19153-19155 W SYLVAN ST 91335

Certificate Information: 19153-19155 W SYLVAN ST 91335

Application / Permit
22014-10000-01695
Plan Check / Job No.
B22LA06539
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING ATTACHED GARAGE TO ACCESSORY DWELLING UNIT. AND CONVERT EXISTING CLOSET TO LAUNDRY CLOSET. ALL WORK PER WOOD FRAME PRESCRIPTIVE PROVISIONS
Permit Issued
Issued on 6/7/2022
Issuing Office
Metro
Current Status
CofO Issued on 12/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/14/2022 APPLICANT
Assigned to Plan Check Engineer 4/27/2022 GEORGE ALVAREZ
Corrections Issued 4/28/2022 GEORGE ALVAREZ
Building Plans Picked Up 4/29/2022 APPLICANT
Plan Check Approved 5/24/2022 STANLEY RAAP
Issued 6/7/2022 APPLICANT
CofO in Progress 12/23/2022 SEAN HAUPT
CofO Issued 12/28/2022 MICHAEL SMITH
Permit Finaled 12/28/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/13/2022 MEGAN GODINEZ
Sewer availability Cleared 5/13/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 5/16/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 5/16/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 5/16/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 5/16/2022 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/27/2022 Corrections Issued SEAN HAUPT
Footing/Foundation/Slab 8/2/2022 Not Ready for Inspection SEAN HAUPT
Deputy Drilled-In Anchors 8/12/2022 Partial Approval SEAN HAUPT
Excavation/Setback/Form/Re-Bar 8/18/2022 Approved SEAN HAUPT
Footing/Foundation/Slab 8/18/2022 Approved SEAN HAUPT
Sewer 8/18/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 9/26/2022 Partial Approval DAVID SANDOVAL
ELECTRICAL-Rough 9/26/2022 Corrections Issued DAVID SANDOVAL
Green Building Rough 9/26/2022 Not Ready for Inspection DAVID SANDOVAL
HVAC-Rough 9/26/2022 Approved DAVID SANDOVAL
PLUMBING-Rough 9/26/2022 Corrections Issued DAVID SANDOVAL
Sewer 9/26/2022 Not Ready for Inspection DAVID SANDOVAL
BUILDING-Rough-Frame 10/13/2022 Approved SEAN HAUPT
ELECTRICAL-Rough 10/13/2022 Approved SEAN HAUPT
Green Building Rough 10/13/2022 Approved SEAN HAUPT
Insulation 10/13/2022 Approved SEAN HAUPT
Interior/Exterior Lathing 10/13/2022 Approved SEAN HAUPT
PLUMBING-Rough 10/13/2022 Approved SEAN HAUPT
Drywall Nailing 10/21/2022 Approved SEAN HAUPT
Final 12/5/2022 Corrections Issued SEAN HAUPT
Green Building Final 12/5/2022 Not Ready for Inspection SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 12/5/2022 SGSOV Not Ready SEAN HAUPT
Smoke Detectors 12/5/2022 Approved SEAN HAUPT
Special/Order Compliance 12/5/2022 Partial Inspection MORRIS JACKSON
Final 12/23/2022 OK to Issue CofO SEAN HAUPT
Green Building Final 12/23/2022 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 12/23/2022 SGSOV Approved SEAN HAUPT