9407 S WADSWORTH AVE 90002

Certificate Information: 9407 S WADSWORTH AVE 90002

Application / Permit
22014-10000-01665
Plan Check / Job No.
B22LA06357
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EXISTING TWO CAR GARAGE TO BE CONVERTED INTO ADU AND 1-STORY ADDITION PER ORDINANCE AND LAMC 12.22 A33(c)&(d).
Permit Issued
Issued on 8/2/2022
Issuing Office
Metro
Current Status
CofO Issued on 4/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/10/2022 APPLICANT
Assigned to Plan Check Engineer 4/15/2022 ZAW HAN
Corrections Issued 4/19/2022 ZAW HAN
Building Plans Picked Up 4/21/2022 APPLICANT
Applicant returned to address corrections 7/29/2022 ZAW HAN
Plan Check Approved 8/1/2022 CRISTINA SALAZAR
Issued 8/2/2022 APPLICANT
CofO in Progress 4/14/2023 JOHN KLARIN
CofO Issued 4/14/2023 ANSON MAGLASANG
Permit Finaled 4/14/2023 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 4/26/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 6/10/2022 STEVE MELGAR
Sewer availability Cleared 6/10/2022 STEVE MELGAR
Construction near power lines Cleared 7/27/2022 TINA MIRANDA
Low Impact Development Cleared 7/28/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 8/1/2022 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/17/2022 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 10/17/2022 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 11/9/2022 Corrections Issued JOHN KLARIN
Green Building Rough 11/9/2022 Approved JOHN KLARIN
Rough-Elec/Plmb/HVAC 11/9/2022 Corrections Issued JOHN KLARIN
HVAC-Rough 11/15/2022 Approved JOHN KLARIN
Interior/Exterior Lathing 11/15/2022 Approved JOHN KLARIN
Shower Pan 11/15/2022 Approved JOHN KLARIN
Underground Mechanical 11/15/2022 Partial Approval JOHN KLARIN
Insulation 11/21/2022 Approved JOHN KLARIN
Interior/Exterior Lathing 11/21/2022 Approved JOHN KLARIN
Drywall Nailing 11/28/2022 Approved JOHN KLARIN
Gas Test 1/3/2023 Approved JOHN KLARIN
Sewer 1/3/2023 Approved JOHN KLARIN
ELECTRICAL-Final 1/20/2023 Approved JOHN KLARIN
Gas Test 1/20/2023 Approved JOHN KLARIN
HVAC-Final 1/20/2023 Approved JOHN KLARIN
PLUMBING-Final 1/20/2023 Approved JOHN KLARIN
BUILDING-Rough-Frame 1/31/2023 Partial Approval JOHN KLARIN
Final 1/31/2023 Corrections Issued JOHN KLARIN
Green Building Final 1/31/2023 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 1/31/2023 SGSOV Approved JOHN KLARIN
Smoke Detectors 1/31/2023 Approved JOHN KLARIN
Pre-Inspection 2/16/2023 Approved JOHN KLARIN
BUILDING-Rough-Frame 2/27/2023 Approved JOHN KLARIN
Final 2/27/2023 Corrections Issued JOHN KLARIN
Green Building Final 2/27/2023 Approved JOHN KLARIN
ELECTRICAL-Final 3/13/2023 Approved JAMES CHAVEZ
Final 4/13/2023 OK to Issue CofO JOHN KLARIN