5833 W 78TH PL 90045

Certificate Information: 5833 W 78TH PL 90045

Application / Permit
22014-10000-01609
Plan Check / Job No.
B22LA06229
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
515 SF OF ADDITION TO EXISTING SINGLE FAMILY DWELLING AND NEW DECK
Permit Issued
Issued on 5/2/2024
Issuing Office
Valley
Current Status
CofO Issued on 12/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/8/2022 APPLICANT
Assigned to Plan Check Engineer 4/22/2022 VARAND SARKISIAN
Corrections Issued 4/26/2022 VARAND SARKISIAN
Building Plans Picked Up 4/27/2022 APPLICANT
Plan Check Approved 9/13/2022 VARAND SARKISIAN
Issued 5/2/2024 APPLICANT
CofO in Progress 11/27/2024 BOBBY KEY
Permit Finaled 12/3/2024 RICHARD STEINBACH
CofO Issued 12/3/2024 RICHARD STEINBACH
Permit Finaled 12/3/2024 RICHARD STEINBACH

Permit Application Clearance Information

Sewer availability Cleared 5/5/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 5/6/2022 DINAH GARIN
Hydrant and Access approval Cleared 5/28/2022 GILBERT URREA
Low Impact Development Cleared 8/9/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 8/25/2022 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 9/13/2022 VARAND SARKISIAN

Contact Information

Architect Bo, Kyle Sundius; Lic. No.: C38566       ,
Contractor M D H Builders / Design / Development; Lic. No.: 1067773-B 6700 FALLBROOK AVE 100A      WEST HILLS, CA 91307
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/17/2024 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 5/24/2024 Partial Approval BOBBY KEY
Special/Order Compliance 5/24/2024 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 6/3/2024 Corrections Issued TEMISTOCLES CAAL
Deputy Wood Construction 7/3/2024 Conditional Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 7/5/2024 Not Ready for Inspection JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 7/12/2024 Not Ready for Inspection BOBBY KEY
Footing/Foundation/Slab 7/12/2024 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 7/16/2024 Approved BOBBY KEY
Footing/Foundation/Slab 7/16/2024 Approved BOBBY KEY
Rough-Elec/Plmb/HVAC 7/16/2024 Approved BOBBY KEY
BUILDING-Rough-Frame 8/6/2024 Approved BOBBY KEY
Insulation 8/6/2024 Approved BOBBY KEY
Interior/Exterior Lathing 8/6/2024 Approved BOBBY KEY
Drywall Nailing 8/8/2024 Approved REGINA MENDEZ
ELECTRICAL-Final 9/26/2024 Approved BOBBY KEY
Final 9/26/2024 Corrections Issued BOBBY KEY
HVAC-Final 9/26/2024 Approved BOBBY KEY
PLUMBING-Final 9/26/2024 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 9/26/2024 SGSOV Approved BOBBY KEY
Smoke Detectors 9/26/2024 Corrections Issued BOBBY KEY
Final 11/27/2024 OK to Issue CofO BOBBY KEY
Smoke Detectors 11/27/2024 Approved BOBBY KEY