5833 W 78TH PL 90045
Certificate Information: 5833 W 78TH PL 90045
- Application / Permit
- 22014-10000-01609
- Plan Check / Job No.
- B22LA06229
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 515 SF OF ADDITION TO EXISTING SINGLE FAMILY DWELLING AND NEW DECK
- Permit Issued
- Issued on 5/2/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2022 | VARAND SARKISIAN |
| Corrections Issued | 4/26/2022 | VARAND SARKISIAN |
| Building Plans Picked Up | 4/27/2022 | APPLICANT |
| Plan Check Approved | 9/13/2022 | VARAND SARKISIAN |
| Issued | 5/2/2024 | APPLICANT |
| CofO in Progress | 11/27/2024 | BOBBY KEY |
| Permit Finaled | 12/3/2024 | RICHARD STEINBACH |
| CofO Issued | 12/3/2024 | RICHARD STEINBACH |
| Permit Finaled | 12/3/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Sewer availability | Cleared | 5/5/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2022 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 5/28/2022 | GILBERT URREA |
| Low Impact Development | Cleared | 8/9/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 8/25/2022 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 9/13/2022 | VARAND SARKISIAN |
Contact Information
| Architect | Bo, Kyle Sundius; Lic. No.: C38566 | , |
| Contractor | M D H Builders / Design / Development; Lic. No.: 1067773-B | 6700 FALLBROOK AVE 100A WEST HILLS, CA 91307 |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/17/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 5/24/2024 | Partial Approval | BOBBY KEY |
| Special/Order Compliance | 5/24/2024 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 6/3/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Deputy Wood Construction | 7/3/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 7/5/2024 | Not Ready for Inspection | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2024 | Not Ready for Inspection | BOBBY KEY |
| Footing/Foundation/Slab | 7/12/2024 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2024 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 7/16/2024 | Approved | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 7/16/2024 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 8/6/2024 | Approved | BOBBY KEY |
| Insulation | 8/6/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 8/6/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 8/8/2024 | Approved | REGINA MENDEZ |
| ELECTRICAL-Final | 9/26/2024 | Approved | BOBBY KEY |
| Final | 9/26/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 9/26/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 9/26/2024 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 9/26/2024 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 9/26/2024 | Corrections Issued | BOBBY KEY |
| Final | 11/27/2024 | OK to Issue CofO | BOBBY KEY |
| Smoke Detectors | 11/27/2024 | Approved | BOBBY KEY |