1211 N AVENUE 49 90042
Certificate Information: 1211 N AVENUE 49 90042
- Application / Permit
- 22014-10000-01722
- Plan Check / Job No.
- B22LA06601
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION AND CONVERT GARAGE TO 1-STORY ADU.
- Permit Issued
- Issued on 3/9/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2022 | ERIC WONG |
| Corrections Issued | 4/30/2022 | ERIC WONG |
| Quality Review Completed | 5/12/2022 | KEN GILL |
| Building Plans Picked Up | 5/17/2022 | APPLICANT |
| Plan Check Approved | 10/20/2022 | ERIC WONG |
| Issued | 3/9/2023 | APPLICANT |
| CofO in Progress | 2/9/2024 | ROY SPAULDING |
| Permit Finaled | 3/21/2024 | DEROLD HAUFF |
| CofO Issued | 3/21/2024 | DEROLD HAUFF |
| Permit Finaled | 3/21/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/15/2022 | KIRK LINKLATER |
| Address approval | Cleared | 8/22/2022 | ABEL CASILLAS |
| Roof/Waste drainage to street | Cleared | 8/22/2022 | ABEL CASILLAS |
| Street Frontage | Cleared | 8/22/2022 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 8/29/2022 | ABEL CASILLAS |
| Sewer availability | Cleared | 8/29/2022 | ABEL CASILLAS |
| Green Code | Cleared | 9/15/2022 | ERIC WONG |
| Miscellaneous | Cleared | 9/22/2022 | DANIEL SCHNEIDEREIT |
Contact Information
| Contractor | Instabuilt Construction Inc; Lic. No.: 1000012-B | 1799 N HILL AVE PASADENA, CA 91104 |
| Engineer | Zaarour,, Mikhael; Lic. No.: C68212 | 1016 VIA LA PAZ SAN PEDRO, CA 90732 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/15/2023 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 4/25/2023 | Partial Approval | CRAIG VAUGHAN |
| Deputy Drilled-In Anchors | 4/26/2023 | Conditional Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 4/27/2023 | Approved | CRAIG VAUGHAN |
| Wood Frame | 5/19/2023 | Partial Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 6/12/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 6/12/2023 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 6/12/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 6/12/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 6/12/2023 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 6/15/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Green Building Rough | 6/15/2023 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 6/15/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Insulation | 6/15/2023 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 6/15/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Drywall Nailing | 6/22/2023 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 7/12/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Sewer | 9/26/2023 | Approved | THOMAS LOGRASSO |
| Underground Mechanical | 9/26/2023 | Partial Approval | THOMAS LOGRASSO |
| Underground Mechanical | 9/29/2023 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 11/3/2023 | Approved | ROY SPAULDING |
| ELECTRICAL-Final | 11/3/2023 | Partial Approval | ROY SPAULDING |
| Final | 11/3/2023 | Corrections Issued | ROY SPAULDING |
| Footing/Foundation/Slab | 11/3/2023 | Approved | ROY SPAULDING |
| Green Building Final | 11/3/2023 | Partial Approval | ROY SPAULDING |
| HVAC-Final | 11/3/2023 | Partial Approval | ROY SPAULDING |
| PLUMBING-Final | 11/3/2023 | Partial Approval | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 11/3/2023 | SGSOV Approved | ROY SPAULDING |
| Smoke Detectors | 11/3/2023 | Approved | ROY SPAULDING |
| ELECTRICAL-Final | 11/15/2023 | Approved | ROY SPAULDING |
| Final | 11/15/2023 | Corrections Issued | ROY SPAULDING |
| Green Building Final | 11/15/2023 | Approved | ROY SPAULDING |
| HVAC-Final | 11/15/2023 | Approved | ROY SPAULDING |
| PLUMBING-Final | 11/15/2023 | Approved | ROY SPAULDING |
| Service/Power Release | 11/15/2023 | Approved | ROY SPAULDING |
| Final | 2/6/2024 | OK to Issue CofO | ROY SPAULDING |