968 N NORMAN PL 90049

Certificate Information: 968 N NORMAN PL 90049

Application / Permit
22014-10000-01650
Plan Check / Job No.
B22LA06305
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2ND STORY ADDITION TO EXISTING SINGLE FAMILY DWELLING.
Permit Issued
Issued on 12/8/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 2/19/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/13/2022 APPLICANT
Assigned to Plan Check Engineer 4/28/2022 QUAN NGHIEM
Corrections Issued 5/17/2022 QUAN NGHIEM
Quality Review Completed 5/18/2022 CHAD DOI
Building Plans Picked Up 5/27/2022 APPLICANT
Applicant returned to address corrections 1/24/2023 QUAN NGHIEM
Plan Check Approved 8/1/2023 QUAN NGHIEM
Issued 12/8/2023 APPLICANT
CofO in Progress 2/18/2026 EVAN COOPER
Permit Finaled 2/19/2026 RICHARD STEINBACH
CofO Issued 2/19/2026 RICHARD STEINBACH
Permit Finaled 2/19/2026 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/18/2022 KIRK LINKLATER
Hydrant and Access approval Cleared 11/14/2022 MATTHEW CRAIG
BHO/Hillside ordinance Cleared 12/22/2022 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 12/22/2022 ANTHONY MAINEZ
Sewer availability Cleared 12/22/2022 ANTHONY MAINEZ
Watercourse Cleared 2/1/2023 HISASHI KOBAYAKAWA
Low Impact Development Cleared 4/12/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 4/12/2023 AHMED AMARRAGY
BHO/Hillside ordinance Cleared 6/29/2023 AHMED AMARRAGY
BHO/Hillside ordinance Cleared 6/29/2023 AHMED AMARRAGY
BHO/Hillside ordinance Cleared 6/29/2023 AHMED AMARRAGY
BHO/Hillside ordinance Cleared 6/29/2023 AHMED AMARRAGY

Contact Information

Contractor Owner-Builder       ,
Engineer Chen,, Junfei; Lic. No.: C85841 50 OUTLAW      IRVINE, CA 92602

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 9/10/2024 Corrections Issued CARLOS MATAMOROS
BUILDING-Rough-Frame 9/12/2024 Partial Approval CARLOS MATAMOROS
FLOOD-Proofing Certificate 9/12/2024 Approved CARLOS MATAMOROS
Green Building Rough 9/12/2024 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Rough 9/12/2024 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 9/12/2024 Partial Approval CARLOS MATAMOROS
Verify Sprinkler Sign Off 9/12/2024 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 9/19/2024 Partial Approval CARLOS MATAMOROS
Wood Frame 9/19/2024 Partial Approval CARLOS MATAMOROS
Deputy Wood Construction 9/20/2024 Conditional Approval MICHAEL PELHAM
Deputy Wood Construction 10/21/2024 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 10/23/2024 Corrections Issued CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 10/29/2024 Partial Approval CARLOS MATAMOROS
Gas Test 10/29/2024 Approved CARLOS MATAMOROS
PLUMBING-Rough 10/29/2024 Partial Approval CARLOS MATAMOROS
HVAC-Rough 11/6/2024 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 12/16/2024 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 12/16/2024 Approved CARLOS MATAMOROS
Green Building Rough 12/16/2024 Approved CARLOS MATAMOROS
Insulation 3/4/2025 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 3/4/2025 Approved CARLOS MATAMOROS
Drywall Nailing 3/11/2025 Approved CARLOS MATAMOROS
Gas Test 5/2/2025 Approved CARLOS MATAMOROS
Shower Pan 5/2/2025 Approved CARLOS MATAMOROS
Underground Mechanical 5/2/2025 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 5/22/2025 Approved CARLOS MATAMOROS
Pre-Inspection 8/12/2025 Corrections Issued CARLOS MATAMOROS
Sewer 11/3/2025 Approved CARLOS MATAMOROS
Underground Mechanical 11/3/2025 Approved CARLOS MATAMOROS
Green Building Final 11/26/2025 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Final 11/26/2025 Approved CARLOS MATAMOROS
Service/Power Release 11/26/2025 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Final 12/8/2025 Approved CARLOS MATAMOROS
Service/Power Release 12/8/2025 Approved CARLOS MATAMOROS
Green Building Final 1/15/2026 Approved EVAN COOPER
PLUMBING-Final 1/15/2026 Approved EVAN COOPER
Final 2/6/2026 OK to Issue CofO EVAN COOPER
Footing/Foundation/Slab 2/6/2026 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 2/6/2026 SGSOV Approved EVAN COOPER
Smoke Detectors 2/6/2026 Approved EVAN COOPER