145 S ROBERTSON BLVD 90048
Certificate Information: 145 S ROBERTSON BLVD 90048
- Application / Permit
- 22014-10000-01599
- Plan Check / Job No.
- B22LA06205
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- TI to existing restaurant including remodel of existing kitchen, dining room, bathrooms, and outdoor eating area. Exterior work includes the relocation of and existing ramps, new raised entry platform, new exterior canopy at the entrance ramp.
- Permit Issued
- Issued on 12/2/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/1/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2022 | SALVADOR QUINTANILLA |
| Corrections Issued | 4/25/2022 | SALVADOR QUINTANILLA |
| Quality Review Completed | 4/27/2022 | KEN GILL |
| Building Plans Picked Up | 4/28/2022 | APPLICANT |
| Applicant returned to address corrections | 5/10/2022 | SALVADOR QUINTANILLA |
| Disabled Access Plans Picked Up | 5/19/2022 | APPLICANT |
| Applicant returned to address corrections | 6/7/2022 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 6/30/2022 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 10/25/2022 | SALVADOR QUINTANILLA |
| Plan Check Approved | 10/26/2022 | SALVADOR QUINTANILLA |
| Issued | 12/2/2022 | APPLICANT |
| Permit Finaled | 4/1/2026 | ERNESTO CORRAL |
| CofO Issued | 4/1/2026 | ERNESTO CORRAL |
| Permit Finaled | 4/1/2026 | ERNESTO CORRAL |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/5/2022 | JEANIE LAM |
| "Q" conditions | Cleared | 5/9/2022 | NOAH MCCOY |
| Comm Cor/Mini-Mall | Cleared | 5/9/2022 | ANACANY HURTADO |
| ZA Case | Cleared | 5/10/2022 | JASON CHAN |
| ZA Case | Cleared | 5/10/2022 | JASON CHAN |
| ZA Case | Cleared | 5/10/2022 | JASON CHAN |
| ZA Case | Cleared | 5/10/2022 | JASON CHAN |
| ZA Case | Cleared | 5/10/2022 | JASON CHAN |
| Miscellaneous | Cleared | 6/8/2022 | NOAH MCCOY |
| Sewer availability | Cleared | 7/21/2022 | JEANIE LAM |
| ZA Case | Cleared | 7/21/2022 | OMAR GALICIA |
| DAS Clearance | Cleared | 8/2/2022 | EDDIE GARIN |
| Food Service Establishment | Cleared | 8/17/2022 | KENNETH BROWNE |
| Food establishment approval | Cleared | 8/17/2022 | LACDHS APPROVED |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2022 | JEANIE LAM |
Contact Information
| Contractor | Ferrante Koberling Construction Inc; Lic. No.: 988562-B | 2360 EASTMAN AVENUE 112 OXNARD, CA 93030 |
| Engineer | Paniagua,, Cristobal; Lic. No.: C72894 | 1538 W 92ND ST LOS ANGELES, CA 90047 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/7/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Footing/Foundation/Slab | 4/12/2023 | Partial Inspection | ALFREDO LOPEZ |
| METHANE-Barrier | 4/12/2023 | Partial Approval | ALFREDO LOPEZ |
| METHANE-Subgrade | 4/12/2023 | Partial Approval | ALFREDO LOPEZ |
| Excavation/Setback/Form/Re-Bar | 4/13/2023 | Approved | ALFREDO LOPEZ |
| Footing/Foundation/Slab | 5/25/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| METHANE-Barrier | 5/25/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| METHANE-Subgrade | 5/25/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Footing/Foundation/Slab | 6/8/2023 | Partial Approval | JEROME BLACKWOOD |
| Green Building Rough | 6/8/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| METHANE-Barrier | 6/8/2023 | Approved | JEROME BLACKWOOD |
| METHANE-Rough | 6/8/2023 | Approved | JEROME BLACKWOOD |
| METHANE-Subgrade | 6/8/2023 | Approved | JEROME BLACKWOOD |
| Wood Frame | 6/8/2023 | Corrections Issued | JEROME BLACKWOOD |
| Green Building Rough | 6/16/2023 | Partial Inspection | JEROME BLACKWOOD |
| Wood Frame | 6/16/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Footing/Foundation/Slab | 6/30/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Footing/Foundation/Slab | 7/13/2023 | Partial Approval | JEROME BLACKWOOD |
| Footing/Foundation/Slab | 7/17/2023 | Partial Approval | JEROME BLACKWOOD |
| Green Building Rough | 7/21/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Wood Frame | 7/21/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Green Building Rough | 7/25/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Insulation | 7/25/2023 | Partial Approval | ALFREDO LOPEZ |
| Wood Frame | 7/25/2023 | Partial Approval | ALFREDO LOPEZ |
| Excavation/Setback/Form/Re-Bar | 9/7/2023 | Partial Approval | JEROME BLACKWOOD |
| Excavation/Setback/Form/Re-Bar | 9/29/2023 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 10/18/2023 | Partial Approval | RICARDO ROBLES |
| Green Building Rough | 10/20/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Wood Frame | 10/20/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Green Building Rough | 10/30/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 10/30/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Green Building Rough | 11/3/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Wood Frame | 11/3/2023 | Partial Approval | JEROME BLACKWOOD |
| Green Building Rough | 11/16/2023 | Partial Approval | RICARDO ROBLES |
| Wood Frame | 11/16/2023 | Partial Approval | RICARDO ROBLES |
| Green Building Rough | 12/1/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Interior/Exterior Lathing | 12/1/2023 | Partial Approval | ALFREDO LOPEZ |
| Drywall Nailing | 12/4/2023 | Partial Approval | RICARDO ROBLES |
| Insulation | 12/4/2023 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 12/6/2023 | Partial Approval | ALFREDO LOPEZ |
| Interior/Exterior Lathing | 12/11/2023 | Approved | ALFREDO LOPEZ |
| T-Bar Ceiling | 1/16/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Final | 12/11/2025 | Not Ready for Inspection | CHRISTOPHER BLACKWOOD |
| Footing/Foundation/Slab | 12/11/2025 | Approved | CHRISTOPHER BLACKWOOD |
| Green Building Final | 12/11/2025 | Not Ready for Inspection | CHRISTOPHER BLACKWOOD |
| Green Building Rough | 12/11/2025 | Approved | CHRISTOPHER BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 12/11/2025 | SGSOV Approved | CHRISTOPHER BLACKWOOD |
| Smoke Detectors | 12/11/2025 | Approved | CHRISTOPHER BLACKWOOD |
| Wood Frame | 12/11/2025 | Approved | CHRISTOPHER BLACKWOOD |
| Final | 3/12/2026 | Partial Approval | IAN BLINN |
| Green Building Final | 3/12/2026 | Approved | IAN BLINN |