1918 W 41ST PL 90062

Certificate Information: 1918 W 41ST PL 90062

Application / Permit
22014-10000-01649
Plan Check / Job No.
B22LA06287
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* NEW 2-STORY DETACHED ADU PER LAMC 12.22A.33(c)-(d).
Permit Issued
Issued on 9/19/2023
Issuing Office
Current Status
Issued on 9/19/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/9/2022 APPLICANT
Assigned to Plan Check Engineer 4/15/2022 VIVIAN LAO
Corrections Issued 4/16/2022 VIVIAN LAO
Applicant returned to address corrections 5/19/2022 VIVIAN LAO
Plan Check Approved 9/8/2023 VIVIAN LAO
Issued 9/19/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/23/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 6/9/2022 JEANIE LAM
Sewer availability Cleared 6/9/2022 JEANIE LAM
Low Impact Development Cleared 9/15/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 9/20/2022 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Te,, Visal; Lic. No.: C77634 424 E CYPRESS AVE      MONROVIA, CA 91016

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/7/2023 Partial Approval SABAS ALONSO
Underground Mechanical 12/7/2023 Partial Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 12/18/2023 Approved SABAS ALONSO
Footing/Foundation/Slab 12/18/2023 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 3/21/2024 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/14/2024 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/29/2024 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 9/27/2024 Approved CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 12/12/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 12/23/2024 Partial Approval ANTHONY RAMOS
Green Building Rough 5/16/2025 Approved SABAS ALONSO
HVAC-Rough 5/16/2025 Approved SABAS ALONSO
ELECTRICAL-Rough 5/30/2025 Corrections Issued MICHAEL LEWIS
PLUMBING-Rough 5/30/2025 Corrections Issued MICHAEL LEWIS
Gas Test 6/12/2025 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 6/12/2025 Approved SABAS ALONSO
Underground Mechanical 6/12/2025 Approved SABAS ALONSO
ELECTRICAL-Rough 6/25/2025 Approved SABAS ALONSO
Sewer 6/25/2025 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 7/18/2025 Corrections Issued SABAS ALONSO
Verify Sprinkler Sign Off 7/18/2025 Not Ready for Inspection SABAS ALONSO
Insulation 8/21/2025 Conditional Approval JOSH MEISTER
BUILDING-Rough-Frame 9/16/2025 Partial Inspection ANTHONY RAMOS
Drywall Nailing 9/16/2025 Approved ANTHONY RAMOS
Insulation 9/16/2025 Approved ANTHONY RAMOS
Verify Sprinkler Sign Off 9/16/2025 Approved ANTHONY RAMOS
Shower Pan 3/10/2026 Partial Approval SABAS ALONSO
Shower Pan 3/24/2026 Approved MICHAEL LEWIS