1219 W 47TH ST 90037
Certificate Information: 1219 W 47TH ST 90037
- Application / Permit
- 22014-10000-01671
- Plan Check / Job No.
- B22LA06370
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EXISTING 2 CAR GARAGE TO BE CONVERTED INTO A.D.U. UNIT AND PROPOSED 1 STORY ADDITION TO BE PART OF THE A.D.U. (TOTAL 700 SF A.D.U.) (1,200 SF max per Ordinance LAMC 12.22 A.33(c)-(d))
- Permit Issued
- Issued on 7/13/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2022 | KHUONG TRUONG |
| Corrections Issued | 5/5/2022 | KHUONG TRUONG |
| Building Plans Picked Up | 5/10/2022 | APPLICANT |
| Applicant returned to address corrections | 7/11/2022 | CRISTINA SALAZAR |
| Plan Check Approved | 7/13/2022 | AUNG SOE |
| Issued | 7/13/2022 | APPLICANT |
| CofO in Progress | 2/26/2024 | ALIZAH MAYAGOITIA |
| CofO Issued | 2/28/2024 | DEROLD HAUFF |
| Permit Finaled | 2/28/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/2/2022 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 6/2/2022 | AMAAN MALIK |
| Community Plan Implem. Overlay | Cleared | 6/13/2022 | RAFAEL FONTES |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 6/14/2022 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wu,, Harold Ping-Hung; Lic. No.: C35693 | 1168 SAN GABRIEL BLVD NO N ROSEMEAD, CA 91770 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/7/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 9/7/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Sewer | 9/7/2022 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 9/13/2022 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 11/29/2022 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 12/6/2022 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 12/23/2022 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Rough | 12/23/2022 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 1/10/2023 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Rough | 1/10/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 1/31/2023 | No Access for Inspection | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2023 | No Access for Inspection | STUART CHAPMAN |
| PLUMBING-Rough | 1/31/2023 | No Access for Inspection | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2023 | Conditional Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 2/2/2023 | No Access for Inspection | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2023 | No Access for Inspection | STUART CHAPMAN |
| PLUMBING-Rough | 2/2/2023 | No Access for Inspection | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2023 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 2/16/2023 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 2/16/2023 | Partial Approval | SABAS ALONSO |
| PLUMBING-Rough | 2/16/2023 | Corrections Issued | SABAS ALONSO |
| BUILDING-Rough-Frame | 2/21/2023 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 2/21/2023 | Approved | SABAS ALONSO |
| Green Building Rough | 2/21/2023 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 2/21/2023 | Partial Approval | SABAS ALONSO |
| PLUMBING-Rough | 2/21/2023 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 3/15/2023 | Approved | SABAS ALONSO |
| Insulation | 3/28/2023 | Approved | SABAS ALONSO |
| Insulation | 4/5/2023 | Approved | SABAS ALONSO |
| Drywall Nailing | 4/7/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 4/12/2023 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 8/18/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 8/18/2023 | Corrections Issued | STUART CHAPMAN |
| HVAC-Final | 8/18/2023 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Final | 8/18/2023 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Final | 9/28/2023 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Final | 9/28/2023 | Corrections Issued | RONNIE MINDANAO |
| ELECTRICAL-Final | 1/2/2024 | Corrections Issued | HERBERT GIRON |
| Final | 1/2/2024 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 1/2/2024 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 1/2/2024 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 1/2/2024 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 1/2/2024 | SGSOV Not Ready | HERBERT GIRON |
| Smoke Detectors | 1/2/2024 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 2/21/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 2/21/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Final | 2/21/2024 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 2/21/2024 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 2/21/2024 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 2/21/2024 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Final | 2/26/2024 | OK to Issue CofO | ALIZAH MAYAGOITIA |