710 S DEVON AVE 90024
Certificate Information: 710 S DEVON AVE 90024
- Application / Permit
- 22014-10000-01732
- Plan Check / Job No.
- B22LA06644
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED ADDITION- ELEVATOR SHAFT TO 2-STORY SFD
- Permit Issued
- Issued on 7/19/2022
- Issuing Office
- Metro
- Current Status
- Issued on 7/19/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/27/2022 | ADAM HEGAZI |
| Corrections Issued | 4/29/2022 | ADAM HEGAZI |
| Building Plans Picked Up | 5/9/2022 | APPLICANT |
| Plan Check Approved | 7/19/2022 | LUKE GONZALES |
| Issued | 7/19/2022 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/16/2022 | KIRK LINKLATER |
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2022 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 7/7/2022 | CINDY QI |
Contact Information
| Contractor | Libolt Design & Remodel Inc; Lic. No.: 549068-B | 85 544 TREVISTO DR INDIO, CA 92203 |
| Engineer | Vrtis,, Joseph Stanley; Lic. No.: C41216 | 12842 WRIGHT AVE CHINO, CA 917103261 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/1/2022 | Partial Inspection | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 9/21/2022 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 9/21/2022 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 10/11/2022 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 10/11/2022 | Not Ready for Inspection | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 10/26/2022 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 11/7/2022 | Corrections Issued | STEPHANIE SWANSON |
| Drywall Nailing | 11/14/2022 | Approved | CHRISTOPHER WILSON |
| Insulation | 11/14/2022 | Approved | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 2/28/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 2/28/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 2/28/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Green Building Final | 2/28/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 2/28/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 2/28/2023 | SGSOV Approved | GERMAN RODRIGUEZ MENDOZA |
| Smoke Detectors | 2/28/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |