501 N LATIMER ROAD 90402
Certificate Information: 501 N LATIMER ROAD 90402
- Application / Permit
- 22014-10000-01748
- Plan Check / Job No.
- B22LA06707
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND REMODEL TO (E) SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 7/28/2022
- Issuing Office
- Current Status
- CofO Issued on 5/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2022 | LAMAR DAVIS |
| Corrections Issued | 5/2/2022 | LAMAR DAVIS |
| Building Plans Picked Up | 5/9/2022 | APPLICANT |
| Quality Review Completed | 5/10/2022 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 6/7/2022 | LAMAR DAVIS |
| Issued | 7/28/2022 | APPLICANT |
| CofO in Progress | 5/2/2025 | HERBERT GIRON |
| Permit Finaled | 5/14/2025 | RICHARD STEINBACH |
| CofO Issued | 5/14/2025 | RICHARD STEINBACH |
| Permit Finaled | 5/14/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 5/12/2022 | JOHN CONNEALLY |
| Coastal Zone | Cleared | 5/20/2022 | DALIA MOKAYED |
| Roof/Waste drainage to street | Cleared | 5/20/2022 | STEVEN JIN |
| ZA Case | Cleared | 5/20/2022 | DALIA MOKAYED |
| Eng Process Fee Ord 176,300 | Cleared | 5/28/2022 | STEVEN JIN |
| Grading Pre-Inspection | Cleared | 6/7/2022 | TIMOTHY POWELL |
Contact Information
| Contractor | Tm Design Build; Lic. No.: 1068098-B | 27475 YNEZ RD #349 TEMECULA, CA 92591 |
| Engineer | Baad,, Katherine Firestone; Lic. No.: C64669 | 5232 ZAKON RD TORRANCE, CA 90505 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/25/2022 | Corrections Issued | KEVIN SARGSYAN |
| Pre-Inspection | 10/25/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 11/10/2022 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 11/10/2022 | Partial Approval | KEVIN SARGSYAN |
| Underground Mechanical | 12/2/2022 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 12/6/2022 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 12/23/2022 | No Access for Inspection | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 1/13/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Steel/Welding | 2/7/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 2/17/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Deputy Reinf. Concrete | 2/22/2023 | Conditional Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 2/22/2023 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 2/22/2023 | Partial Approval | KEVIN SARGSYAN |
| Underground Mechanical | 4/7/2023 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 5/5/2023 | Partial Approval | OGANES TARAKHCHYAN |
| HVAC-Rough | 5/12/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Underground Mechanical | 5/12/2023 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 6/1/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 6/1/2023 | Approved | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 7/20/2023 | No Access for Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2023 | Approved | OGANES TARAKHCHYAN |
| Sewer | 8/9/2023 | Corrections Issued | KENNETH NAGLE |
| Sewer | 8/16/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Sewer | 8/29/2023 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 11/14/2023 | Partial Approval | HERBERT GIRON |
| Underground Mechanical | 11/14/2023 | Partial Approval | HERBERT GIRON |
| Deputy Steel/Welding | 11/15/2023 | Conditional Approval | ARAM AVEDISIAN |
| Underground Mechanical | 11/15/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| Wood Frame | 12/1/2023 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2023 | Partial Approval | ARAM AVEDISIAN |
| Reinforced Concrete Frame | 12/21/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 2/16/2024 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Rough | 2/16/2024 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 3/1/2024 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 3/8/2024 | Approved | EVAN COOPER |
| PLUMBING-Rough | 3/8/2024 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 3/15/2024 | Approved | ARAM AVEDISIAN |
| Insulation | 4/2/2024 | Approved | EVAN COOPER |
| Shower Pan | 4/2/2024 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 4/10/2024 | Partial Approval | ARAM AVEDISIAN |
| Drywall Nailing | 4/22/2024 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 4/22/2024 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 12/13/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 12/13/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 12/18/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 4/14/2025 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 4/14/2025 | Approved | HERBERT GIRON |
| Green Building Final | 4/14/2025 | Approved | HERBERT GIRON |
| HVAC-Final | 4/14/2025 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 4/14/2025 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 4/14/2025 | Approved | HERBERT GIRON |
| Structural Steel Frame | 4/14/2025 | Approved | HERBERT GIRON |
| Final | 4/29/2025 | Corrections Issued | HERBERT GIRON |
| Final | 5/2/2025 | OK to Issue CofO | HERBERT GIRON |
| Service/Power Release | 5/2/2025 | Approved | HERBERT GIRON |