023 | APPLICANT |
| CofO in Progress | 12/7/2023 | ALIZAH MAYAGOITIA |
| No Progress | 12/8/2023 | SCOTT FINNILA |
| CofO in Progress | 6/5/2025 | ALIZAH MAYAGOITIA |
| CofO in Progress | 6/6/2025 | ALIZAH MAYAGOITIA |
| No Progress | 6/11/2025 | CHARLES BOGHOSKHAN |
| CofO in Progress | 6/11/2025 | CHARLES BOGHOSKHAN |
| CofO in Progress | 6/16/2025 | ALIZAH MAYAGOITIA |
Permit Application Clearance Information
| Specific Plan | Cleared | 11/2/2022 | NASHYA JENSEN |
| Address approval | Cleared | 11/3/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 11/3/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 11/3/2022 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Final | 2/22/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 2/22/2023 | Partial Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 3/24/2023 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 3/24/2023 | Approved | CRAIG VAUGHAN |
| Gas Test | 3/24/2023 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 3/24/2023 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 3/24/2023 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 3/24/2023 | Partial Approval | CRAIG VAUGHAN |
| Pre-Inspection | 3/24/2023 | Partial Approval | CRAIG VAUGHAN |
| Shower Pan | 3/24/2023 | Approved | CRAIG VAUGHAN |
| Smoke Detectors | 3/24/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 4/3/2023 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 4/3/2023 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 4/3/2023 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 4/3/2023 | Approved | OSVALDO PARAMO |
| Smoke Detectors | 4/4/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Drywall Nailing | 4/12/2023 | Approved | OSVALDO PARAMO |
| Final | 10/2/2023 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 10/2/2023 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 10/2/2023 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 10/2/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Final | 12/6/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 12/6/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| HVAC-Final | 12/6/2023 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 12/6/2023 | Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 12/6/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 6/6/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Final | 6/16/2025 | Corrections Issued | ALIZAH MAYAGOITIA |