717 E 99TH ST 90002
Certificate Information: 717 E 99TH ST 90002
- Application / Permit
- 22014-10000-01639
- Plan Check / Job No.
- B22LA06280
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* CONVERT PORTION OF (E) 2-CAR GARAGE TO ADU AND ADD TO A DU (585 SF) PER LAMC 12.22A.33(c)-(d).
- Permit Issued
- Issued on 6/12/2025
- Issuing Office
- Current Status
- Permit Finaled on 7/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/4/2022 | VIVIAN LAO |
| Corrections Issued | 5/5/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 6/7/2022 | VIVIAN LAO |
| Plan Check Approved | 10/25/2022 | VIVIAN LAO |
| Issued | 6/12/2025 | APPLICANT |
| Permit Finaled | 7/30/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 5/24/2022 | JEANETTE VONG |
| Construction within easement | Cleared | 7/6/2022 | TINA MIRANDA |
| Eng Process Fee Ord 176,300 | Cleared | 7/12/2022 | JEANETTE VONG |
| Low Impact Development | Cleared | 10/19/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 10/21/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 10/21/2022 | JEANETTE VONG |
Contact Information
| Contractor | L A Developing Inc; Lic. No.: 1083426-B | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/18/2025 | Approved | JOHN KLARIN |
| Drywall Nailing | 6/18/2025 | Approved | JOHN KLARIN |
| Final | 6/18/2025 | Conditional Approval | JOHN KLARIN |
| Footing/Foundation/Slab | 6/18/2025 | Approved | JOHN KLARIN |
| Green Building Final | 6/18/2025 | Approved | JOHN KLARIN |
| Green Building Rough | 6/18/2025 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 6/18/2025 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 6/18/2025 | Approved | JOHN KLARIN |