3421 1/2 W 77TH ST 90043

Certificate Information: 3421 1/2 W 77TH ST 90043

Application / Permit
22014-10000-01662
Plan Check / Job No.
B22LA06348
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT STORAGE AND (N) ADDITION TO (N) ATTACHED ADU (360SQFT TOTAL) TO (E) SFD W/ GARAGE
Permit Issued
Issued on 12/8/2022
Issuing Office
Metro
Current Status
CofO Issued on 5/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/18/2022 APPLICANT
Assigned to Plan Check Engineer 5/23/2022 FERNANDO FLORES
Corrections Issued 5/24/2022 FERNANDO FLORES
Building Plans Picked Up 5/26/2022 APPLICANT
Applicant returned to address corrections 6/30/2022 MINA HABILI
Plan Check Approved 9/21/2022 KHUONG TRUONG
Issued 12/8/2022 APPLICANT
CofO in Progress 3/14/2024 JOSE MACIAS
CofO Issued 5/17/2024 DEROLD HAUFF
Permit Finaled 5/17/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/7/2022 JEANIE LAM
Roof/Waste drainage to street Cleared 6/7/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 6/13/2022 JEANIE LAM
ZA Case Cleared 6/14/2022 RUBEN VASQUEZ
Tenant Habitability Plan Cleared 6/15/2022 MICHAEL SOTO
Sewer availability Cleared 6/17/2022 JEANIE LAM
Construction near power lines Cleared 8/31/2022 TINA MIRANDA

Contact Information

Contractor Schi Solutions Inc; Lic. No.: 1085283-B 8932 COLUBUS AVE APT 1      NORTH HILLS, CA 91343

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/20/2023 Approved ENRIQUE MIRELES
Underground Mechanical 3/23/2023 Approved ENRIQUE MIRELES
Deputy Drilled-In Anchors 4/13/2023 Approved ENRIQUE MIRELES
Sewer 4/14/2023 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 4/20/2023 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 5/17/2023 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 6/12/2023 Approved ENRIQUE MIRELES
Wood Frame 6/12/2023 Approved ENRIQUE MIRELES
Insulation 6/28/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 6/28/2023 Approved ENRIQUE MIRELES
Drywall Nailing 7/7/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 9/8/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Final 9/8/2023 Approved ENRIQUE MIRELES
Final 9/8/2023 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 9/8/2023 Approved ENRIQUE MIRELES
Gas Test 9/8/2023 Approved ENRIQUE MIRELES
Green Building Final 9/8/2023 Approved ENRIQUE MIRELES
Green Building Rough 9/8/2023 Approved ENRIQUE MIRELES
HVAC-Final 9/8/2023 Approved ENRIQUE MIRELES
PLUMBING-Final 9/8/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 9/8/2023 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 9/8/2023 Approved ENRIQUE MIRELES
Service/Power Release 9/25/2023 Approved ENRIQUE MIRELES
Final 3/13/2024 OK to Issue CofO JOSE MACIAS