262-262 1/2 S ORANGE DR 90036
Certificate Information: 262-262 1/2 S ORANGE DR 90036
- Application / Permit
- 22014-10000-01636
- Plan Check / Job No.
- B22LA06277
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: CONVERT (E) 2-STORY RECREATION ROOM WITH ATTACHED GARAGE TO (N) 2-STORY ACCESSORY DWELLING UNIT WITH ATTACHED GARAGE PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 9/21/2022
- Issuing Office
- Current Status
- CofO Issued on 3/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2022 | DANIEL YIP |
| Corrections Issued | 4/14/2022 | DANIEL YIP |
| Applicant returned to address corrections | 4/30/2022 | DANIEL YIP |
| Plan Check Approved | 6/15/2022 | DANIEL YIP |
| Issued | 9/21/2022 | APPLICANT |
| CofO in Progress | 2/2/2023 | RICHARD DOCKUS |
| Permit Finaled | 3/18/2023 | DEROLD HAUFF |
| CofO Issued | 3/18/2023 | DEROLD HAUFF |
| Permit Finaled | 3/18/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/20/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/20/2022 | WALLIE JONG |
| Sewer availability | Cleared | 4/20/2022 | WALLIE JONG |
| Construction near power lines | Cleared | 6/14/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 10/6/2022 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 10/6/2022 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 10/6/2022 | Approved | JOSEPH MCGARRY |
| Insulation | 10/19/2022 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 12/2/2022 | No Access for Inspection | RICHARD DOCKUS |
| Drywall Nailing | 12/2/2022 | No Access for Inspection | RICHARD DOCKUS |
| Final | 12/2/2022 | No Access for Inspection | RICHARD DOCKUS |
| METHANE-Final | 12/2/2022 | No Access for Inspection | RICHARD DOCKUS |
| METHANE-Rough | 12/2/2022 | No Access for Inspection | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 12/2/2022 | SGSOV Not Ready | RICHARD DOCKUS |
| Smoke Detectors | 12/2/2022 | No Access for Inspection | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 12/14/2022 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 12/14/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 12/14/2022 | Corrections Issued | RICHARD DOCKUS |
| Final | 12/14/2022 | Corrections Issued | RICHARD DOCKUS |
| HVAC-Final | 12/14/2022 | Corrections Issued | RICHARD DOCKUS |
| METHANE-Final | 12/14/2022 | Approved | RICHARD DOCKUS |
| METHANE-Rough | 12/14/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 12/14/2022 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 12/14/2022 | SGSOV Not Ready | RICHARD DOCKUS |
| Smoke Detectors | 12/14/2022 | Approved | RICHARD DOCKUS |
| Final | 2/1/2023 | OK to Issue CofO | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 2/1/2023 | SGSOV Approved | RICHARD DOCKUS |