3717 W 60TH ST 90043
Certificate Information: 3717 W 60TH ST 90043
- Application / Permit
- 22014-10000-01737
- Plan Check / Job No.
- B22LA06655
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF DETACHED GARAGE TO ADU WITH LOWER FLOOR STORAGE AND 2ND FLOOR ADDITION AND ROOF DECK. LOWER FLOOR STORAGE 101 S FT. ADU PER 12.22 A.33 (c) & d() 2 OF 2
- Permit Issued
- Issued on 12/1/2023
- Issuing Office
- Metro
- Current Status
- Issued on 12/1/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2022 | ADRIANA LOPEZ |
| Corrections Issued | 6/23/2022 | ADRIANA LOPEZ |
| Quality Review Completed | 6/24/2022 | FARUK SEZER |
| Building Plans Picked Up | 7/12/2022 | APPLICANT |
| Applicant returned to address corrections | 5/16/2023 | ADRIANA LOPEZ |
| Plan Check Approved | 6/7/2023 | ADRIANA LOPEZ |
| No Progress | 6/7/2023 | ADRIANA LOPEZ |
| Plan Check Approved | 6/7/2023 | ADRIANA LOPEZ |
| Issued | 12/1/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/28/2022 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 9/28/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 10/11/2022 | JEANIE LAM |
| Sewer availability | Cleared | 10/11/2022 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Truong,, Phong; Lic. No.: C70784 | 20439 E CRESTLINE DRIVE WALNUT, CA 91789 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/2/2024 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 2/7/2024 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 2/16/2024 | Corrections Issued | JOSE MACIAS |
| Deputy Drilled-In Anchors | 2/26/2024 | Approved | JOSE MACIAS |
| Footing/Foundation/Slab | 2/28/2024 | Conditional Approval | JOSE MACIAS |
| Pre-Inspection | 2/28/2024 | Not Ready for Inspection | JOSE MACIAS |
| Footing/Foundation/Slab | 3/8/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 5/21/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 5/21/2024 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 6/14/2024 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 6/14/2024 | Corrections Issued | JOSE MACIAS |
| PLUMBING-Rough | 6/25/2024 | Approved | JOSE MACIAS |
| Deputy Wood Construction | 7/30/2024 | Conditional Approval | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2024 | Approved | JOSE MACIAS |
| HVAC-Rough | 8/1/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 8/19/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 8/19/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 8/19/2024 | Corrections Issued | JOSE MACIAS |
| Insulation | 8/21/2024 | Approved | JOSE MACIAS |
| Drywall Nailing | 8/27/2024 | Corrections Issued | JOSE MACIAS |
| Shower Pan | 8/27/2024 | Approved | JOSE MACIAS |
| Drywall Nailing | 9/3/2024 | Approved | AMIR NAZARIAN |
| Pre-Inspection | 9/16/2024 | Approved | MICHAEL LEWIS |
| Sewer | 12/31/2024 | Approved | BARRY HACHE |
| Final | 4/27/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 4/27/2026 | Not Ready for Inspection | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 4/27/2026 | SGSOV Not Ready | SALVADOR MARTINEZ |
| Smoke Detectors | 4/27/2026 | Not Ready for Inspection | SALVADOR MARTINEZ |