1211 N AVENUE 49 90042

Certificate Information: 1211 N AVENUE 49 90042

Application / Permit
22014-10000-01722
Plan Check / Job No.
B22LA06601
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND CONVERT GARAGE TO 1-STORY ADU.
Permit Issued
Issued on 3/9/2023
Issuing Office
Metro
Current Status
CofO Issued on 3/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/13/2022 APPLICANT
Assigned to Plan Check Engineer 4/28/2022 ERIC WONG
Corrections Issued 4/30/2022 ERIC WONG
Quality Review Completed 5/12/2022 KEN GILL
Building Plans Picked Up 5/17/2022 APPLICANT
Plan Check Approved 10/20/2022 ERIC WONG
Issued 3/9/2023 APPLICANT
CofO in Progress 2/9/2024 ROY SPAULDING
Permit Finaled 3/21/2024 DEROLD HAUFF
CofO Issued 3/21/2024 DEROLD HAUFF
Permit Finaled 3/21/2024 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/15/2022 KIRK LINKLATER
Address approval Cleared 8/22/2022 ABEL CASILLAS
Roof/Waste drainage to street Cleared 8/22/2022 ABEL CASILLAS
Street Frontage Cleared 8/22/2022 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 8/29/2022 ABEL CASILLAS
Sewer availability Cleared 8/29/2022 ABEL CASILLAS
Green Code Cleared 9/15/2022 ERIC WONG
Miscellaneous Cleared 9/22/2022 DANIEL SCHNEIDEREIT

Contact Information

Contractor Instabuilt Construction Inc; Lic. No.: 1000012-B 1799 N HILL AVE      PASADENA, CA 91104
Engineer Zaarour,, Mikhael; Lic. No.: C68212 1016 VIA LA PAZ      SAN PEDRO, CA 90732

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/15/2023 Approved CRAIG VAUGHAN
PLUMBING-Rough 4/25/2023 Partial Approval CRAIG VAUGHAN
Deputy Drilled-In Anchors 4/26/2023 Conditional Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 4/27/2023 Approved CRAIG VAUGHAN
Wood Frame 5/19/2023 Partial Inspection OSVALDO PARAMO
BUILDING-Rough-Frame 6/12/2023 Conditional Approval JOAQUIN GREENOUGH
ELECTRICAL-Rough 6/12/2023 Approved JOAQUIN GREENOUGH
Green Building Rough 6/12/2023 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 6/12/2023 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 6/12/2023 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 6/15/2023 Partial Approval KATHRYN BUTTERWORTH
Green Building Rough 6/15/2023 Approved KATHRYN BUTTERWORTH
HVAC-Rough 6/15/2023 Partial Approval KATHRYN BUTTERWORTH
Insulation 6/15/2023 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 6/15/2023 Partial Approval KATHRYN BUTTERWORTH
Drywall Nailing 6/22/2023 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 7/12/2023 Partial Approval KATHRYN BUTTERWORTH
Sewer 9/26/2023 Approved THOMAS LOGRASSO
Underground Mechanical 9/26/2023 Partial Approval THOMAS LOGRASSO
Underground Mechanical 9/29/2023 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 11/3/2023 Approved ROY SPAULDING
ELECTRICAL-Final 11/3/2023 Partial Approval ROY SPAULDING
Final 11/3/2023 Corrections Issued ROY SPAULDING
Footing/Foundation/Slab 11/3/2023 Approved ROY SPAULDING
Green Building Final 11/3/2023 Partial Approval ROY SPAULDING
HVAC-Final 11/3/2023 Partial Approval ROY SPAULDING
PLUMBING-Final 11/3/2023 Partial Approval ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 11/3/2023 SGSOV Approved ROY SPAULDING
Smoke Detectors 11/3/2023 Approved ROY SPAULDING
ELECTRICAL-Final 11/15/2023 Approved ROY SPAULDING
Final 11/15/2023 Corrections Issued ROY SPAULDING
Green Building Final 11/15/2023 Approved ROY SPAULDING
HVAC-Final 11/15/2023 Approved ROY SPAULDING
PLUMBING-Final 11/15/2023 Approved ROY SPAULDING
Service/Power Release 11/15/2023 Approved ROY SPAULDING
Final 2/6/2024 OK to Issue CofO ROY SPAULDING