1203 W 9TH ST 90731
Certificate Information: 1203 W 9TH ST 90731
- Application / Permit
- 22014-10000-01743
- Plan Check / Job No.
- B22LA06688
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 2ND FLOOR ADU (756 SF ) ADDITION WITHIN EXISTING GARAGE / REC ROOM BUILDING FOOTPRINT PER 12.22 A33 C & D
- Permit Issued
- Issued on 11/1/2022
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 5/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2022 | STARR CHEN |
| Corrections Issued | 5/16/2022 | STARR CHEN |
| Quality Review Completed | 5/18/2022 | KEN GILL |
| Applicant returned to address corrections | 9/19/2022 | STARR CHEN |
| Applicant returned to address corrections | 10/17/2022 | STARR CHEN |
| Plan Check Approved | 10/27/2022 | STARR CHEN |
| Issued | 11/1/2022 | APPLICANT |
| CofO in Progress | 5/3/2024 | AMANUEL BERHE |
| Permit Finaled | 5/3/2024 | JOEY BUCHANAN |
| CofO Issued | 5/3/2024 | JOEY BUCHANAN |
| Permit Finaled | 5/3/2024 | JOEY BUCHANAN |
Permit Application Clearance Information
| Address approval | Cleared | 6/29/2022 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 6/29/2022 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2022 | ERIK BEASLEY |
| Sewer availability | Cleared | 7/1/2022 | ERIK BEASLEY |
| Tenant Habitability Plan | Cleared | 8/29/2022 | MICHAEL SOTO |
| Hydrant and Access approval | Cleared | 9/6/2022 | GILBERT URREA |
| GPI Written Notices | Cleared | 9/19/2022 | STARR CHEN |
| Grading Pre-Inspection | Cleared | 9/19/2022 | STARR CHEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 2999 OVERLAND AVE STE 103 LOS ANGELES, CA 90064 |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/14/2023 | Approved | JOEY BUCHANAN |
| Pre-Inspection | 2/14/2023 | Corrections Issued | JOEY BUCHANAN |
| Green Building Rough | 6/28/2023 | Approved | AMANUEL BERHE |
| Wood Frame | 6/28/2023 | Approved | AMANUEL BERHE |
| Insulation | 7/24/2023 | Approved | JOEY BUCHANAN |
| Final | 12/27/2023 | Partial Approval | AMANUEL BERHE |
| Green Building Final | 12/27/2023 | Approved | AMANUEL BERHE |
| SGSOV-Seismic Gas S/O Valve | 12/27/2023 | SGSOV Approved | AMANUEL BERHE |
| Smoke Detectors | 12/27/2023 | Approved | AMANUEL BERHE |
| Final | 5/3/2024 | OK to Issue CofO | AMANUEL BERHE |